HomeMy WebLinkAbout4.o. Pament for Jaycee Park GradingCITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: JANUARY 21, 1992
AGENDA ITEM: CITY PROJECT #223
AGENDA SECTION:
JAYCEE PARK PROJECT
# 91-9
CONSENT
PREPARED BY: DAVID J. BECHTOLD,
DIRECTOR OF PARKS &
RECREATION
AGEM.µ
N
4
7i'
ATTACHMENTS: PAY VOUCHER #4
OVED BY:
v
The grading contract #91-9 for Jaycee Park was for the amount of $37,500
with the firm of Ryan Contracting, Inc.. Our consultants of OSM have
submitted pay voucher#4 for work completed at this time.
The payment of $3,800.00 will come from account #202-24413.
The amount of the voucher is $3,800.00.
With this payment we will have paid a total of $34,627.50 towards the
contracted work.
RECOMMENDED ACTION:
Motion to approve the payment to Ryan Contracting, Inc. for the amount
of $3,800.00 as per Pay Voucher #4 of Park Project -#91-9, City Project
#223.
COUNCIL ACTION!
project Kane or Item Kane:
Project Number or Item Kane A et iption: t
/ f t ! f
Total Estimated Costs:E-E
_... r::. ---�x�•K.:; ::
Department/Person Submitting Proposal: ( ) is (ACM t IF APPLICABLE) ;
FunFunding Fron: 1 '
- _ � .. • : : ... _ .: ..
1) Assessments:
2) Nater Core (Fund 605).
-'�. _.... ..: --(Fund 606):
3) Sanitary Sever Core 1
4) Storm Sever Core (Fund 607'): 1
5) MSA Funds (Fund 203):
6) 5 -Year CIP Funds (Fund 202): 5
� 1
7) Mater/Sever CIP Fund (603): 1
8) General Levy: 1
5 i
g) EDA Funds (Fund 201) i
10) Park Improvement Funds (Fund 205) 1
11) General Operating Budget (Fund 101) 5 i
(Any item over $250.00) i
12) Nater/Sever Operating Budget: 5
L
(Fund 601 or 602) 1
(Any item over $250.00) 5
13) Other Funds: 1
cap, s� 1 -�
Total Funding —�
(Should Equal. Estimated Costs) ---- ------
Department Reviev-and Acknowledgment:
RASE
TITLE DATE_
Finance:
P. lit. /Building Dept:
Parks i Recreation:'L --
Planning Department:
Police:
------------
Fire:
Submitted to Administration for approval on ' f (Signature)
(Date)
Submitted to Council for approval on:
Approved by Council on:
Page 2 Expenditure Worksheet (For Project or Item Listed Above)
1) Accounting/Auditing Fees (301)
Year Cost
Incurred
Estimated
Cost
Account to Ust
2) Architect Fees (302)
3) Engineering Fees (303)
4) Legal Fees (304)
5) Professional Services (310 or 319)
6) Legal notices (351)
7) Easement Costs (510 -usually)
n1 e
GU
8 ) Construction Costs (530 -usually)
p�
C, 7 -S0
1,3a --� V V/
�
a
9) Miscellaneous (???)
10) Continoencies (???)
11) Administrative Fees (Trans to 101)
12) Equipment/Item Costs (500 Series)
13) Other
Total Costs (Must Equal Total
Funding From Previous Page)
PURCHASE ORDER
Minn. Tax Exempt Status No. 9757275 16119
Fed. Tax No. 41-6005501 cotly Of 90semouni
2875145th Street West - PO Box 51?ePD
t
Phone (612) 423-4411 -,vf
Rosemount, MN 55068-4997 aO�Dir.
9IMPORTANT
ABO ORDIR UMBER MUST APPEAR ON ALL CORRESPON-
/► /� NCE, INVOICES, PACKAGES AND SHIPPING PAPERS. NOTIFY
To �/ _/ /, USIMMEDIATELYERBySIF YOU ARE UNABLE TO SHIP COMPLETE
ORDER SY DATE SPECIFIED. YOUR ACCEPTANCE THIS ORDER'
` IS YOUR WARRANTY TO US THAT YOU ARE COMPLYING WITH THE
U.S. FAIR LABOR STANDARDS ACT IF 1938. AS AMENDED. AND WE
/► RESERVE THE RIGHT TO REFUSE MERCHANDISE NOT IN STRICT
ACCORDANCE WITH THIS ORDER.
DATE DATE REQUIRED TERMS SHIP VIA F.O.B. REOUISITlON NO.
s-
QNUW ' DESCRIPTION STOCK NUMBER x;' PRICE .' r AMOUNT
f
l
T1L.Y[Va�V.• -• ivevu�-a .. .+.—�..,...�.. ... .�_. - - �177..i[��/J>•�'�iil�`���
White: Original Yellow: Duplicate Pink: Triplicate Gold* Quadruplicate
Orr
Schelen
Mayeron &
Associates, Inc.
2021 East Hennepin Avenue
Minneapolis, MN 55413
612-331-8660
FAX 331-3806 Engineers
Architects
Planners
Surveyors
January 9, 1992
City of Rosetount
2875 - 145th St. Rest
Rosetount, Minnesota 55068
Re : Jaycee Park - Phase II Grading
City Project No. 223 - Park Project No. 91-9
OSK Cote. No. 4804
City Council
Enclosed are four (4) copies of Construction Paytent Voucher No. 4 on the referenced project in the atount of
S 31800.00.
Please take paytent in atount of S 3,800.00 to Ryan Contracting, Inc., 1534 E. Cliff Rd., Burnsville, Mn. 55337
at your earliest convenience.
Very truly yours,
ORR-SCHELEN-MAYERON
& ASSOCI TES, INC.
Oov-a�
C. Oseundson,P.E.
Project Engineer
HCO:RGD
Enclosures :
cc : Ryan Contracting, Inc.
Equal Opportunity Employer
Estivate Voucher No. 4
Date January 9, 1992
Jaycee Park - Phase II Grading
City Project No. 223 - Park Project No. 91-9
for the
City of Rosemount, Minnesota
Contractor Ryan Contracting, Inc.
1534 E. Cliff Rd.
Burnsville, Mn. 55337
-Ph (612) 894-3200
Fax (612) 894-3207
Contract Date
:
Mork Started
Completion Date : October 15, 1991
Work
Completed
:
Work Completed
Contract
This Amount
Total
to Date
Item
No.
Item
Quantity
Unit
Unit Price Total Price
nonth This Month
Quantity
Total Price
1)
2101.5fl2M
----
Clearing - N
-------------------------------------------
14
Tree
25.00 350.00
0.00
0.00
15
15
375.00
375.00
2 )
3
2101.501
2105.501
Clubbing
Conon Excavation (Plan quantity)
14
15500
Tree
C.Y.
25.00 350.00
1.60 24,800.00
0.00
15,500
24,800.00
)
4)
2573.503
Erosion Control - Silt Fence
1500
L.F.
1,00 1,500.00
0.00
3.2 4,000.00
1,900
7.2
1,900.00
9,000.00
5 )
2575.541
Seeding
8
Acre
1,250.00 10,000.00
0.00
6)
2575.523
Fiber Blankets, Type Regular
500
S.Y.
1.00 500.00
f 37,500.00
s 4,000.00
s
36,450.00
Total
Total to Date S 37,500.00
Page 2 of 2 - 4904
S 4,000.00 s 36,450.00
Estimate Voucher No. 4
CONSTRUCTION PAYMENT
VOUCHER
Date
-------------------------
January 9, 1992
For
Period Ending : December 31,
1991
Project No.
: City Project No. 223
- Park Project
No. 91-9
Class of Work : Jaycee Park - Phase
11 Grading
—
------------------ — - — —
------- —---
To : Ryan Contracting, Inc.
----------- ----------------------------------
1534 E. Cliff Rd.
Location
Burnsville, Mn. 55337
-------------- -----------------
N -----------------
Ph (612) 894-3200
For
City of Rosemount, Minnesota
Fax (612) 694-3207
A.
Original Contract Amount
f
37,500.00
B.
Total Additions
f
0.00
C.
Total Deductions4
0.00
D.
Total Funds Encumbered
t
37,500.00
E.
Total Value of Work Certified to
Date
f
----------------------
36,450.00
F.
Less Retained Percentage
5- . 1
f
1,822.50
G.
Less Total Previous Payments
------------
3
----------------------
.30,821.50
H.
Total Payments including This Voucher
S
34,627.50
I.
Balance Carried Forward
f
2,672.50
J.
APPROVED FOR PAYMENT,
THIS
VOUCHER
f
----------------------
3,800.00
APPROVALS
ORR-SCHELEN-MAYERDN t ASSOCIATES, INC.
Pursuant to our field observation, as performed in accordance with our contract, and based on our professional opinion,
materials are satisfactory and the work properly performed in accordance with the plans and specifications and that the
total work is 97 1 completed as of December 31, 1991 . We hereby recommend pay ent'of this voucher.
JSigned . Signed .------------------ -------------------
Construction Observer
-------------------------------------------------------------------------
This is to certify that to the best of my knowledge, information, and belief, the quantities and values of work
certified herein is a fair approximate estimate for the period covered b
Contractor : Ryan Contracting, Inc. Sign
------------------------------------
Date Title 4
------- -- --
City of Rosemount Approved for payment
Voucher------------------------------------ ------
Checked By : Authorised Representative
------------------------------------ Date _ / "(�''.1c—a --------------
Date . ---- --------------- ---
Page 1 of 2 4904