HomeMy WebLinkAbout7.c. Order Feasibility Report for 145th Street West Street Reconstruction, 2nd PhaseCITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: June 2, 1992
AGENDA ITEM:
Order Feasibility Report for
AGENDA SECTION:
145th Street
West Reconstruction, 2nd Phase
New Business
PREPARED BY:
Public Works
Ron Wasmund
AGEND I -N&' 17
Director/Building Official"
ATTACH. TS:
Resolution
APP VE Y:'
This item consists of adopting the attached resolution for the
ordering of a feasibility study for the construction of 145th Street
West between Shannon Parkway and ChippendaleAvenue.` This is the
first step in the preparation for this phase of 145th Street
Reconstruction, which is anticipated and proposed to occur in 1993.
This phase of the project will include the realignment of
Chippendale/Chili intersection; some reconstruction of Chili to
accomplish the realignment; treatment of Dodd Boulevard at the
intersection with Chippendale; possibly some reconstruction of
Cimarron; all new utilities; surfacing and 'curb and gutter on 145th
Street West.
The project will also require negotiations for the acquisition of land
currently occupied by the old Carroll farm.
Portions of the cost of the project will be recovered through
assessments, the balance will come from respective core accounts.
There could be some extraneous costs associated with this project,
such as the Carroll acquisition. The feasibility report will identify
all of the costs and methods' ofrecovery.
Because of the magnitude of the various components we need additional
time to study and make recommendations.
The original feasibility study that was prepared for the full length
of 145th Street from Cameo to Diamond Path addresses some of the
particulars, but needs refinement. Since OSM did the original`
feasibility and would have the background information�it is our
recommendation to have them prepare this updated report.
RECOMMENDED ACTION: MOTION TO ADOPT A RESOLUTION ORDERING AN UPDATED
FEASIBILITY REPORT FOR 145TH STREET RECONSTRUCTION BETWEEN SHANNON
PARKWAY AND CHIPPENDALE AVENUE, 2ND PHASE.
COUNCIL ACTION:
2
CITY OF ROSEMOUNT
RESOLUTION 1992 -
A RESOLUTION ORDERING AN UPDATED FEASIBILITY REPORT FOR
145TH STREET RECONSTRUCTION BETWEEN
SHANNON PARKWAY AND CHIPPENDALE AVENUE, 2ND PHASE
CITY PROJECT # 235
WHEREAS, the City Council of the City of Rosemount deems it necessary to
investigate the update of the feasibility of 145th Street West Reconstruction, 2nd
Phase, City Project #235.
NOW THEREFORE BE IT RESOLVED, the City Engineer is directed to have the
necessary feasibility report prepared by the Consulting Engineering firm of OSM, Inc.
for 145th Street West Reconstruction, 2nd Phase, City Project #235.
ADOPTED this 2nd day of June, 1992.
E. B. McMenomy, Mayor
ATTEST:
Susan M. Walsh, City Clerk
Motion by:
Voted in favor:
Voted against:_
Seconded by: