HomeMy WebLinkAbout8.a. City Project UpdateCity Project NumberProject NameCouncil Authorizes Plans/SpecsPublic HearingCouncil Receives Plans/Specs Authorize Ad For BidOpen BidsAward ContractStart DateAssessment HearingContractorContract AmountWork Certified To-Date% CompleteSummary416 Well 16 10/01/13 N/A 11/18/14 02/27/15 03/17/15 05/26/15 N/AE.H. Renner & Sons, Inc.$433,105 $380,658 88% Drilling of the production well is complete. Well house design is underway, with construction anticipated in 2017.447145th Street Pedestrian Improvements at RR Crossing01/02/13 N/A N/AUPRR, CPRR, TBDAgreement already in place with Union Pacific. Easement Agreement signed by Canadian Pacific. An agreement with CP for the track extensions can be established now that the easement agreement has been executed. Upon execution of the agreement with CP for the track extensions, work will begin. Sidewalk work will begin after railroad work.465132nd Street West ImprovementsN/ACouncil received the feasibility report and assessment agreement on October 6, 2015. This project is on hold until the status of the Dunmore project is determined.467Dunmore 1st AdditionN/AThis development includes 30 single-family homes by developer Copper Creek. Copper Creek is expected to administer the contract privately. A subdivision agreement has been reviewed by attorneys from both parties; it is expected to be approved at the June 20 City Council meeting.4702017 Street Improvement Project12/20/16 05/02/17 02/21/17 03/24/17 05/02/17 06/01/17 05/02/17McNamara Contracting$934,5602017 Street improvement project includes pavement reconstruction of Shannon Parkway from CSAH 42 to CSAH 46, and mill and overlay of the Shannon Hills neighborhood (Cobbler Ave, Crocus Way, Cranberry Way, Clover Lane). Construction will begin June 19 and be completed by the end of August.473Prestwick Place 13thN/A N/A N/AThis development includes 28 single-family homes by developer KRB Development I, Inc. Sidewalks are installed; wear course will be completed be the end of summer. 474 Greystone 5th N/A N/A N/AThis development includes 23 single-family homes by developer CalAtlantic Homes (formerly Ryland Homes). The developer will administer the contract privately. Street and utilities are inctalled, sidewalk and wear course will be installed by fall. 475 Bella Vista 5th N/A N/A N/AThis development includes 41 single-family homes by developer US Home Corporation (Lennar). The developer is administering the contract privately. Construction is in progress.476Rosewood CommonsN/A N/A N/AThis development includes 7 apartment buildings (one building is expected to be completed in 2017). The project will be designed and constructed privately. The subdivision agreement is expected to be approved at the June 20 City Council meeting.ENG-181Wells 4 & 5 Sealing, New Observation WellN/A 09/01/15 09/29/15 11/17/15 On Hold N/AKeys Well Drilling$39,250 $31,750 81%Well 4 has been converted to an observation well but does not yet have the logger installed. Well 5 has been drilled out, ready to be sealed in the future. Final payment was authorized by Council on October 18, 2016.ENG-188Parking Lot ImprovementsN/A N/ASpring 2017N/A Valley Paving $333,611Connemara Park, Jaycee Park, and City Hall parking lots are scheduled for maintenance in 2017. Improvements will include curb & gutter enhancements/replacement, as well as full pavement replacement. City Hall parking lot is currently in progress, with curb, gutter and base course paving complete. Jaycee Parking lot will be completed with the 2017 Street Improvement project, and construction on Connemara Parking lot will begin in August. 2017-01 Greystone 6th 04/04/17 N/A 05/16/17 06/14/17 06/20/17 07/05/17 N/AFriedges Contracting$1,073,557This development includes 27 single-family homes by developer CalAtlantic Homes (formerly Ryland Homes). The project will be a public city project, with the contract expected to be awarded to Friedges Contracting at the June 20 City Council meeting. Construction is expected to begin July 5. 2017-02 Harmony Villas N/A N/ASummer 2017N/AThis development will be done in two phases, with 16 townhomes in the first phase and 26 townhomes in the second phaase. Both phases will be designed and constructed privately. The subdivision agreement for the first phase is expected to be approved at the June 20 City Council meeting.2017-03RCC and Cameo Ave Parking Lot ImprovementsN/A N/A 05/25/17 06/06/17 06/19/17 N/A Hardrives, Inc. $530,687The Rosemount Community Center and National Guard parking lot will receive a full-depth pavement replacement. Parking improvements along Cameo Avenue will include angled parking to replace the existing parallel parking. The Cameo avenue improvements are in progress; the National Guard portion of the Community Center improvements are in progress, the community center portion will begin August 1 and be completed by September 15.2017-07Prestwick Place 14thN/A N/A N/AThis development includes 38 single-family homes by developer KRB Development I, Inc. The developer will administer the contract privately. Final Plat is schedule for the June 27 Planning Commission meeting. PRIVATEPRIVATEPRIVATEPRIVATEPRIVATEPRIVATEPRIVATEPRIVATEPRIVATECity Projects UpdatePRIVATEPRIVATEPRIVATEPRIVATEPRIVATEG:\ENGPROJ\Project Tracking\Project UpdateUpdated: 6/16/2017