HomeMy WebLinkAbout5.b. Rosewood CrossingE X E C U T I V E S U M M A R Y
Planning Commission Meeting Date: May 23, 2017
Tentative Council Meeting Date: June 20, 2017
AGENDA ITEM: Case 17-20-FP, Final Site and Building
Plan Approval for PUD, and Final Plat for
Rosewood Crossing
AGENDA SECTION:
Public Hearing
PREPARED BY: Kyle Klatt, Senior Planner
Anthony Nemcek, City Planner AGENDA NO. 5.b.
ATTACHMENTS: Site Location Map; Rosewood Crossing
Final Plat; Final Site Plan and Phasing
(Phase 1 – 8 Sheets); Final Grading
Plan, Building Elevations; Resolution
Approving PUD Master Plan; City
Engineer Review Memo Dated 5-23-17
APPROVED BY: KL
RECOMMENDED ACTION:
1)Motion to Recommend Approval the Final Site and Building Plan for the Rosewood
Crossing PUD subject to the following conditions:
a.Execution of an amendment to the Rosewood Crossing PUD Agreement to
incorporate the updated site and building plans.
b.Payment in lieu of replacement trees of $11,700 prior to the issuance of a
building permit for any structure.
c.Incorporation of recommendations from the City Engineer in a review
memorandum dated May 23, 2017 relative to drainage, grading, street design,
easements, utilities and the adjacent sidewalks.
d.Payment of a fee in lieu of park land dedication for each unit consistent with the
City’s adopted fee schedule.
2)Motion to Recommend Approval of the Final Plat subject to the following conditions:
a.Execution of a subdivision agreement.
b.Provision of all easements as required by the City Engineer, and specifically,
drainage and utility easements over Lot 6, Block 1 and Outlot B of the final plat.
SUMMARY
The City Council is being asked to consider a request by Warren Israelson (Copperhead Development,
Inc.) relating to the Rosewood Crossing 225-unit rental apartment complex located south of 145th Street
and east of Downtown. The City approved the PUD Master Development Plan and preliminary plat in
December, 2016. At that time, it was recognized that the item would come back through the process for
final site and building plan approval and final plat approval. After the applicant obtains these approvals,
they would be allowed to obtain building permits for the project. There would be no further public actions
needed regarding the overall site design or even the details associated with the project. They would be
addressed through the administrative issuance of grading and building permits.
2
As part of the Master Development Plan approval there were 14 conditions of approval, many of which
detailed items that were anticipated as part of the final site and building plan. The main issues raised during
the public hearing at the Commission meeting were questions about phasing and what improvements
would be built as what part of the project build-out. The applicant has submitted a phasing plan which
itemizes their build-out intentions. Additionally, the final site and building plan functions like a site plan
review and therefore those specific items are called out in the following analysis.
The applicant is also requesting final plat approval to create the lots for the first two apartment buildings,
accessory garages, the caretaker’s premises, and necessary drainage and utility easements.
Applicant: Warren Israelson
Property Owner: Warren Israelson and Copperhead Development Inc.
Property Location: Lot 1 Block 1 Greif Addition and Lot 1 Block 2 Rosewood Village
3rd Addition
Size of Property: 12.25 Acres
Comprehensive Plan Designation: HDR High Density Residential (pending final Met Council action
on 5/24/17)
Zoning: R-4 High Density Residential/PUD
Number of Units: 225 units overall/65 units within Final Plat area
Site Density: 18.9 units/acre overall
Current Neighboring Land Uses: North – Self-storage Facility
South – Residential and Future Commercial
East – Detached Townhomes
West – Railroad and Rosemount Park and Ride
BACKGROUND
The Planning Commission reviewed the application and conducted a public hearing on this matter at its
October 25, 2016 meeting and continued the item to permit time to modify some of the plans relating to
parking, landscaping, building architecture and site circulation. At the meeting there were several members
of the public in attendance some requested denial of the project and others asked for additional
information. The Commission again reviewed the item at their meeting on November 22, 2017 and
recommended approval of the PUD Master Development Plan. The Plan had been modified to increase
drive, sidewalk and the property access widths, additional landscaping was proposed, including additional
screening along the eastern boundary, and additional information was provided regarding site work and
timing. However, the applicant could not respond to all the phasing questions asked during the meeting
and therefore a recommended condition of approval required submittal of a project phasing plan.
At the City Council meeting in December, the Council heard the presentation from staff, who noted there
are still concerns about on-site parking and therefore a specific condition relating to parking is included as
a recommended condition of approval. The council had questions about fencing, snow storage and
removal and clarifications to site access. The project was approved with conditions.
ISSUE ANALYSIS
Final Plat
The final plat combines the two properties that comprise the site and creates separate lots for five separate
buildings; the caretakers building, two apartment buildings, and two detached garage structures. The
remainder of the site will be designated as Outlot B and additional platting will be required prior to
construction of additional apartment buildings beyond the first two. The plat includes easements for
drainage and utility purposes, but these easements will need to be expanded to account for utility
construction on Outlot B.
3
Final Site and Building Plan
Land use and Zoning
The final step in City review of a PUD is final site and building plan approval. The review is similar to site
plan approval with the caveat that conditions of the PUD Master Development Plan must also be met.
Along with rezoning to PUD, the project received a reguiding of the northern parcel from Business Park
to High Density Residential and southern parcel from Medium Density Residential to High Density
Residential. The Amendment has been submitted to the Metropolitan Council for final approval, which is
tentatively scheduled for May 24, 2017.
Lot and Building Standards
As noted above, each apartment building and detached garage will be placed on a separate lot of record.
There will also be a separate lot for the caretakers building and common space. Because it is a PUD, there
are no issues associated with internal lot lines, only setbacks from the adjoining properties. Building
setback requirements are 30’ for the principal structures from all sides of the PUD and 50’ front yard and
10’ side yard setbacks for accessory structures which would include the parking garages. The plan meets
these standards.
Building and Architecture
One area of interest is the exterior plans for the individual apartment buildings. The applicant has revised
the plans to include more enhancement than previously presented, including additional stone on the
building elevations. The previous review requested additional enhancements on all sides of the buildings
since they face other residential properties and other apartment buildings within the complex. The initial
plan had the enhancements on the front elevations of the apartment buildings.
The current plan has stone veneer wainscoting on the front with the façade under each gable also clad in
stone. The remainder of the front elevation is lap siding, with a small amount of shake siding denoting the
front entrance. The rear elevations have stone wainscoting, stone on the facades of each end, and on the
first floor of the central gabled feature. The second level is shake siding with the interior spaces with patios
and balconies being lap siding. Side elevations include more stone, shake siding with some lap siding. The
PUD Master Plan approval permitted up to 60% of all exterior elevations to be siding, excluding windows
and doors. The new plan meets this condition as 58.66% is lap or shake siding with the remaining 41.34%
stone. The applicant has provided updated drawings for the office/caretaker’s residence and garage units
as well, and these buildings also comply with the required material percentages. The garages are 55%
stone veneer and the leasing office is 46% stone veneer.
The composition of apartment unit types within the project are listed as follows:
Proposed Types of Apartment Units for Rosewood Commons
Type of Unit Size Number of Units Percentage of Units
One Bedroom 700 Square Feet 140 63%
Two Bedroom 829-894 Square Feet 84 37%
The above chart does not take into account the caretaker’s residence, which would bring the overall
number of units up to 225 for the entire project. The final plat area includes two of the apartment
buildings with the caretaker’s residence (65 units).
4
The arrangement and location of the garaged follows the master plan very closely; however, the updated
plans show a service door on the back of each unit. Since the service doors are not a building code
requirement and cannot be accessed from the front of each building, Staff is recommending that they be
eliminated from the plans.
Parks and Open Space
The developer is being asked to pay a fee in lieu of park land for the project. The fee was estimated at
$792,200 based on the City’s current fee schedule. However, the staff is proposing a change in the park
dedication fee calculation which will stratify dedication and resulting fees, based upon the density of the
project. It is anticipated that this modification will be made prior to obtaining any building permits for the
project. Under the current proposal, the payment for the entire project would be $562,000. Actual
payment for each apartment building will occur at the time of building permit and will reflect the current
fee schedule at that time.
The master plan includes a small private playground area on the southern portion of the site in the back of
buildings four, six, and seven. As noted in the master plan review, the final details for the play area should
be submitted to the City for review prior to construction. The updated phasing plan provided by the
applicant identifies that the playground will be installed as part of phase four.
Access and Parking
The City’s approval of the master development plan included several conditions related to parking and
access across the site. The final development plans have been updated to address maneuvering concerns
at the 145th Street entrance, and now provide adequate stacking for vehicles waiting to exit the site onto
145th Street. The phasing plan also includes the construction of a specific number of parking stalls within
each project phase. Overall the applicant is proposing 450 parking stalls of which 113 will be located
within the detached accessory garage structures and 337 will be exterior surface parking stalls, around each
building. The number and location of parking stalls is consistent with the preliminary development plan
approval.
The conditions of preliminary plan approval specified that the project was approved for six buildings and
the office building, and that the parking situation had to be evaluated before a seventh building could be
constructed. The parking evaluation must be completed before the fourth phase is constructed, at which
point the City will have the ability to either find that the parking provided is adequate and the developer
can proceed with all seven buildings, or that the parking is not adequate to meet the actual demand on the
site. If parking is not adequate, one building will need to be eliminated from the plan. The parking analysis
is not needed until the fourth phase, and therefore, will not impact the applicant’s ability to move forward
with the final development plans for phases one and two.
Phasing Plan
The final development plans include a revised phasing plan that more accurately describes the timing of all
proposed improvements to the site. This plan has also been updated to better align the building
numbering with the project phases. The cover sheet for the phasing plan includes all project
improvements, while the latter drawings focus on the improvements that will be completed with each
specific phase. Please note that the Rosewood Crossing final plat covers the first two phases of the project
and will allow construction to commence on both these buildings without any additional approvals (other
than a building permit) from the City. Any subsequent phases will be subject to approval of a final plat.
The need for future final plats will help the City ensure that the timing requirements for various
improvements as spelled out in the preliminary approval and the required parking study are met by the
applicant.
5
Each phase of the project will essentially include one of the 32-unit apartment buildings, detached garage
structure with 16 parking stalls, surface parking around each building, access road extension, fencing to the
furthest extent of each phase, and landscaping. In addition to these elements, the first project phase will
include the caretaker’s residence/office, the sanitary sewer mains, and approximately half of the storm
sewer pipes required to serve the entire project area. Water service will be extended in each phase with the
other improvements. Staff does not have any specific comments concerning the phasing plan, but would
like to see more of the trees along the boundary with the Rosewood Village Second Addition installed in
phase four.
Landscaping and Tree Preservation
The original site plan approved with the PUD indicated a total of 151 trees planted throughout the
development. This was far short from the required trees. The landscaping plan provided with the final
plat, final site and building plan indicates a total of 240 trees. This exceeds the 233 trees required by code
(eight plus one tree per unit). The majority of the new trees are located along the eastern property line.
With regard to foundation plantings the landscaping plan is consistent with the original plan approved
with the PUD. The landscape plan indicates 105 foundation plantings spaced 30 inches off center will be
planted along the front and sides of each building. The number of foundation plantings is in compliance
with the City’s Landscape Ordinance requirement of one foundation planting per 10 linear feet of building
perimeter.
The tree preservation plan provided with the original PUD application indicated that the developer will be
removing 196 caliper inches of existing vegetation beyond the threshold for removal without replacement
being required. Because of the amount of landscaping required for the site before any replacement, staff is
recommending the applicant pay in lieu of planting for the trees. The cost per tree is $300 and therefore
the applicant would be required to pay $11,700.
Signage
The applicant is proposing a monument sign that will be located at the entrance along 145th Street. The
grading/site plan has been updated to include the proposed sign. A sign permit for the sign may be
approved administratively so long as it meets all the requirements of the Sign Ordinance.
Trash Enclosure
The plans supplied by the applicant indicate that dumpsters will be located adjacent or in-between the
garages at four different locations on the site. The site plan indicates that the enclosures will be
constructed of concrete block and the final construction plans will be reviewed by the Fire Marshall prior
to issuance of a building permit to ensure the proper separation between the enclosure and the adjacent
garage structures is maintained.
Fencing
The applicant is proposing an aluminum picket fence that will extend southward from 145th Street along
the western edge of the project area. The fence will be extended between each of the garages and
terminate with “Garage 7” in the southern portion of the site. The type of fence proposed and location of
the fence are consistent with the approved master plan.
Lighting
The lighting indicated on the final site plan is consistent with that which was provided with the original
PUD application. The plan demonstrates compliance with City’s lighting ordinance for lighting standards
and the maximum intensity of light at neighboring property lines.
6
Engineering
The City’s project engineer has reviewed the plan and provided comments in the Engineer’s Memo dated
May 23, 2017. Generally, the comments pertain to information that must be included for review prior to
building permit approval. The development fees that must be paid by the applicant are $84,096.25 for the
storm sewer trunk charge, $13,168.75 for the sanitary sewer trunk charge, and $79,625 for the water main
trunk charge.
CONCLUSION & RECOMMENDATION
Staff recommends that the Planning Commission recommend approval of the application for a Planned Unit
Development Final Site and Building Plan and Final Plat to allow the construction of the first two phases of
an apartment complex with two two-story buildings and a leasing office/maintenance building that contains
a community room and a three-bedroom caretaker’s unit subject to the conditions of approval outlined in
the recommended action section above.
1011GARAGE 4B
8 STALLS- 963.50
GA
R
A
G
E
2
16 S
T
A
L
L
S
-
9
6
4
.
0
0
BLDG 1-32 UNITS
966.00
BLDG 3-32 UNIT
965.00
BLDG 4-32 UNIT
963.50
BLDG 5-32 UNIT
963.00
BLDG 2-32 UNIT
964.0
BLDG 7-32 UNIT
962.00
BLDG 6-32 UNIT
962.5016LEASING
OFFICE
969.25 18161119111118111311111311161109421011117110311168GARAGE 4A8 STALLS- 964.00GARAGE 3
16 STALLS- 964.68
GARAGE 616 STALLS- 962.50GARAGE 5
16 STALLS
-
9
6
3
.
0
0
GA
R
A
G
E
1
16 S
T
A
L
L
S 11A
DECORATIVE FENCE
A
M
A
M
M
A
A
L
L
L
A
DECORATIVE FENCE
M
DECORATIVE FENCE
15
"
R
C
P10
M 201020101020102020106A
L
M
11DECORATIVE FENCE
A
M
A
12020
20 15L
A
M
A
A
A
L
M
M
M
M
M
A
L
L
A
A
L1212M
L
A
A
M
L
M
AA
L
A
M
A
A
L
L
A14
A
A
A12
L
L
L L
L
A
LL
M
M
M
L L
A
M
2020
A
L
L
A
A
L
L
L
12 12
12202020
107201911DECORATIVE FENCE
DECORATIVE FENCE1 196123I hereby certify that this plan was prepared by me,
or under my direct supervision, and that I am a
duly registered engineer under the laws of the
State of Minnesota.
Warren John Israelson
6001 Egan Drive, Ste 100, Savage, MN 55378
Phone: 952.226.3200 Web: www.kjwalk.com
Date: Revision:
Original
Registration #: 40175
Rosewood
Crossing
Rosemount, MN
SHEET 1 of 8
Date: 4/25/2017
0 50 100 150
FILE PATH: C:\Users\Skills\Documents\Projects\Rosemount\Rosewood Crossing\Engineering\CAD\DWGs\RWC-PhaseCover.dwg
Legend
Existing watermain
Proposed watermain
Existing sanitary
Proposed sanitary
Existing storm
Proposed storm
Existing hydrant
Proposed hydrant
Existing gate valve
Proposed gate valve
Existing manhole
Proposed manhole
Proposed catchbasin
Silt fence
Inlet protectors
Parking lot lights
Building Lights
Rip Rap
TYPICAL PARKING SPACE
(NOT TO SCALE)
BLDG
CONCRETE SIDEWALK6.5'4'17.5'8.5'
NOTES
LIGHTS ALSO INSTALLED ON EXTERIOR OF
BUILDINGS.
LAST SAVED: April 25, 2017
PARKING
REQUIRED
2 STALLS PER UNIT (225 UNITS)450
PROVIDED
GARAGE STALLS 113
PARKING STALLS 337
TOTAL 450
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
PAVED ACCESS EASEMENT
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
For Review
April 25,2017
04/25/13
Phasing Plan
Cover
PHASE 1
PHASE 3
PHASE 2
PHASE 5
PHASE 4
PHASE 6
PHASE 7
SHEET INDEX
1 Cover
2 Phase 1
3 Phase 2
4 Phase 3
5 Phase 4
6 Phase 5
7 Phase 6
8 Phase 7
BLDG 1-32 UNITS
966.00
LEASING
OFFICE
969.251
111811131113GA
R
A
G
E
1
16
S
T
A
L
L
S
A
DECORATIVE FENCE
A
M
A
L
DECORATIVE FENCE 1010101010106M
A
201212L
AA
L
A
M12 L
2020
12 12
12202020
20Temporary
Turn Around
R45
For Review
April 25,2017
I hereby certify that this plan was prepared by me,
or under my direct supervision, and that I am a
duly registered engineer under the laws of the
State of Minnesota.
Warren John Israelson
6001 Egan Drive, Ste 100, Savage, MN 55378
Phone: 952.226.3200 Web: www.kjwalk.com
Date:
04/25/13
Revision:
Original
Phasing Plan
Phase 1
Registration #: 40175
Rosewood
Crossing
Rosemount, MN
SHEET 2 of 8
Date: 4/25/2017
0 50 100 150
FILE PATH: C:\Users\Skills\Documents\Projects\Rosemount\Rosewood Crossing\Engineering\CAD\DWGs\RWC-Phase1.dwg
TYPICAL PARKING SPACE
(NOT TO SCALE)
BLDG
CONCRETE SIDEWALK6.5'4'17.5'8.5'
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
NOTES
LIGHTS ALSO INSTALLED ON EXTERIOR OF
BUILDINGS.
LAST SAVED: April 25, 2017
PARKING
REQUIRED
2 STALLS PER UNIT (33 UNITS)66
PROVIDED
GARAGE STALLS 17
PARKING STALLS 61
TOTAL 78
GA
R
A
G
E
2
16 S
T
A
L
L
S
-
9
6
4
.
0
0
BLDG 1-32 UNITS
966.00
BLDG 2-32 UNIT
964.0
LEASING
OFFICE
969.251
11118111311113116211GA
R
A
G
E
1
16
S
T
A
L
L
S
A
DECORATIVE FENCE
A
M
A
L
A
DECORATIVE FENCE
DECORATIVE FENCE 1010101010106M
1A
201212L
AA
L
A
M12 L
2020
12 12
12202020
10720Temporary
Turn Around
R45
I hereby certify that this plan was prepared by me,
or under my direct supervision, and that I am a
duly registered engineer under the laws of the
State of Minnesota.
Warren John Israelson
6001 Egan Drive, Ste 100, Savage, MN 55378
Phone: 952.226.3200 Web: www.kjwalk.com
Date:Revision:
Original
Registration #: 40175
Rosewood
Crossing
Rosemount, MN
SHEET 3 of 8
Date: 4/25/2017
0 50 100 150
FILE PATH: C:\Users\Skills\Documents\Projects\Rosemount\Rosewood Crossing\Engineering\CAD\DWGs\RWC-Phase2.dwg
TYPICAL PARKING SPACE
(NOT TO SCALE)
BLDG
CONCRETE SIDEWALK6.5'4'17.5'8.5'
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
NOTES
LIGHTS ALSO INSTALLED ON EXTERIOR OF
BUILDINGS.
LAST SAVED: April 25, 2017
PARKING
REQUIRED
2 STALLS PER UNIT (65 UNITS)130
PROVIDED
GARAGE STALLS 33
PARKING STALLS 97
TOTAL 130
For Review
April 25,2017
04/25/13
Phasing Plan
Phase 2
1GA
R
A
G
E
2
16
S
T
A
L
L
S
-
9
6
4
.
0
0
BLDG 1-32 UNITS
966.00
BLDG 3-32 UNIT
965.00
BLDG 2-32 UNIT
964.016LEASING
OFFICE
969.25 11111181113111131162111171011GARAGE 3
16 STALLS- 964.68
GA
R
A
G
E
1
16
S
T
A
L
L
S
A
DECORATIVE FENCE
A
M
A
M
A
L
L
A
DECORATIVE FENCE
DECORATIVE FENCE 10201020101020102020106L
M
1A
M
A
120201212 L
A
A
M
L
M
AA
L
A
M
1412L
2020
12 12
12202020
10720Phase 3 Gr
a
v
e
l
l
o
o
p Phase 3 Gravel loopPhase 3 Gravel loopI hereby certify that this plan was prepared by me,
or under my direct supervision, and that I am a
duly registered engineer under the laws of the
State of Minnesota.
Warren John Israelson
6001 Egan Drive, Ste 100, Savage, MN 55378
Phone: 952.226.3200 Web: www.kjwalk.com
Date:Revision:
Original
Registration #: 40175
Rosewood
Crossing
Rosemount, MN
SHEET 4 of 8
Date: 4/25/2017
0 50 100 150
FILE PATH: C:\Users\Skills\Documents\Projects\Rosemount\Rosewood Crossing\Engineering\CAD\DWGs\RWC-Phase3.dwg
TYPICAL PARKING SPACE
(NOT TO SCALE)
BLDG
CONCRETE SIDEWALK6.5'4'17.5'8.5'
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
NOTES
LIGHTS ALSO INSTALLED ON EXTERIOR OF
BUILDINGS.
LAST SAVED: April 25, 2017
PARKING
REQUIRED
2 STALLS PER UNIT (97 UNITS)194
PROVIDED
GARAGE STALLS 49
PARKING STALLS 155
TOTAL 204
For Review
April 25,2017
04/25/13
Phasing Plan
Phase 3
11GARAGE 4B
8 STALLS- 963.50
GA
R
A
G
E
2
16
S
T
A
L
L
S
-
9
6
4
.
0
0
BLDG 1-32 UNITS
966.00
BLDG 3-32 UNIT
965.00
BLDG 4-32 UNIT
963.50
BLDG 2-32 UNIT
964.016LEASING
OFFICE
969.25 116191111811131111311621111711011GARAGE 4A8 STALLS- 964.00GARAGE 3
16 STALLS- 964.68
GA
R
A
G
E
1
16
S
T
A
L
L
S
A
DECORATIVE FENCE
A
M
A
M
A
A
L
L
L
A
DECORATIVE FENCE
DECORATIVE FENCE 10201020101020102020106A
L
M
1A
M
A
12020 15L
A
M
A
M
M
A
L
L
A
A1212
L
A
A
M
L
M
AA
L
A
M
1412L
2020
12 12
12202020
10720Phase 3 Gr
a
v
e
l
l
o
o
p 19Phase 3 Gravel loopI hereby certify that this plan was prepared by me,
or under my direct supervision, and that I am a
duly registered engineer under the laws of the
State of Minnesota.
Warren John Israelson
6001 Egan Drive, Ste 100, Savage, MN 55378
Phone: 952.226.3200 Web: www.kjwalk.com
Date:Revision:
Original
Registration #: 40175
Rosewood
Crossing
Rosemount, MN
SHEET 5 of 8
Date: 4/25/2017
0 50 100 150
FILE PATH: C:\Users\Skills\Documents\Projects\Rosemount\Rosewood Crossing\Engineering\CAD\DWGs\RWC-Phase4.dwg
TYPICAL PARKING SPACE
(NOT TO SCALE)
BLDG
CONCRETE SIDEWALK6.5'4'17.5'8.5'
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
NOTES
LIGHTS ALSO INSTALLED ON EXTERIOR OF
BUILDINGS.
LAST SAVED: April 25, 2017
PARKING
REQUIRED
2 STALLS PER UNIT (129 UNITS)258
PROVIDED
GARAGE STALLS 65
PARKING STALLS 204
TOTAL 269
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
PAVED ACCESS EASEMENT
For Review
April 25,2017
04/25/13
Phasing Plan
Phase 4
1011GARAGE 4B
8 STALLS- 963.50
GA
R
A
G
E
2
16
S
T
A
L
L
S
-
9
6
4
.
0
0
BLDG 1-32 UNITS
966.00
BLDG 3-32 UNIT
965.00
BLDG 4-32 UNIT
963.50
BLDG 5-32 UNIT
963.00
BLDG 2-32 UNIT
964.016LEASING
OFFICE
969.25 1161191111811131111131161109421111711011GARAGE 4A8 STALLS- 964.00GARAGE 3
16 STALLS- 964.68
GARAGE 5
16 STALLS
-
9
6
3
.
0
0
GA
R
A
G
E
1
16
S
T
A
L
L
S
A
DECORATIVE FENCE
A
M
A
M
M
A
A
L
L
L
A
DECORATIVE FENCE
DECORATIVE FENCE 10M 201020101020102020106A
L
M
1A
M
A
12020
20 15L
A
M
A
M
M
A
L
L
A
A
L1212M
L
A
A
M
L
M
AA
L
A
M
DECORATIVE FENCE1412L
L L
L
A2020
L
12 12
12202020
107201911DECORATIVE FENCE Phase 3 Gravel loopI hereby certify that this plan was prepared by me,
or under my direct supervision, and that I am a
duly registered engineer under the laws of the
State of Minnesota.
Warren John Israelson
6001 Egan Drive, Ste 100, Savage, MN 55378
Phone: 952.226.3200 Web: www.kjwalk.com
Date:Revision:
Original
Registration #: 40175
Rosewood
Crossing
Rosemount, MN
SHEET 6 of 8
Date: 4/25/2017
0 50 100 150
FILE PATH: C:\Users\Skills\Documents\Projects\Rosemount\Rosewood Crossing\Engineering\CAD\DWGs\RWC-Phase5.dwg
TYPICAL PARKING SPACE
(NOT TO SCALE)
BLDG
CONCRETE SIDEWALK6.5'4'17.5'8.5'
NOTES
LIGHTS ALSO INSTALLED ON EXTERIOR OF
BUILDINGS.
LAST SAVED: April 25, 2017
PARKING
REQUIRED
2 STALLS PER UNIT (161 UNITS)322
PROVIDED
GARAGE STALLS 81
PARKING STALLS 245
TOTAL 326
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
PAVED ACCESS EASEMENT
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
For Review
April 25,2017
04/25/13
Phasing Plan
Phase 5
1011GARAGE 4B
8 STALLS- 963.50
GA
R
A
G
E
2
16
S
T
A
L
L
S
-
9
6
4
.
0
0
BLDG 1-32 UNITS
966.00
BLDG 3-32 UNIT
965.00
BLDG 4-32 UNIT
963.50
BLDG 5-32 UNIT
963.00
BLDG 2-32 UNIT
964.0
BLDG 6-32 UNIT
962.5016LEASING
OFFICE
969.25 181611191111181113111113116110942101111711011GARAGE 4A8 STALLS- 964.00GARAGE 3
16 STALLS- 964.68
GARAGE 616 STALLS- 962.50GARAGE 5
16 STALLS
-
9
6
3
.
0
0
GA
R
A
G
E
1
16
S
T
A
L
L
S
A
DECORATIVE FENCE
A
M
A
M
M
A
A
L
L
L
A
DECORATIVE FENCE
DECORATIVE FENCE 10M 201020101020102020106A
L
M
11A
M
A
12020
20 15L
A
M
A
M
M
M
A
L
L
A
A
L1212M
L
A
A
M
L
M
AA
L
A
M
14A
A12
L
L
L L
L
A2020
A
L
L
L
12 12
12202020
107201911DECORATIVE FENCE
DECORATIVE FENCE1 196Phase 3 Gravel loopI hereby certify that this plan was prepared by me,
or under my direct supervision, and that I am a
duly registered engineer under the laws of the
State of Minnesota.
Warren John Israelson
6001 Egan Drive, Ste 100, Savage, MN 55378
Phone: 952.226.3200 Web: www.kjwalk.com
Date:Revision:
Original
Registration #: 40175
Rosewood
Crossing
Rosemount, MN
SHEET 7 of 8
Date: 4/25/2017
0 50 100 150
FILE PATH: C:\Users\Skills\Documents\Projects\Rosemount\Rosewood Crossing\Engineering\CAD\DWGs\RWC-Phase6.dwg
TYPICAL PARKING SPACE
(NOT TO SCALE)
BLDG
CONCRETE SIDEWALK6.5'4'17.5'8.5'
NOTES
LIGHTS ALSO INSTALLED ON EXTERIOR OF
BUILDINGS.
LAST SAVED: April 25, 2017
PARKING
REQUIRED
2 STALLS PER UNIT (193 UNITS)386
PROVIDED
GARAGE STALLS 97
PARKING STALLS 289
TOTAL 386
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
PAVED ACCESS EASEMENT
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
For Review
April 25,2017
04/25/13
Phasing Plan
Phase 6
1011GARAGE 4B
8 STALLS- 963.50
GA
R
A
G
E
2
16
S
T
A
L
L
S
-
9
6
4
.
0
0
BLDG 1-32 UNITS
966.00
BLDG 3-32 UNIT
965.00
BLDG 4-32 UNIT
963.50
BLDG 5-32 UNIT
963.00
BLDG 2-32 UNIT
964.0
BLDG 7-32 UNIT
962.00
BLDG 6-32 UNIT
962.5016LEASING
OFFICE
969.25 181611191111181113111113111611094210111171103111GARAGE 4A8 STALLS- 964.00GARAGE 3
16 STALLS- 964.68
GARAGE 616 STALLS- 962.50GARAGE 5
16 STALLS
-
9
6
3
.
0
0
GA
R
A
G
E
1
16
S
T
A
L
L
S 11A
DECORATIVE FENCE
A
M
A
M
M
A
A
L
L
L
A
DECORATIVE FENCE
M
DECORATIVE FENCE 10M 201020101020102020106A
L
M
11DECORATIVE FENCE
A
M
A
12020
20 15L
A
M
A
A
A
L
M
M
M
M
M
A
L
L
A
A
L1212M
L
A
A
M
L
M
AA
L
A
M
A
A
L
L
A14
A
A
A12
L
L
L L
L
A
LL
M
M
M
L L
A
M
2020
A
L
L
A
A
L
L
L
12 12
12202020
107201911DECORATIVE FENCE
DECORATIVE FENCE1 196123I hereby certify that this plan was prepared by me,
or under my direct supervision, and that I am a
duly registered engineer under the laws of the
State of Minnesota.
Warren John Israelson
6001 Egan Drive, Ste 100, Savage, MN 55378
Phone: 952.226.3200 Web: www.kjwalk.com
Date:Revision:
Original
Registration #: 40175
Rosewood
Crossing
Rosemount, MN
SHEET 8 of 8
Date: 4/25/2017
0 50 100 150
FILE PATH: C:\Users\Skills\Documents\Projects\Rosemount\Rosewood Crossing\Engineering\CAD\DWGs\RWC-Phase7.dwg
TYPICAL PARKING SPACE
(NOT TO SCALE)
BLDG
CONCRETE SIDEWALK6.5'4'17.5'8.5'
NOTES
LIGHTS ALSO INSTALLED ON EXTERIOR OF
BUILDINGS.
LAST SAVED: April 25, 2017
PARKING
REQUIRED
2 STALLS PER UNIT (225 UNITS)450
PROVIDED
GARAGE STALLS 113
PARKING STALLS 337
TOTAL 450
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
PAVED ACCESS EASEMENT
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
DUMPSTER LOCATION
WITH CONCRETE
BLOCK ENCLOSURE
For Review
April 25,2017
04/25/13
Phasing Plan
Phase 7
1011REMOVE EXISTING ENTRACE ANDCONSTRUCT NEW ENTRANCEGARAGE 6A
8 STALLS- 963.50
GA
R
A
G
E
2
16 S
T
A
L
L
S69.2BLDG 1-32 UNITS
966.27
BLDG 7-32 UNIT
965.31
BLDG 6-32 UNIT
963.50
BLDG 3-32 UNIT
963.00
BLDG 2-32 UNIT
964.27
BLDG 5-32 UNIT
962.00
BLDG 4-32 UNIT
962.5016LEASING
OFFICE
970.00 18161119111118511113111113111961101911210111171103111GARAGE 6B8 STALLS- 964.00GARAGE 7
16 STALLS- 964.68
GARAGE 416 STALLS- 962.50GARAGE 3
16 STALLS
-
9
6
3
.
0
0
GA
R
A
G
E
1
16
S
T
A
L
L
S 171020'X 75' ROCK CONSTRUCTION ENTRANCE20102010227.87 10201017.47
2036.44 20106191.221
5
6
.
0
2
11202020201511412121220201212
12
962.50959.00961.30HP 70.0965.10964.58963.10962.60961.50962.00961.50959.90960.00963.50969.53968.00967.19962.00961.50961.00961.00967.56962.50960.50962.00961.00959.60965.33966.18965.89965.89965.56965.56965.23965.23964.89965.61964.61963.33963.61963.89963.56963.56963.23963.23962.89963.89966.00968.91968.24967.85967.76967.24966.28965.72966.39968.60968.60968.24969.62967.77966.58969.13962.61965.30965.20965.78966.63966.72967.48964.67964.58965.15964.94964.68962.33963.43963.90964.18965.43965.90965
.
2
3
965
.
5
6
965
.
8
9
963
.
8
9
963
.
5
6
963
.
2
3964.33964.67967.66963.38964.94964.46964.68964.68964.40963.62963.90SIGN
MONUMENT
30'30'I hereby certify that this plan was prepared by me,
or under my direct supervision, and that I am a
duly registered engineer under the laws of the
State of Minnesota.
Warren John Israelson
6001 Egan Drive, Ste 100, Savage, MN 55378
Phone: 952.226.3200 Web: www.kjwalk.com
Date:
04/18/13
Revision:
Original
Grading and
Erosion Control Plan
Registration #: 40175
Rosewood
Crossing
Rosemount, MN
SHEET 4 of 9
Date: 5/17/2017
0 50 100 150
FILE PATH: C:\Users\Skills\Documents\Projects\Rosemount\Rosewood Crossing\Engineering\CAD\DWGs\RWCOM-APT.dwg
04/18/16 Revised
06/17/16 Revised
07/18/16 Revised
Silt Fence to be installed along perimeter of
construction area prior to the start of work.
NOTES:
MAXIMUM ALLOWABLE SLOPE 3:1
PONDS MAY BE USED AS TEMPORARY SEDIMENTATION
BASINS DURING CONSTRUCTION, IF A POND IS USED AS
A TEMP. SED. BASIN IT MUST BE CLEANED OUT PRIOR
TO BEING PUT INTO SERVICE.
DRAINAGE TO THE TEMPORARY SEDIMENTATION
BASINS MUST BE MAINTAINED THROUGHOUT THE
CONSTRUCTION PROCESS.
SEED MIXES AS SHOWN IN LEGEND , WHERE NOT
SPECIFIED USE MN DOT MIX 250 AS GENERAL SITE
STABILIZATION.
STOCKPILES TO BE STABILIZED IF NOT UTILIZED FOR
MORE THAN 7 DAYS.
LAST SAVED: May 17, 2017
09/08/16 Revised
11/17/16 Revised
For Review
MAY 15,2017
01/10/17 Revised
CB & DROP IN INLET PROTECTORS
LEGEND
SILT FENCE
DRAINAGE ARROW
05/15/17 Revised
5" CASING
LP LAP 6" REVEAL
COVERED VENT
LP LAP 4" REVEAL
SINGLE DOOR WITH SIDELITES
IN COVERED ENTRY
STONE VENEER
LP SHINGLES
ASPHALT SHINGLES
LP LAP 6" REVEAL
LP LAP 4" REVEAL
STONE VENEER
5" CASING
COVERED VENT
ASPHALT SHINGLES
LP LAP 6" REVEAL
5" CASING
LP SHINGLES
COVERED VENT
LP LAP 4" REVEAL
COVERED VENT
LP LAP 4" REVEAL
5" CASING
LP SHINGLES
STONE VENEERSTONE VENEER
LP LAP 6" REVEAL
ASPHALT SHINGLESASPHALT SHINGLES
24'.+/Á
(4106'.'8#6+10Á
4'#4'.'8#6+10Á'ICP&TKXG5VG5CXCIG/02JQPG9GDYYYMLYCNMEQO4+)*6'.'8#6+10Á.'(6'.'8#6+10Á#22#46/'065)#4#)'524'.+/Á
5KFKPI
5VQPG
4GXKUGFÁ
ÁÁÁ
ÁÁ
ÁÁÁ
ÁÁ
Á
ÁÁÁÁÁÁÁÁÁÁÁÁ
Á
Á
ÁÁÁÁÁÁÁÁÁÁÁÁÁÁ
:18*&4:18*&4:18*&4:18*&4:18*&4:18*&4:18*&4:18*&4:18*&4:18*&4:18*&4:18*&4:18*&4:18*&4:18*&4:18*&4ÁÁ
ÁÁÁ
&7/256'4'0%.1574'
%10%4'6'/#5104;70+6
:%10%(6)5
:64'#6'&5+..2.#6 Á)4#07.#4(+..
&4#+06+.'
95+.641%-
#.7/(#5%+#
);2$1#4&
#52*#.65*+0).'5
('.6
5*'#6*+0)
411(64755'5
#.7/8'06'&51((+6 4Á+057.#6+10
'0'4);*''.
)4#&'
2174'&%10%9#..
94'$#42'4%1&'
*14+<.#25+&+0)
9'#6*'4$#44+'4
5647%65*'#6*+0)
:567&5"1%
);2$1#4&4Á25+
4+&)+&+057.
LP SHINGLES
CONCRETE MASONRY UNIT
STONE VENEER
ASPHALT SHINGLES
LP LAP 6" REVEAL
STONE VENEER
LP LAP 6" REVEAL
8'X7' GARAGE DOORSDUMPSTER ENCLOSURE
CONCRETE MASONRY UNIT
DUMPSTER ENCLOSURE
CONCRETE MASONRY UNIT
LP LAP 6" REVEALASPHALT SHINGLES
DUMPSTER ENCLOSURE
CONCRETE MASONRY UNIT
#22#46/'065)#4#)'54'#4'.'8#6+10Á
(170+102.#0Á'ICP&TKXG5VG5CXCIG/02JQPG9GDYYYMLYCNMEQO4'#4'.'8#6+10Á.'(6'.'8#6+10Á4+)*6'.'8#6+10Á
911&567&(4#/+0)
)4155#4'#53(6
24'.+/Á
24'.+/Á
(.1142.#0Á
411(2.#0Á6;2+%#.)#4#)'9#..5'%6+10Á
6QVCN5VQPG
5KFKPI
5VQPG
4GXKUGFÁ
STONE VENEER
LP LAP 6" REVEAL
LP SHINGLES
DOUBLE DOORS
IN COVERED ENTRY DOUBLE DOORS
IN COVERED ENTRY
ASPHALT SHINGLES
ASPHALT SHINGLES
5" CASING
LP LAP 6" REVEAL
STONE VENEER
LP LAP 4" REVEAL
LP SHINGLES
COVERED VENT
LP LAP 6" REVEAL
5" CASING
LP LAP 4" REVEAL
COVERED VENT
LP LAP 6" REVEAL
STONE VENEER
.'#5+0)1((+%'/#+06#0%'2#46;411/%#4'6#-'4#22#46/'06(4106'.'8#6+10Á
4'#4'.'8#6+10Á4+)*6'.'8#6+10Á.'(6'.'8#6+10Á'ICP&TKXG5VG5CXCIG/02JQPG9GDYYYMLYCNMEQO24'.+/Á
24'.+/Á
5KFKPI
5VQPG
4GXKUGFÁ
ExposedPicketDesignsCoveredPicketDesignsSpecialtyDesignsWireFenceDesignsMatch the styles seen here with actual product installations on our website at www.jerith.comREV011414ORNAMENTAL Fencesof Distinction™American SeriesLibertyECONOMYHEAVY DUTYResidentialAeroRegencyIndustrialEP-1These designs have no top rail, and are classic “wrought iron” designs that have been used for over 100 years.A smooth top rail makes these styles perfect around pools. These are our most popular designs because of this. Their aluminum construction makes them ideal for pool enclosures since they can never rust.These fences have a narrower space between the pickets to keep pets inside your yard. The spacing also makes it very difficult for children to obtain a foothold on the fence.Jerith’s Patriot line of wire fence is a great alternative to aluminum fence that’s strong, but has a more subtle visual presence that blends in with the environment.To see our full line of wire fence alternatives, download the Patriot Wire Fence Style Guide ALUMINUM FENCEWIRE FENCEFINIALS, GATES, ARBORS AND LATCHESJerith has a wide variety of scrolls, finials and other items to accent your Jerith fence. Gates are also available to match any of our fence designs, and we have aluminum arbors to highlight a walkway or gate into your yard. ACCESSORIESAVAILABLE GRADESAligned picketsStaggered pickets Aligned pickets with finialsAligned pickets withflush bottom railAligned pickets with finialsand flush bottom railEP-2EP-3EP-5EP-6CP-1Aligned picketsStaggered pickets Staggered pickets with finialsAligned picketswith flush bottom railStaggered picketswith flush bottom railCP-2CP-3CP-4CP-5Two rail designCP-6SP-1Aligned pickets with top rail Staggered pickets with top rail Aligned pickets Pickets with top rail andcombination picket spacingLoops and open picketsSP-2SP-3SP-4EP-4Technical specifications are available on our website with available heights and accessories.Jerith Manufacturing Company, Inc.14400 McNulty Road, Philadelphia, PA 19154215-676-4068 • Fax 215-676-9756Call Toll Free 800-344-2242ALUMINUM FENCESTYLE GUIDE
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2016 - 85
A RESOLUTION APPROVING THE PLANNED UNIT DEVELOPMENT (PUD)
MASTER DEVELOPMENT PLAN WITH REZONING FOR
ROSEWOOD COMMONS
WHEREAS, the Community Development Department of the City of Rosemount received an
application from Copperhead Development Inc. and Warren Israelson requesting a Planned Unit
Development (PUD) Master Development Plan with Rezoning concerning property legally
described as:
Lot 1 Block 1 of the Greif Addition
Together with:
Lot 1 Block 2 of the Rosewood Village 3`d Addirion;Dakota County,Minnesota.
WHEREAS, on November 22, 2016,the Planning Cotni ussion of the City of Rosemount held a
public hearing and reviewed the PUD Master Development Plan; and
WHEREAS, on November 22, 2016, the Planning Con unission recommended approval of the
PUD Master Development Plan, subject to conditions; and
WHEREAS, on December 20, 2016, the City Council of the City of Rosemount reviewed the
Planning Coinmissiods recommendations.
NOW,THEREFORE, BE IT RESOLVED, the Council of the City of Rosemount hereby
approves the Planned Unit Development Master Plan with the rezoning of the property from BP-
Business Park and R1-Low Density Residential, subject to the following conditions:
a) Execution of a PUD Agreement.
b) Approval of a Comprehensive Plan Amendment reguiding the property to HDR
c) The preliminary development plans are approved for no more than seven apartment
buildings and 225 dwelling units. However, final approval for a seventh apartment building
32 additional units) is subject to completion of a parking study after construction of the
third apartment building in development phase three. If the City Council finds that adequate
parking has been provided for the all existing structures, the seventh unit may be
incorporated as shown in the preliminary development plans. If the City Council determines
that there is a parking shortage, the preliminary plans will be amended to eliminate a
building,anticipated as building number three (Phase 5) from the plans.
d) A deviation from City Code Section 11-6-1H to allow the office and public gathering space
to share parking otherwise required for the apartment use.
e) Payment in lieu of replacement trees up to $11,700 should there be no additional reasonable
locations for tree plantings.
The developer shall consider the use of sound insulating materials for portions of any
buildings that will be facing the railroad right-of-way.
RESOLUTION 2016-`
g) Incorporation of recommendations from the City Engineer in a review memorandum dated
November 22,2016 relative to drainage,grading, street design,easements,utilities and the
adjacent sidewalks.
h) Pay a fee in lieu of park land dedication for 225 units consistent with the most recent fee
schedule as adopted by the City Council. The payment of these fees shall be collected at the
time a building permit is issued for each building.
i) Construction of the emergency vehicle access connecting to Lower 147`' Court West must
be completed as part of the fourth phase. Maintenance of the emergency vehicle access
through the railroad spur and up to the Lower 147' Court West cul-de-sac shall be the
responsibiliry of the developer and/or the Rosewood Crossing HOA. These maintenance
responsibilities will include snow removal, signage,pavement markings, and other
requirements specified in Resolution No. 2010-44 approving the Rosewood Village Third
Addition.
j) Provision of contact information for the caretaker or other responsible party in the absence
of a caretaker must be submitted to the city.
k) The applicant is responsible for reconstruction of shared access drive with El Dorado
Packaging and all costs associated with this construction.
1) Repair and maintenance of all private trails and sidewalks are the responsibility of the
developer and/or homeowners association(s). Snow removal from all public and private
trails and sidewalks shall be the responsibility of the developer and/or homeowners
association(s.
m) Entry monuments shall be subject to sign permits and normal zoning standards.Appropriate
sight distances must be maintained.
n) The applicant shall obtain final site and building plan approval from the City prior to any
site work or issuance of building permit. The Plans should address the following items:
The construction and installation of the decorative fence shall coincide with the
timing of construction of apartment buildings within each phase. Submission of
details for the decorative fence prior to the approval of a final plan for the first
phase.
Submission of finallandscape plan that meets ordinance criteria for site and
foundation plantings,landscape screening and buffering. includes:
Realignment of the sidewalk at least four feet from parking and driving areas when
said sidewalk is not located in front of a building. Sidewalks adjacent to parking areas
shall be increased to 7 feet.
Revision of the main entrance road to include sufficient vehicle stacking areas as
required by the City Engineer.
All garbage storage areas and dumpsters must meet City ordinance standards for
construction and screening,including fire code separarion requirements.
Submission of detailed plans for the playground area.
2
RESOLUTION 2016-
A Final Phasing Plan that addresses installation of landscaping,paving,utilities, and
parking. A temporary turn-around shall be provided on the site prior to the
construction of the second or any subsequent apartment buildings. No more than
three of the apartment buildings may be constructed before the emergency vehicle
access,with curbing on both sides through the adjacent parking lot,providing a
connection to Lower 147`'' Court West is installed and connected to the built
porrions of the site.
Exterior building materials are limited to no more than 60%lap siding not including
doors and windows.All other primary materials will be limited to brick or natural
stone. Final architectural plans shall be submitted with any final PUD development
plans. The final development plans shall include exterior material samples and colors.
A lighting plan that includes details about parking lot lighting standards and a
photometric plan which conforms to the City's lighting ordinance.
ADOPTED this 20`'' day of December,2016, by the City Council of the City o osemount.
William H. Droste,Mayor
ATTEST:
larissa adler, City Clerk
3
MEMORANDUM
DATE: May 23, 2017
TO: Kyle Klatt, Senior Planner
CC: Kim Lindquist, Community Development Director
John Morast, Director of Public Works/City Engineer
Amy Roudebush, Planning and Personnel Secretary
FROM: Mitch Hatcher, Project Engineer
RE: Rosewood Crossing Engineering Review
SUBMITTAL:
Prepared by KJ Walk, Rosewood Crossing dated July 18, 2016, updated January 10, 2017. The
review comments were generated from the following documents included in the submittal:
Plan comprised of the following:
▫ Site Plan
▫ Grading & Erosion Control Plan (Updated 5/15/17)
▫ Utility Plan
▫ Landscape Plan
▫ Details
▫ Phasing Plan (Updated 4/25/17)
GENERAL COMMENTS:
1. Development fees are required based on the current Schedule of Rates and Fees. The
estimated development fees are listed below:
Storm Sewer Trunk Charge: $ 6,865 / acre
Sanitary Sewer Trunk Charge: $ 1,075 / acre
Watermain Trunk Charge: $ 6,500 / acre
2. A Subdivision Agreement will be required for the installation of public utilities. The city is
currently preparing the agreement. The agreement will go to council for approved at the
same time as the final plat.
3. Existing conditions and removal plan should be included for review.
4. Typical cross section and pavement sections should be provided for the drive and parking
areas.
5. The developer is required to obtain a NPDES construction Stormwater Permit and provide
a copy of the approved SWPPP to the City prior to the start of any construction activity.
6. Street and utility construction shall be installed in accordance with the 2015 City of
Rosemount General Specifications and Standard Detail Plates and the Engineering
Guidelines.
7. Final construction plans and specifications for street and utilities should be submitted to the
City for review.
8. City inspection of utility installation is required during construction.
9. Upon completion of the sanitary sewer, watermain, and storm sewer construction, the City
requires record drawings. See Engineering Guidelines for submittal and formatting
requirements.
UTILITY COMMENTS:
10. All required agreements with the railroad for the utility crossings should be secured by the
developer.
11. Developer is responsible for obtaining MPCA Sanitary Sewer Extension Permit and MDH
Watermain Permit.
12. Hydrant spacing should be approved by the Fire Marshal.
13. Watermain is required to be DIP CL 52.
14. Existing sanitary stub provided at Lower 147th Ct is 8” not 10”.
STORMWATER COMMENTS:
15. Two-foot sump catch basin is required prior to discharging to Pond A.
16. It is recommended that street grades are a minimum of 1.0%. Several locations show street
grades to be less than 1.0%.
17. It is recommended catch basins are placed in the curb line to collect drainage. Some are
shown in the parking stalls and drive lanes.
18. Additional catch basins may be required. Inlets are generally required every 300’. Inlets
should be located such that 3 cfs is the maximum flow at the inlet for the 10-yr design event
and does not exceed the applicable spread and run design.
Should you have any questions or comments regarding the items listed above, please contact me at
651-322-2015.