HomeMy WebLinkAbout8.b. Community Center ReportCITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
PORT AUTHORITY COMMISSION MEETING DATE: MARCH 2, 1993
AGENDA ITEM: MULTI-PURPOSE ARENA/
AGENDA
SECTION:
PROJECT UPDATE
EXECUTIVE DIRECTOR'S RPT
PREPARED BY: STEPHAN JILK,
CITY ADMINISTRATOR
AGENDA
■ A
`) # 8B
ATTACHMENTS: MEMO
AP
This will be a verbal report on the status of the Armory and Community
Center project as it relates to the construction of the facility, the
decision City Council has made relating to the operation of the facility,
the completion date of the arena portion of the project and a general
progress report.
Please review the attached update report for specifics and I will attempt
to verbally provide you with additional information pertinent to this
project.
RECOMMENDED ACTION: None at this time.
PORT AUTHORITY ACTION:
ROSEMOUNT COMMUNITY CENTER UPDATE
MARCH, 1993
REPORT #3
FROM: STEPHAN JILR, CITY ADMINISTRATOR
Construction
Construction is proceeding _along well. Work is actually a bit
ahead of schedule. Please refer to the attached drawing. Lower
level walls are complete in the Phase I area on the west, north and
east sections. Footings have been poured in Phase 2B (Armory North
and footings are to be poured in the Community Center (Phase 2A)
the week of March 1. That footing schedule is almost a month ahead
of time based on the existing schedule.
Structural steel for the lower level of Phase I should be on site
next week.
No delays on the work schedule have been experienced.
Proiect Schedule
Please refer to the schedule (attached) provided to you on February
2, 1993. This schedule has not been changed and is still based on
an arena completion of December 15, 1993_
Project Completion Move Un
In our request to receive a cost estimate to move up the completion
date of the Arena to December 15, 1993 the contractor had provided
a cost estimate of $51,000 based on the additional cost put
together by the subcontractors. These costs have been challenged
and the cost increase estimate of $7,000 to $10,000, put together
by our cost analyst has been provided to the contractor.
I have conducted a cost analysis of the revenue and expenses
related to the operation of the arena to determine what our break
even point would be in deciding whether to move ahead with a "move
up" completion of the Arena. Based on this review it is apparent
that based on our budget used to develop financing for the project
we would experience the following:
1) Weekly revenue of $7,973.
2) Weekly operating expense of $3,790
3) Net Revenue for each week of $4,183
4) To cover an additional cost of $51,000 would take 12 weeks to
recover
5) To cover our additional cost of $10,000 would take 2.4 weeks
to recover.
6) We are looking to move the schedule up by some seven weeks so
we could expect a net income of $29,281 difference between a
completion of Feb. 4 and Dec. 15
Rosemount Community Center Update
Page 2
7) If the Arena is not open until Feb. 4th we may experience a
greater loss than seven weeks net revenue because some ice
users may not be willing to book ice at all in 1993-1994 if
they can't get in earlier - that is they may likely just go
to another arena for the season. So our actual "net loss may
be greater than just a seven week net. That cannot be
determined until we experience it.
At this time the contractor is reviewing our cost analyst's numbers
and on Monday, March 1, we will be meeting with him and
representatives of all subcontractors, the architect and the cost
analyst. We should have a final cost for consideration by Tuesday
evening. I believe, at this time, based on our cost analyst's
numbers and the fact that the project is slightly ahead of schedule
now that we should be able to get the December 15th completion date
with a cost that is acceptable.
Jan. 1993
February
March
April
ARMORY SCHEDULE
Construction - Building
Construction — Utilities
Water, no activity
- Sewer, no activity
- Highway 3 Improvements - plans being made
Relocation - Port Authority approves quick take of
properties
Port Authority receiving/reviewing relocation
payment requests
Staffing Consider alternates for Administration
Construction - Building
- Consider "move up" schedule
- Construction Continues
Construction - Utilities
- Water, no activity
- Sewer, no activity
Storm, Plans being made
- Highway 3, Plans being made
Relocation - Schedule Public Hearing for Quick Take
- Continue to negotiate for purchase/relocation
Staffing Approve facility management structure
Authorize Hiring of Manager
Construction - Building
Start up for 'move up" schedule
- Construction Continues
Construction - Utilities
- Water, no activity
- Sewer, no activity
- Storm, Complete design, advertise for bids
- Highway 3, Complete design, authorize bids
Relocation — Continue to negotiate for purchase/relocation
- Demolition Bid/Specs developed
Staffing Accept applications for Manager Position
- Select applicants for interview
Construction - Building
- Construction Continues
Construction - Utilities
- Water, work continues
- Sewer, work continues
- Storm, Construction Contract Awarded
- Highway 3, No activity
1
(April cont) Relocation
Staffing
Relocations concluded
- Property is officially acquired
- Advertise for Demolition of Properties
- Conduct Interviews
May Construction
- Building
- Construction Continues
Construction
- Utilities
- Water, Construction Continues
- Sewer, Construction Continues
- Storm, construction begins
- Highway 3, Construction Contract Awarded
Relocation
- Demolition of properties on Hwy 3 Begins
Staffing
- Manager Hired
June Construction
- Building
- Construction Continues
Construction
- Utilities
- water, complete
- Sewer, complete
- Storm, complete
- Highway 3, Construction Begins
Relocation
— Demolition complete
Staffing Other facility staff designated
July Construction
- Building
- Construction Continues
Construction
- Utilities
- Water, complete
- Sewer, complete
- Storm, construction continues
- Highway 3, Construction Begins
Relocation
- Completed
Staffing
- Advertise for other facility staff positions
August Construction
- Building
- Construction Continues
Construction
- Utilities
- Water, complete
- Sewer, complete
- Storm, construction continues
- Highway 3, construction continues
Relocation
- Completed
Staffing
- Applications received and interviews held for
other positions
2
September
Construction -
Building
-
Construction Continues
Construction -
Utilities
-
Water, complete
-
Sewer, complete
-
Storm, construction continues
-
Highway 3, complete
Relocation -
Completed
Staffing -
Other facility full-time staff hired
October
Construction -
Building
-
Construction Continues
Construction -
Utilities
-
Water, complete
-
Sewer, complete
-
Storm, construction continues
-
Highway 3, complete
Relocation -
Completed
Staffing
- All facility full-time staff hired
November
Construction
- Building
-
Construction Continues
Construction
- Utilities: Completed
- Water
- Sewer
- Storm
- Highway 3
Relocation
- Completed
Staffing
- Complete Hiring
December
Construction
- Building
- Arena Open for Operation
- Construction on remainder continues
Construction
- Utilities - Completed
Relocation
- Completed
Staffing
- Completed Hiring
Jan. 1994
Construction
- Building
- Construction Continues
February
Construction
- Building Completed
- Entire Facility Grand Opening
3
Rosemount Armory/Community Center
1993 1994
(Shaded area shows start of project to finish)