HomeMy WebLinkAbout5.a. Receive Feasibility / Set Public Hearing, Country Hills 4th Addition , City Project #222CITY OF ROSEMOUNT EXECUTIVE SUMMARY FOR ACTION CITY COUNCIL MEETING DATE: June 4, 1991 AGENDA ITEM: Receive Feasibility/Set Public AGENDA SECTION: Hearing, Country Hills 4th Addition, Prj 222 Old Business PREPARED BY: Ron Wasmund AGENDA INS n n # 5 A Public Works Director/Building Official L��) H ATTACHMENTS: (2) Resolutions, Hearing Notice AP OVED Y: / Mailing List Attached are copies of resolutions receiving the feasibi ity report for Country Hills 4th Addition public improvements and calling for a public hearing on said improvements. Staff is recommending the public hearing be held on June 18, 1991 at 8:00 P.M. OSM, the consulting engineers on the project, will have the feasibility report to us on Monday. As soon as we receive it we will deliver it to you. RECOMMENDED ACTION: MOTION TO ADOPT A RESOLUTION RECEIVING THE FEASIBILITY REPORT, COUNTRY HILLS 4TH ADDITION STREET AND UTILITY IMPROVEMENTS, CITY PROJECT #222. MOTION TO ADOPT A RESOLUTION CALLING FOR A PUBLIC HEARING,COUNTRY HILLS 4TH ADDITION STREET AND UTILITY IMPROVEMENTS, CITY PROJECT #222. COUNCIL ACTION: 3 Country Hills 4th Addition Tentative Development/Approval Schedule JUNE 4, 1991 - Accept Feasibility Study - Set Public Improvement Hearing Date - Review 4th Addition Final Plat/PUD Amendment JUNE 18, 1991 - Hold Public Improvement Hearing Approve 4th Addition Plans & Specifications Authorize Advertisement for Bids Approve 4th Addition Final Plat/PUD Amendment JUNE 20-21, - Bid Notice Publications 1991 JULY 11, 1991 - Open Bids JULY 16, 1991 - Award Bid JULY 25-31, - Sign Contract/Notice to proceed 1991 - Pre -construction Meeting (JULY - Site grading by Developer) (AUGUST - OCTOBER - Public Improvements by City) CITY OF ROSEMOUNT DAKOTA COUNTY, MINNESOTA RESOLUTION 1991 - A RESOLUTION RECEIVING THE FEASIBILITY REPORT COUNTRY HILLS 4TH ADDITION STREET & UTILITY IMPROVEMENTS CITY PROJECT #222 WHEREAS, the City Council deemed it necessary and expedient that the City of Rosemount, Minnesota, construct certain improvements, to -wit: City Project #222, Country Hills 4th Addition Street & Utility Improvements, in the City as described in and in accordance with the feasibility report prepared by Orr-Schelen-Mayeron & Associates, Inc., Consulting Engineers; and WHEREAS, the City Council has been advised by the Consulting Engineers that said utility and street improvements, City Project #222, is feasible, and should best be made as proposed, and the Consulting Engineers' report to this effect has heretofore been received by Council, and filed with the City Clerk on June 4, 1991; and NOW THEREFORE BE IT RESOLVED, the City Council of the City of Rosemount accepts the feasibility report for City Project #222 and places it on file. ADOPTED this 4th day of June, 1991. ATTEST: Susan M. Walsh, City Clerk Motion by: Vote in favor: Vote against: Vernon J. Napper, Mayor Seconded by: CITY OF ROSEMOUNT DAKOTA COUNTY, MINNESOTA RESOLUTION 1991 - A RESOLUTION CALLING FOR A PUBLIC HEARING COUNTRY HILLS 4TH ADDITION STREET & UTILITY IMPROVEMENTS CITY PROJECT #222 WHEREAS, the City Council received the feasibility report and found the project feasible for Country Hills 4th Addition Street & Utility Improvements, City Project #222, on the 4th day of June, 1991; and WHEREAS, the statute provided that no such improvements shall be made until the Council has held a public hearing on such improvements following mailed notice and two publications thereof in the official newspaper stating time and place of the hearing, the general nature of the improvement, the estimated costs thereof, and the area proposed to be assessed, in accordance with the law; and NOW THEREFORE, BE IT RESOLVED by the City Council of the City of Rosemount, Minnesota, as follows: 1. A public hearing will be held at the time and place set forth in the Notice of Hearing attached hereto as Exhibit A to consider said proposed improvements. 2. The nature of the improvements, the estimated cost of each major portion thereof, and the areas proposed to be assessed therefor are described in the form of Notice of Hearing hereto attached. 3. The notice of said public hearing shall be in substantially the form contained in the notice hereto attached. 4. The City Clerk is hereby authorized and directed to cause notice of said hearing to be given two publications in the official newspaper. Said publications shall be one week apart, and at least three days shall elapse between the last publication and the hearing. Not less than ten days before the hearing the Clerk shall mail notice of the hearing to the owner of each parcel of land within the area proposed to be assessed as described in the notice. For the purpose of giving such mailed notice, owners shall be those shown to be such on the records of the County Auditor or, if the tax statements in the County are mailed by the County Treasurer, on the records of the County Treasurer. As to properties not listed on the records of the County Auditor or the County Treasurer, the Clerk shall ascertain such ownership by any practicable means and give mailed notice to such owners. ADOPTED this 3th day of June, 1991. ATTEST: Susan M. Walsh, City Clerk Motion by: Voted in favor: Voted against: Vernon J. Napper, Mayor Seconded by: 2 'EXHIBIT Atl CITY OF ROSEMOUNT DAKOTA COUNTY, MINNESOTA PUBLIC NOTICE NOTICE OF PUBLIC HEARING ON IMPROVEMENTS COUNTRY HILLS 4TH ADDITION STREET & UTILITY IMPROVEMENTS PROJECT NO. 222 TO WHOM IT MAY CONCERN: NOTICE IS HEREBY GIVEN, that the City Council of the City of Rosemount, Minnesota, will meet at 8:00 o'clock p.m. or as soon thereafter as possible, Tuesday, June 18, 1991, in the Council Chambers of the City Hall, 2875 145th Street West, to consider the following improvements: Project #222 - Country Hills 4th Addition Street & Utility Improvements The nature of improvements shall include the construction of street construction, trailway, watermain, sanitary sewer, storm sewer, curb and gutter. The total estimated cost of said improvements is $252,130. The total assessment cost of said improvements is $252,130. The area proposed to be assessed for the foregoing improvements would generally be all that area generally described as that part of the East One Half of the Southwest Quarter of Section 19, Township 115, Range 19, Dakota County, Minnesota and the Southeast Quarter of said Section 19 except the East 2,000 feet thereof, lying North of Country Hills 3rd Addition, according to the recorded plat thereof, said Dakota County. Together with: The South 400 feet of the Northwest Quarter of Said Section 19. Together with: The East 275 feet of the North 950 feet of the South 1,350 feet of said Northwest Quarter. Together with: The South 1,350 feet of the Northeast Quarter of said Section 19 except the East 2,000 feet thereof: Except: That part of said South 1,350 feet except said east 2,000 feet thereof, described as follows: Commencing at the southeast corner of said parcel; thence North 1 degree 12 minutes 41 seconds West, along said west line of said east 2,000 feet a distance of 200.02 feet to the point of beginning of the parcel to be described; thence continuing North 1 degree 12 minutes 41 seconds West 992.52 feet; thence South 29 degrees 17 minutes 56 seconds West 116.12 feet; thence southerly 522.25 feet along a tangential curve, concave to the east having a central angle of 47 degrees 29 minutes 47 seconds and a radius of 630.00 feet; thence South 18 degrees 11 minutes 52 seconds East 406.31 feet to the point of beginning. Such person as desires to be heard with reference to the proposed improvements will be heard at this meeting. Written or oral opinions will be considered. Dated this 4th day of June, 1991. BY ORDER OF THE CITY COUNCIL. Susan M. Walsh City Clerk City of Rosemount Dakota County, Minnesota Fd MAILING LIST FOR COUNTRY HILLS 4TH ADDITION PUBLIC HEARING - JUNE 18, 1991 - 8:00 P.M, U. S. Home Corporation 300 Hwy 169 Suite 870 St. Louis Park, MN 55426 Feasibility Report for Country Dills Fourth Addition Utilities and Street Improvements City Project No. 222 For the 1011 �i osem.ount P.O. Box 510 0 2875 - 145th Street W. Rosemount, Minnesota 55068 III OSM Comm. No. 4 June 1 FEASIBILITY REPORT COUNTRY HILLS FOURTH ADDITION CITY PROJECT NO. 222 ROSEMOUNT, MINNESOTA JUNE 4, 1991 I hereby certify that this plan, specification or report was prepared by me or under my direct supervision and that I am a duly Registered Professional Engineer under the laws of the State of Minnesota. C, 0 Osmundson, P.E., OSM & Associates, Inc. Date: June 4, 1991 Reg No. 19156 1 1 i 1 1 f 1 1 1 1 1 1 1 1 1 COUNTRY HILLS FOURTH ADDITION CITY PROJECT NO. 222 ROSEMOUNT, MINNESOTA TABLE OF CONTENTS TITLE PAGE/CERTIFICATION TALBE OF CONTENTS LETTER OF TRANSMITTAL EXECUTIVE SUMMARY 1.0 INTRODUCTION PAGE NO. 1 1.1 Authorization 1 1.2 Scope 1 1.3 Data Available 1 2.0 GENERAL BACKGROUND 2.1 Location 2.2 Project Area 2.3 Existing Conditions 3.0 PROPOSED IMPROVEMENTS 3.1 Sanitary Sewer 3.2 Watermain 3.3 Storm Drain 3.4 Street Construction 3.5 Trailway 3.6 Permits 3.7 Right-of-way and Easements 2 2 2 k, 3 3 4 4 4 4 Table of Contents - Continued PAGE NO. 4.0 FINANCING 5 4.1 Cost Estimate 5 4.2 Assessment Area 5 4.3 Cost Recovery 6 4.3.1 Assessment 6 4.3.2 Pending Assessment 6 5.0 PROJECT SCHEDULE 8 Drawings No's 1 through 5 APPENDIX May 26, 1991 Honorable Mayor and Council City of Rosemount 2875 145th Street West Rosemount, MN 55068 RE: Country Hills Fourth Addition Project No. 222 OSM Comm. No. 4788.00 Dear Mayor and Council: Enclosed is the Feasibility Report for Country Hills Fourth Addition Utility and Street Improvements, Project No. 222. This report addresses the sanitary sewer, watermain, storm drain and street necessary for the plat. We would be happy to discuss this report with you at your convenience. Please call if you have any questions. Respectfully, ORR-SCHELEN-MAYERON & ASSOCIATES, INC. Henry O. Osmundson, P.E. Project Manager r HCO/cmw 05/24-hm&c.ltr Enclosure Ul 1 EXECUTIVE SUMMARY City Project No. 222 provides for the installation of City Utilities and Streets in the Country Hills Fourth Addition Development in western Rosemount. The project includes the installation of sanitary sewer, watermain, storm drain, and street facilities within the Fourth Addition. The grading of the area will be completed by the developer under a private contract. The impetus for the project was a petition from the developer, U.S. Homes, Inc. The project is feasible from an engineering standpoint and can best be accomplished under one contract. The project includes the construction of approximately 700 lineal feet of sanitary sewer, 1650 feet of watermain, 490 feet of storm drain, 1650 feet of street construction and 900 feet of bituminous trail construction. The total estimated cost is $242,700. The funding for the project will come from assessments to the benefitted property and the Water Core Fund. The project can be initiated in August, with construction substantially complete in September of 1991. The final lift of bituminous will be completed by May 31, 1992. i r 1 1.0 INTRODUCTION 1.1 Authorization - On April 16, 1991, the Rosemount City Council authorized the preparation of an Engineering Feasibility Report for Public Utilities and Street Construction for the Country Hills Fourth Addition. This project has been designated as City Project No. 222. The developer submitted a petition for these improvements, which constituted 100% of the benefitted property. 1.2 Scope - This project provides for the construction of utilities and streets in the Country Hills Fourth Addition in western Rosemount. Sanitary sewer, water, storm drain, street, and trail facilities will be provided to the Fourth Addition. The developer, U.S. Homes, is responsible for the site grading in the Fourth Addition, which will be completed prior to the construction of the utilities and street examined in this report. 1.3 Data Available - Information and materials used in the preparation of this report include: ♦ City of Rosemount Record Plans. ♦ Comprehensive Water System Plan, October, 1988. ♦ Comprehensive Storm Water Drainage Plan, West Drainage Area, May, 1989. ♦ Country Hills Fourth Addition Preliminary Plat and Preliminary Grading Plan. 1 1 2.0 GENERAL BACKGROUND 2.1 Location - The project is located in the southeast quarter of the northwest quarter of Section 19, adjacent to future additions of the Country Hills PUD, s and the Shannon Hills School and Park. The project location is shown on Drawing No. 1 at the end of this report. 2.2 Project Area - The Country Hills Fourth Addition consists of 31 single family residential lots, plus dedicated street right-of-way, and includes Outlot B which is designated as a "common area" for the development. The Country Hills Fourth Addition consists of 13 acres which is part of the Country Hills Planned Unit Development (PUD). The Country Hills Fourth Addition is north of the Third Addition and west of the Shannon Park School. The First, Second and Third Additions were constructed in the middle and late 1980's. City Project No. 194, Shannon Parkway Street and Utilities provides access and sewer and water services to the Fourth Addition. The project area is currently zoned R-1. 2.3 Existing Conditions - The terrain is primarily rolling grassland with a pond near the northwest corner of the addition. IStormwater from Shannon Parkway and the Shannon Hills School currently flows west through an in place storm drain line, along Damask Path, and into Pond "BIR -136". 1 3.0 1 n 1 PROPOSED IMPROVEMENTS 3.1 Sanitary Sewer - The proposed project will provide sanitary sewer service to the Country Hills Fourth Addition. City Project No. 194 provided sanitary sewer service along Damask Path. Only services will need to be constructed from the Damask sewer line. The proposed 8" PVC gravity line along Daniel Lane will generally flow from the southeast to the northwest and connect into the existing sanitary line on Damask Path. Four inch services will be provided to the lots within the Fourth Addition. The proposed sanitary sewer facilities are shown on Drawing No. 2. 3.2 Watermain - The proposed watermain facilities will provide water service to the Fourth Addition, plus an extension to the future addition to the west. A 12" watermain will be extended west and south within Damask path from an existing extension in Shannon Parkway. An 8" watermain will be extended west from an existing extension off of Shannon Parkway, along Daniel Lane where it connects with the proposed 12" watermain on Damask Path. The proposed facilities include 1" services to each of the residential lots. Hydrants will be spaced accordingly for a residential area. The proposed watermain facilities are shown on Drawing No. 3. 3.3 Storm Drain - The proposed storm drain facilities will drain the proposed subdivision to the northwest into Pond BIR -136. The proposed system includes an extension of the storm drain on Damask Path and relocation of existing outlet into Pond BIR -136. This relocation is due to a change in lot configuration from a very preliminary plan which was used when Project No. 194 was designed. New catch basins will be placed at the intersection of Daniel Lane and Damask Path. These catch basins will drain northwest into Pond BIR -136. The proposed piping ranges in size from 12" to 24" in diameter. In accordance with the city policy, all storm drain facilities are sized to convey runoff from a 10 year storm event, and all ponding areas and outlet sewers are sized for a 100 year storm event. 3 3.4 3.5 1 3.6 1 3.7 1 r] t A future outlet may be necessary for Pond BIR -136 when the adjacent areas are developed, but is not necessary at this time. The Comprehensive Stormwater Drainage plan proposes that Pond BIR -136 drain westerly to Pond BIR -140, and eventually to Birger Pond. Street Construction - The proposed streets will be constructed to city standards which call for a 32' wide street. The street section will consist of 3" of bituminous courses and 6" of Class 5 based on the soil information known at this time. The street will be flanked by surmountable concrete curb and gutter. The street section design and cost estimate are based on the assumption that an acceptable subgrade is provided by the grading operation, for which the Developer is responsible. A small amount of sodding and seeding blanket are provided in this project for erosion control. Trailway - An 8' wide bituminous trail is proposed to be constructed within the Country Hills Fourth Addition along the north side of Damask Path for approximately 900'. Permits - Permits will be required for this project from the Minnesota Department of Health for watermain extensions and the Minnesota Pollution Control Agency for sanitary sewer extensions. Approval of the sanitary sewer plans is also required by the Metropolitan Waste Control Commission. Right-of-way and Easements - The 60' right-of-way and all necessary easements are anticipated to be dedicated by the developer on the final plat. Storm drain facilities north of Damask Path will require utility and drainage easement for the two outlets to Pond BIR -136. In addition, a ponding/drainage easement is required for this pond. Also, necessary easements for a future westerly outlet for this pond should be provided. 4 1 4.0 FINANCING 4.1 Cost Estimate - A detailed Cost Estimate can be found in the Appendix. The following estimates are based on 1990 and 1991 construction costs and include a 10% contingency factor and all related administrative costs. The administrative costs are estimated at 30% and include legal, engineering, interest, and other administration. A summary of these costs are as follows: These costs do not reflect the cost of land acquisition for easements, which are anticipated to be dedicated by the developer. 4.2 Assessment Area - The following parcels of land are located within the project and assessment area: The Country Hills Planned Unit Development, not including Additions 1, 2, and 3. remaining r The rema g p operty is proposed to be platted as: County Hills Fourth Addition Block 1, Lots 1 through 11 i Block 2, Lots 1 through 11 and Outlot B ■ Block 3, Lots 1 through 9 Outlots A, C, D, and E County Hills Fourth Addition has a total of 31 buildable lots. 5 1 Sanitary Sewer $ 24,500 Sanitary Sewer Services 14,900 Watermain 60,400 16,900 Water Services Storm Drain 29,000 90,300 Street Construction Trailway 6.700 TOTAL PROJECT COST $242,700 These costs do not reflect the cost of land acquisition for easements, which are anticipated to be dedicated by the developer. 4.2 Assessment Area - The following parcels of land are located within the project and assessment area: The Country Hills Planned Unit Development, not including Additions 1, 2, and 3. remaining r The rema g p operty is proposed to be platted as: County Hills Fourth Addition Block 1, Lots 1 through 11 i Block 2, Lots 1 through 11 and Outlot B ■ Block 3, Lots 1 through 9 Outlots A, C, D, and E County Hills Fourth Addition has a total of 31 buildable lots. 5 1 Using these estimated assessments, the funding for the project would be as shown on the chart on the following page. The project has a 1 total assessable cost of $235,500, which if spread over the 31 lots, produces an estimated assessment rate of $7,600 per lot. 4.3.2 PENDING ASSESSMENT: There are no pending assessments against the project area at this time. 6 4.3 Cost Recovery 4.3.1 ASSESSMENT: The sanitary sewer, storm drain, trail, and street ' construction proposed for the Shannon Hills Second Addition is regarded as residential equivalent sizing and therefore will be 100% assessable toward the benefitted lots included in the Second Addition. The proposed watermain facilities include the installation of the 12" main along Damask Path. The Comprehensive Water System Report plans for this 12" main to the west. Without this required 12" main, an 8" would be the largest pipe necessary four the development. Therefore, the cost of oversizing the pipe from a 12" to an 8" pipe should come out of the Watermain Core Fund. This is estimated to be $7,200 and will be determined by bid prices for the project. Using these estimated assessments, the funding for the project would be as shown on the chart on the following page. The project has a 1 total assessable cost of $235,500, which if spread over the 31 lots, produces an estimated assessment rate of $7,600 per lot. 4.3.2 PENDING ASSESSMENT: There are no pending assessments against the project area at this time. 6 COUNTRY HILLS FOURTH ESTIMATED COSTS AND FUNDING SOURCES 7 FUNDING STORM WATER/ FIVE ESTIMATED SEWER WATERMAIN SEWER YEAR TOTAL ITEM COST ASSESSMENT CORE CORE C.I.P C.I.P. REVENUES A. Sanitary Sewer $ 24,500 $ 24,500 0 0 0 0 $ 24,500 B. Sanitary Sewer 14,900 14,900 0 0 0 0 14,900 Services C. Watermain 60,400 53,200 0 7,200 0 0 60,400 D. Water Services 16,900 16,900 0 0 0 0 16,900 E. Storm Drain 29,000 29,000 0 0 0 0 29,000 F. Street 90,300 90,300 0 0 0 0 90,300 G. Trailway 6.700 6,700 0 0 0 0 6,700 TOTAL $242,700 $235,500 0 7,200 0 0 $242,700 7 n 1 8 5.0 PROJECT SCHEDULE The proposed schedule for this improvement is as follows: Receive Feasibility Report June 4, 1991 Final Plat Approval June 18, 1991 Public Hearing July 2, 1991 Order Preparation of Plans and Spec's July 2, 1991 Receive Plans and Spec's/Order Ad for Bid July 2, 1991 Bid Opening July 29, 1991 Award Contract August 6, 1991 Begin Construction August 1991 Completion of Construction September 1991 Assessment Hearing Spring 1992 First Payment with Real Estate Taxes Fall 1992 1 8 1 1 1 1 1 PROJEC Drown By:, P.S.H. Date: 6-4-91 gr elen Hayeron & (Bx Associates, Inc. Lngineers • Surveyors • Planners Beat Hennepin Avenue 0 Ylnaeepolla. YM 56413 0 612 -131 -OW Drawing Title LOCATION MAP COUNTRY HILLS 4TH ADD. CITY PROJECT NO. 222 CITY OF ROSEMOUNT Comm. No. { 4788.00 ._-E Sheet no. 1 LEGEND: ��••� PROPOSED SAN. SEWER 9 t / I / ! t \ � tO r' Y' Y' f EX. 8" P.� W 4 O s 6 i 3 3 O � T C O i 0 Drawn By: pp r P.S.H. 3ohelen Yayeron 1, Date CAI* Associates, Inc. Eagine6r3 • surveyors a Planners 6-4-91 3061 E"t H•an•vi• Aveaw 6 Yl6e*&P*" YM 66413 0 us -361-3660 Drawing Title Comm. No. SANITARY SEWER CONSTRUCTION 4788 COUNTRY HILLS 4TH ADD. Sheet no. CITY PROJECT NO. 222 2 CITY OF ROSEMOUNT LEGEND: PROPOSED WATERMAN PROPOSED 12" WATERMAN to 4t 3 2 , V 3 EX. 12 . Xn \��p� ` \ 7A 0 U T L 0 T 8 r\ /—PROPOSED %�- 8" WATERMAJN 9 11 10 4 else, 7EX. 8" 6 Drawn ly,: P.S.H. a elen Mayeron & Date: Associates, Inc. ZnSineers a Surv*yore s Planners 6-4-91 zt m..uepiu Awes*@ 0 MIRM—P0118- XX 66418 0 $12-331-18" r I a Drawing Title WATERMAN CONSTRUCTION COUNTRY HILLS 4TH ADD. CITY PROJECT NO. 222 CITY OF ROSEMOUNT Comm. No. 4788 Sheep. t no. 3 PROPOSED 2411 STORM DRAIN LEGEND: PROPOSED STORM SEWER 00 3 2 1211 L 00, 121 1511 1511 2 � V 9 4 3 PROPOSED 18" 4 STORM DRAIN 3 Drown BY: pp P.S.H. S0on Uayeron Date: CA Associates, Inc. jCnginsery a Surveyor@ a Planners 6-4-91 2= Seat Hannept. A1.s-f 01 91ba-P"'L "M 66418 01 018 -331 -OW 5 1% Drawing Title STORM SEWER CONSTRUCTION COUNTRY HILLS 4TH ADD. CITY PROJECT NO. 222 CITY OF ROSEMOUNT Comm. No. 4788 Sheet no. 4 ri S r rown y: Drawing Title P.S.H.CASUelen STREET CONSTRUCTION ltnyeron &COUNTRY HILLS 4TH ADD. Date Assoointes, Inc. _ Engineers a sur..,or. a Plannorn CITY PROJECT NO. 222 6-4-91 3M ZWA R....pla Avenue 0 r,.,w.u. wM "4* .""u-8-0 CITY OF ROSEMOUNT 8 9 Comm. No. 4788 Sheet no. 5 r 1 1 1 1 1 1 1 1 1 1 1 ADDENDIX A PRELIMINARY COST ESTIMATE COUNTRY HILLS 4TH ADDITION STREET AND UTILITY IMPROVEMENTS CITY OF ROSEMOUNT, MINNESOTA CITY PROJECT NO. 222 OSM COMM. NO. 4788.00 ITEM A. SANITARY SEWER 8" PVC SDR 35 Manhole Excess Manhole Depth Rock Stabilization TOTAL UNIT QUANTITIES UNIT PRICE TOTAL 700 L.F. $ 14.00 $ 9,800.00 5 Each $ 950.00 $ 4,750.00 39 L.F. $ 60.00 $ 2,340.00 30 Ton $ 7.00 $ 210.00 Total $ 17,100.00 10% Contingency 1,710.00 Total Sanitary Sewer Construction Cost $ 18,810.00 Plus 30% Legal, Engineering, Administration $ 5,650.00 and Financing TOTAL SANITARY SEWER PROJECT COST $ 243460.00 Appendix A - Preliminary Cost Estimate - Continued TOTAL UNIT ITEM QUANTITIES UNIT PRICE TOTAL B. SANITARY SEWER SERVICES 4" PVC Service Pipe 1,400 L.F. $ 7.00 $ 9,800.00 8" x 4" PVC Sewer Wyes 15 Each $ 40.00 $ 600.00 Total $ 10,400.00 10% Contingency 1,040.00 Total Sanitary Sewer Construction Cost $ 11,440.00 Plus 30% Legal, Engineering, Administration $ 3,430.00 and Financing TOTAL SANITARY SERVICES $ 14,870.00 PROJECT COST Appendix A - Preliminary Cost Estimate - Continued TOTAL UNIT ITEM QUANTITIES UNIT PRICE TOTAL C. WATERMAIN 12" DIP Class 52 900 L.F. $ 23.00 $ 20,700.00 8" DIP Class 52 750 L.F. $ 15.00 $ 11,250.00 12" DIP Gate Valve 1 Each $ 900.00 $ 900.00 8" DIP Gate Valve & Box 1 Each $ 500.00 $ 500.00 Hydrants 5 Each $ 1,100.00 $ 5,500.00 6" DIP Hydrant Leads 50 L.F. $ 15.00 $ 750.00 Fittings 1,600 Lbs. $ 1.00 $ 1,600.00 Connect to Existing 2 Each $ 400.00 $ 800.00 Rock Stabilization 30 Ton $ 7.00 $ 210.00 Total $ 42,210.00 10% Contingency 4,290.00 Total Sanitary Sewer Construction Cost $ 46,500.00 Plus 30% Legal, Engineering, Administration $ 13,900.00 and Financing TOTAL WATERMAIN PROJECT COST $ 60,400.00 Appendix A - Preliminary Cost Estimate - Continued TOTAL UNIT ITEM QUANTITIES UNIT PRICE TOTAL D. WATER SERVICES 1" Corp Cocks 1" Curb Stop & Box 1" Copper Service Pipe 31 Each $ 40.00 $ 1,240.00 31 Each $ 70.00 $ 2,170.00 1,400 L.F. $ 6.00 $ 8,400.00 Total $ 11,810.00 10% Contingency 1,190.00 Total Sanitary Sewer Construction Cost $ 13,000.00 Plus 30% Legal, Engineering, Administration $ 3,900.00 and Financing TOTAL WATERMAIN SERVICES $ 16,900.00 PROJECT COST 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Appendix A - Preliminary Cost Estimate - Continued TOTAL UNIT ITEM QUANTITIES UNIT PRICE TOTAL E. STORM DRAIN 12" RCP C.B. Leads 35 L.F. $ 18.00 $ 630.00 15" RCP C.B. Leads 77 L.F. $ 19.00 $ 1,463.00 18" RCP 180 L.F. $ 20.00 $ 3,600.00 24" RCP 200 L.F. $ 25.00 $ 5,000.00 18" FES w/Trash Guard 1 Each $ 900.00 $ 900.00 24" FES w/Trash Guard 1 Each $ 1,200.00 $ 1,200.00 4' Dia. C.B./MH (0'-8') 2 Each $ 900.00 $ 1.800.00 Excess 4' Dia. MH Depth > 8' 12 L.F. $ 100.00 $ 1,200.00 Catch Basin Type A 2 Each $ 700.00 $ 1,400.00 Catch Basin Type B 2 Each $ 750.00 $ 1,500.00 Grouted Rip Rap 20 C.Y. $ 60.00 $ 1,200.00 Rock Stabilization 50 Ton $ 7.00 $ 350.00 Total $ 20,243.00 10% Contingency 2,057.00 Total Sanitary Sewer Construction Cost $ 22,300.00 Plus 30% Legal, Engineering, Administration $ 6,700.00 and Financing TOTAL STORM DRAIN PROJECT COST 29,000.00 Appendix A - Preliminary Cost Estimate - Continued TOTAL UNIT ITEM QUANTITIES UNIT PRICE TOTAL F. STREETS Subgrade Preparation 17 R.S. $ 100.00 $ 1,700.00 Aggregate Base, Class 5 2,235 Ton $ 7.00 $ 15,645.00 100% Crushed 2331 Bituminous Base Course 500 Ton $ 20.00 $ 10,000.00 2341 Bituminous Wear Course 500 Ton $ 22.00 $ 11,000.00 Bituminous Material for 300 Gal. $ 1.80 $ 540.00 Tack Coat Concrete Curb & Gutter D418 3,400 L.F. $ 5.00 $ 17,000.00 Seed w/Mulch & Fertilizer .9 Acre $ 1,500.00 $ 1,350.00 Sodding 1,200 S.Y. $ 2.00 $ 2,400.00 Furnish & Install Signs 6 Each $ 200.00 $ 1,200.00 Rem & Re -install Temp. 1 L.S. $ 500.00 Barricades Fiber Blanket 500 S.Y. $ 2.00 $ 1,000.00 Adjust MH 8 Each $ 100.00 $ 800.00 Total $ 63,135.00 10% Contingency 6,365.00 Total Sanitary Sewer Construction Cost $ 69,500.00 Plus 30% Legal, Engineering, Administration $ 20,800.00 and Financing TOTAL STREET PROJECT COST $ 90,300.00 Annendix A - Preliminary Cost Estimate - Continued TOTAL UNIT ITEM QUANTITIES UNIT PRICE TOTAL G. TRAILWAY Aggregate Base Class 5 350 Ton $ 7.00 $ 2,450.00 100% Crushed 2341 Btiminous Wear Course 100 Ton $ 23.00 $ 2,300.00 Total $ 4,750.00 10% Contingency 450.00 Total Sanitary Sewer Construction Cost 0.00 $ 5,200.00 Plus 30% Legal, Engineering, Administration $ 1,500.00 and Financing TOTAL TRAILWAY CONSTRUCTION COST $ 6,700.00 Appendix A - Preliminary Cost Estimate - Continued PROJECT COST A. Sanitary Sewer B. Sanitary Sewer Services C. Watermain D. Water Services E. Storm Drain F. Street G. Trailway TOTAL PROJECT $ 24,460.00 $ 14.870.00 $ 60,400.00 $ 16.900.00 $ 29,000.00 $ 90.300.00 $ 6.700.00 $ 242.630.00