HomeMy WebLinkAbout6.g. Order Project Authorize Plans and Specifications – 132nd Street Improvements – City Project 465EXECUTIVE SUMMARY
City Council Regular Meeting: July 18, 2017
AGENDA ITEM: Order Project / Authorize Plans and
Specifications – 132nd Street
Improvements – City Project 465
AGENDA SECTION:
Consent
PREPARED BY: Mitch Hatcher, PE, Project Engineer AGENDA NO. 6.g.
ATTACHMENTS: Final Design Proposal, Resolution, Map APPROVED BY: LJM
RECOMMENDED ACTION: Motion to Adopt a Resolution Ordering the Project, and
Authorizing the Plans and Specifications for 132nd Street Improvements – City Project 465.
BACKGROUND
At the October 6, 2015, City Council meeting, Council received the Feasibility Report for the 132nd
Street Improvement Project. No action has been taken since this meeting as the project is dependent on
the construction of the adjacent Dunmore subdivision. As the Dunmore subdivision agreement and final
plat were approved at the June 20, 2017, City Council meeting, and all development-related fees have now
been paid, final design of the 132nd Street Improvements can now commence.
The proposed project includes the upgrade of approximately 600 feet of
rural gravel roadway to urban roadway along with the extension of trunk utility systems. The
proposed improvements consist of:
Upgrade of existing rural gravel roadway including:
▫Bituminous pavement with concrete curb & gutter
▫Storm sewer
▫Bituminous trail
Extension of trunk municipal utilities including:
▫8 inch sanitary sewer
▫16 inch water main
The attached proposal from WSB & Associates details the scope and fee for final design.
The total estimated project cost for 132nd Street West Improvements is $426,431. The project is proposed
to be funded from a combination of the following funding sources:
Sanitary Sewer Core Funds, Water Core Funds, and Storm Core and Utility Funds
Special Assessments to benefitting properties
Only the surface and water main improvements and are proposed to be assessed to benefitting
property owners. Assessments to the surrounding properties are proposed to be collected by
agreement.
SUMMARY
Staff recommends Council adoption of a resolution ordering the project, and authorizing the preparation
of plans and specifications for 132nd Street Improvements – City Project 465.
701 Xenia Avenue South | Suite 300 | Minneapolis, MN 55416 | (763) 541-4800
Building a legacy – your legacy.
Equal Opportunity Employer | wsbeng.com K:\01928-710\Admin\Docs\Final Design Proposal\LTR Proposal - 132nd Street Final Design.docx
July 12, 2017
Mr. Logan Martin
City Administrator
City of Rosemount
2875 145th Street West
Rosemount, MN 55068
Re: Scope and Estimated Fee to Provide Professional Engineering Services for
132nd Street Improvement Project - Final Design
Dear Mr. Martin:
We appreciate the opportunity to present this proposal for professional services related to the 132nd
Street Improvement Project. This letter proposal outlines the services required to prepare all necessary
documents to complete plans and specifications.
PROJECT BACKGROUND
At the October 6, 2015 City Council meeting, Council received the Feasibility Report for the 132nd Street
Improvement Project. No action has been taken since this meeting as the project is dependent on the
construction of the adjacent Dunmore subdivision. As the Dunmore subdivision agreement and final plat
were approved at the June 20, 2017 City Council meeting, and all development-related fees have now
been paid, final design of the 132nd Street Improvements can now commence.
The 132nd Street Improvement Project includes upgrading the existing gravel roadway to an urban section
with bituminous pavement, curb and gutter, sanitary sewer, watermain, and storm sewer.
The schedule for the project is to begin construction in September 2017 and it is anticipated that
construction will be completed in October 2017.
PROJECT APPROACH/SCOPE OF SERVICES
WSB’s project scope and proposed work plan are based on our understanding of the project as
previously described and contained within the feasibility report. In order to complete the project, we
propose the following scope of services:
Final Design
WSB will complete final design services, including, but not limited to:
Plans and specifications
Quantity and cost estimates
Assessment rolls and calculations
Bidding documents
Staff reports
City Council meetings
Logan Martin - City of Rosemount
July 12, 2017
Page 2 of 2
K:\01928-710\Admin\Docs\Final Design Proposal\LTR Proposal - 132nd Street Final Design.docx
SCHEDULE
WSB will complete the project for a construction start date of September 2017. Following is a proposed
detailed schedule:
Authorize Preparation of Plans and Specifications July 18, 2017
Receive Plans and Specifications/Ratify Ad for Bid August 15, 2017
Bid Opening August 25, 2017
Award Contract September 5, 2017
Begin Construction September 11, 2017
Substantial Completion October 31, 2017
PROPOSED FEE
We propose to conduct Final Design work on an hourly basis for an estimated fee of $26,616.
We will review our progress weekly and will not exceed this amount without your prior approval should the
scope of the project change.
This letter represents our entire understanding of the project scope. If you are in agreement, please sign
on the space provided and return one original signed copy to us for our records. We will start
immediately upon receipt of the signed agreement.
If you have any questions concerning the work plan or fee as discussed, please feel free to contact me at
(763) 287-7191. We look forward to working with you and greatly appreciate the opportunity to assist you
and your staff in the completion of this project.
Sincerely,
WSB & Associates, Inc.
Monica Heil, PE
Senior Project Manager
Attachment
cc: Mitch Hatcher, WSB & Associates, Inc.
Andy Brotzler, WSB & Associates, Inc.
ACCEPTED BY: CITY OF ROSEMOUNT, MN
I hereby authorize WSB & Associates, Inc. to complete the services identified above not to exceed
$26,616 without prior approval.
Signature: Date:
Name:
Title:
Task Description11.1 Surveying 81624$3,720.001.2 Design 10 30 1656$7,062.001.3 Specifications 6 8 822$2,536.001.4 Quantity Tabulations and Cost Estimate 2 810$1,192.001.5 Meetings 2 6 614$1,954.001.6 Utility Coordination 12 1224$3,228.001.7 QA / QC 2 66822$2,868.001.8 Bidding Preparation and Analysis 8 8 824$2,856.001.9 City Coordination2020$1,200.00Task 1 Total Estimated Hours and Fee 4 50 72 20 24 22 16 8 216 $26,616.00Total Estimated Hours 4 50 72 20 24 22 16 8 216Average Hourly Billing Rate170.00 160.00 109.00 60.00 137.00 88.00 164.00 130.00Total Fee by Labor Classification $680.00 $8,000.00 $7,848.00 $1,200.00 $3,288.00 $1,936.00 $2,624.00 $1,040.00 $26,616.00TOTAL PROJECT COST $26,616.00Total HoursConstruction SpecialistFinal DesignProject EngineerProject ManagerProject Engineer (City Billing Rate)Engineering TechnicianEstimate of CostCity of Rosemount, MinnesotaProfessional Engineering Services132nd Street Improvement Project - Final DesignEstimated HoursPrincipalAdminTwo Person Survey CrewCost
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2017 -
A RESOLUTION ORDERING PROJECT AND
AUTHORIZING THE PREPARATION OF THE PLANS AND SPECIFICATIONS FOR
132ND STREET WEST IMRPOVEMENTS
CITY PROJECT 465
WHEREAS, the City Council received and accepted the Feasibility Report on October 6, 2015 for
City Project 465
NOW THEREFORE BE IT RESOLVED, the City Council of the City of Rosemount hereby
orders the improvements of the 132nd Street Improvements – City Project 465.
BE IT FURTHER RESOLVED, the City Engineer is hereby ordered to prepare plans and
specifications for said improvements of City Project 465.
ADOPTED this 18th day of July, 2017.
______________________________
William H. Droste, Mayor
ATTEST:
Clarissa Hadler, City Clerk
?§A@
COACHFORDDODD BLVD132ND CT W
S ROBERT TRL (STH 3)CT1 3 6 T H S T W
131 ST ST W
B R ASSPKWY
BONAIRE PATH W
C H A R L S TO N WAY BOLIVIA AVE WBRI
LLI
ANTBLANCA AVE WS T W
CHARLSTONAVECOUCHTOWN136TH ST W
COLESHIRE PATHCORLISS TRL
137TH ST
CORCORANAVECORCHMANAVEBLANCA AVE W1 2 8 T H
COUCH-TOWNCORLISS132ND ST W
1 3 5 T H S T W
1 3 3 R D S T
BRI
CK PATHWAY AVEBRASS PKWYGEM AVEB R O N Z ECT
COACHFORDAVECAR RAC
H
WAYC A R R A C H
AVE
CARRACHAVEAVECONNEMARAWAYCOACHFORDPATHCOUCHTOWN CTC
O
UCHTOWN
C
T
TRLBROCKCARLINGFORDCARLINGFORDLANE134TH ST W
BRICK PATHWAYDODD BLVDCARBURYWAY1 3 5 T H S T WBRONZE PKWY133R D ST
BRONZE PKWYBUTTERFLY PATH1 3 4 T H S T
CARBURYAVECOA C HFORDAVE
KEEGANLAKE
BrockwayPark
BrockwayParkT:/GIS/City/Maps/Departmental Maps/Engineering/Chris/Location Map - 465132nd Street West Improvements
City Project 465, May 2015