CITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: December 7, 1993
AGENDA ITEM: Change Order #1, Shannon Hills 5th
AGENDA SECTION:
Addition, City Project #243
Consent
PREPARED BY: Bud Osmundson
AGENDA
City Engineer/Assistant Public Works Director
ATTACHMENTS: Change Order #1
APPR VED Y:
7
This item is a request for Council to consider Change Order #1 for City Project #243, the
construction of streets and utilities for the Shannon Hills 5th Addition.
The contractor had two items which added to the contract cost. The first was a
requirement to clean storm sewer catch basins in the Shannon Hills 3rd Addition due to
extraordinary run-off of the open grading site of the 5th Addition. Total cost of this item
was $440.00. The second item was additional sub -grade excavation and placement of
granular material and aggregate required to stabilized the sub -grade prior to the
installation of bituminous. The total cost of this work was $5,938.37. The total cost of
the Change Order then was an increase to the contract in the amount of $6,378.37. The
Developer, Ground Development, has been informed of these additional costs and has
approved them.
Staff recommends approval of this Change Order.
RECOMMENDED ACTION: MOTION TO APPROVE CHANGE ORDER #1, SHANNO
5TH ADDITION STREET AND UTILITY IMPROVEMENTS, CITY PROJECT #243.
COUNCIL ACTION:
F " Orr
Schelen 300 Park Place Center 612-595-5775 Change Order
Mayeron & 5775 Wavzata Boulevard 1-800-753-5775
Associates, Inc. Minneapolis, AIN 55416-1228 FAX 595-5774
Change Order No. 1 City Project No. 243
Project: Shannon Hills Fifth Addition OSM Project No. 5096.00
Owners: City of Rosemount
Date of Issuance: November 19, 1993
2875 - 145th Street West
Rosemount, MN 55068
Contractor: S. J. Louis Construction, Inc.
Engineer: Orr-Schelen-Mayeron & Associates,
P.O. Box 1373
Inc.
St. Cloud, MN 56302
5775 Wayzata Boulevard
Minneapolis, MN 55416
You are directed to make the following changes in the Contract Documents:
Description:
1. Clean storm sewer catch basins located on Shannon Hills 3rd Addition.
Total Cost: $440.00
2. Additional subgrade excavation, granular material and 3" aggregate required to stabilize
roadway subgrade prior to installing bituminous.
Total Cost: $5,938.37
Total Cost Change Order No. 1: $6,378.37
Attachments (list documents supporting change): N/A
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIME
Original Contract Price:
Original Contract Time:
$192,161.55
N/A
Previous Change Orders No. _ to No. _:
Net Change from Previous Change Orders:
$ -0-
N/A
Contract Price Prior to this Change Order:
Contract Time Prior to this Change Order:
$192,161.55
N/A
Net Increase of this Change Order:
Net Increase (decrease) of Change Order:
$6,378.37
N/A
Contract Price with all Approved Change Orders:
Contract Time with Approved Change Orders:
$198,539.92
N/A
Recommended
Approved
By:
By:
Contractor
Engineer
Approve
Approved
Date of Council Action
By: `� -; ��_
By:
City Engineer
City Manager
Engineers • Architects • Pianners • Surveyors