Loading...
HomeMy WebLinkAbout8.a. City Projects UpdateCity Project NumberProject NameCouncil Authorizes Plans/SpecsPublic HearingCouncil Receives Plans/Specs Authorize Ad For BidOpen BidsAward ContractStart DateAssessment HearingContractorContract AmountWork Certified To-Date% CompleteSummary416 Well 16 10/01/13 N/A 11/18/14 02/27/15 03/17/15 05/26/15 N/AE.H. Renner & Sons, Inc.$433,105 $380,658 88% Drilling of the production well is complete. Well house design is underway, with construction anticipated in 2017.447145th Street Pedestrian Improvements at RR Crossing01/02/13 N/A N/AUPRR, CPRR, TBDAgreement already in place with Union Pacific. Easement Agreement signed by Canadian Pacific. An agreement with CP for the track extensions can be established now that the easement agreement has been executed. Upon execution of the agreement with CP for the track extensions, work will begin. Sidewalk work will begin after railroad work.453Danbury Way Reconstruction07/21/15 07/21/15 01/19/16 02/19/16 04/19/16 June 2016 04/19/16McNamara Contracting$1,244,198 $1,305,103 105% Project is complete.465132nd Street West ImprovementsN/ACouncil received the feasibility report and assessment agreement on October 6, 2015. This project is on hold until the status of the Dunmore project is determined.466Horseshoe Lake Lift Station05/05/15 N/A 08/18/15 09/04/15 09/15/15 10/19/15 N/ARyan Contracting$667,284 $667,284 100% Project is substantially complete. Lift station is online and running. Punch list items remain.467Dunmore 1st AdditionN/AThis development includes 30 single-family homes by developer Copper Creek. Copper Creek is expected to administer the contract privately, but the project is temporarily on hold. A subdivision agreement is being reviewed by attorneys from both parties.4702017 Street Improvement Project12/20/16 05/02/17 02/21/17 03/24/17 05/02/17 06/01/17 05/02/172017 Street improvement project includes pavement reconstruction of Shannon Parkway from CSAH 42 to CSAH 46, and mill and overlay of the Shannon Hills neighborhood (Cobbler Ave, Crocus Way, Cranberry Way, Clover Lane). Bids will be opened March 24, 2017. 473Prestwick Place 13thN/A N/A N/AThis development includes 28 single-family homes by developer KRB Development I, Inc. Sidewalks and wear course will be completed Spring 2017. 474 Greystone 5th N/A N/A N/AThis development includes 23 single-family homes by developer CalAtlantic Homes (formerly Ryland Homes). The developer will administer the contract privately. Construction is expected to begin Spring 2017. 475 Bella Vista 5th N/A N/A N/AThis development includes 41 single-family homes by developer US Home Corporation (Lennar). The developer will administer the contract privately. Construction is expected to begin Spring 2017. 476Rosewood CommonsN/A N/A N/A This development includes 7 apartment buildings. The project will be designed and constructed privately. Schedule is still TBD.ENG-181Wells 4 & 5 Sealing, New Observation WellN/A 09/01/15 09/29/15 11/17/15 On Hold N/AKeys Well Drilling$39,250 $31,750 81%Well 4 has been converted to an observation well but does not yet have the logger installed. Well 5 has been drilled out, ready to be sealed in the future. Final payment was authorized by Council on October 18, 2016.470 ENG-186 ENG-188Parking Lot MaintenanceN/A N/A N/A N/A N/ASpring 2017N/AConnemara Park, Jaycee Park, and City Hall parking lots are scheduled for maintenance in 2017. Improvements will include curb & gutter enhancements/replacement, as well as full pavement replacement. Connemara Park and City Hall will be bid together as one project. Jaycee Park will be included in the contract of the 2017 Street Improveent Project.2017-01 Greystone 6th TBD N/A TBD TBD TBDSummer 2017N/AThis development includes 27 single-family homes by developer CalAtlantic Homes (formerly Ryland Homes). The project will be a public city project. Schedule is still TBD. Construction is expected to begin Summer 2017. 2017-02 Harmony Villas N/A N/ASummer 2017N/AThis development includes 42 quad/side-by-side townhomes in the Harmony neighborhood. The project will be designed and constructed privately. Construction is expected to begin Summer 2017. PRIVATEPRIVATEPRIVATEPRIVATEPRIVATEPRIVATEPRIVATECity Projects UpdatePRIVATEPRIVATEPRIVATEPRIVATEPRIVATEG:\ENGPROJ\Project Tracking\Project UpdateUpdated: 3/17/2017