HomeMy WebLinkAbout8.a. City Projects UpdateCity Project NumberProject NameCouncil Authorizes Plans/SpecsPublic HearingCouncil Receives Plans/Specs Authorize Ad For BidOpen BidsAward ContractStart DateAssessment HearingContractorContract AmountWork Certified To-Date% CompleteSummary416 Well 16 10/01/13 N/A 11/18/14 02/27/15 03/17/15 05/26/15 N/AE.H. Renner & Sons, Inc.$433,105 $380,658 88% Drilling of the production well is complete. Well house design is underway, with construction anticipated in 2017.447145th Street Pedestrian Improvements at RR Crossing01/02/13 N/A N/AUPRR, CPRR, TBDAgreement already in place with Union Pacific. Easement Agreement signed by Canadian Pacific. An agreement with CP for the track extensions can be established now that the easement agreement has been executed. Upon execution of the agreement with CP for the track extensions, work will begin. Sidewalk work will begin after railroad work.465132nd Street West ImprovementsN/A 07/18/17 08/25/17 09/05/17 N/ACouncil authorized plans and specs on July 18. Bids will be opened August 25. Construction to begin in September and will be complete by November. 467Dunmore 1st AdditionN/AFriedges ContractingThis development includes 30 single-family homes by developer Copper Creek. Copper Creek will administer the contract privately. A subdivision agreement has been approved. Currently the site is being mass graded. Street and Utility construction will begin in September and be finished by November. 4702017 Street Improvement Project12/20/16 05/02/17 02/21/17 03/24/17 05/02/17 06/01/17 05/02/17McNamara Contracting$934,560 $126,494 14%2017 Street improvement project includes pavement reconstruction of Shannon Parkway from CSAH 42 to CSAH 46, reconstruction of Jaycee Park parking lot, and mill and overlay of the Shannon Hills neighborhood (Cobbler Ave, Crocus Way, Cranberry Way, Clover Lane). The Jaycee Park parking lot is complete. Construction on Shannon Parkway is scheduled to conclude on August 11. Construction in the Shannon Hills neighborhood is scheduled to begin August 8 and be completed by August 31. 473Prestwick Place 13thN/A N/A N/AThis development includes 28 single-family homes by developer KRB Development I, Inc. Sidewalks are installed; wear course will be completed by the end of summer. 474 Greystone 5th N/A N/A N/AThis development includes 23 single-family homes by developer CalAtlantic Homes (formerly Ryland Homes). The developer will administer the contract privately. Street and utilities are installed, sidewalk and wear course will be installed by fall. 475 Bella Vista 5th N/A N/A N/AThis development includes 41 single-family homes by developer US Home Corporation (Lennar). The developer is administering the contract privately. The site is currently being mass graded, street and utility construction will follow in September. 476Rosewood CommonsN/A N/A N/AThis development includes 7 apartment buildings (one building is expected to be completed in 2017). The project will be designed and constructed privately. The site is currently being mass graded. ENG-181Wells 4 & 5 Sealing, New Observation WellN/A 09/01/15 09/29/15 11/17/15 On Hold N/AKeys Well Drilling$39,250 $31,750 81%Well 4 has been converted to an observation well but does not yet have the logger installed. Well 5 has been drilled out, ready to be sealed in the future. Final payment was authorized by Council on October 18, 2016.ENG-188Parking Lot ImprovementsN/A N/ASpring 2017N/A Valley Paving $333,611 $261,680 78%Connemara Park and City Hall parking lots are scheduled for maintenance in 2017. Improvements will include curb & gutter enhancements/replacement, as well as full pavement replacement. City Hall parking lot is complete. Construction on the Connemara Park lot will occur August 7 through August 25. 2017-01 Greystone 6th 04/04/17 N/A 05/16/17 06/14/17 06/20/17 07/05/17 N/AFriedges Contracting$1,073,557This development includes 27 single-family homes by developer CalAtlantic Homes (formerly Ryland Homes). The project is a public city project, with the contract awarded to Friedges Contracting at the June 20 City Council meeting. Construction began in July and will be substantially complete in September. Sidewalk and wear course will be in 2018. 2017-02 Harmony Villas N/A N/ASummer 2017N/AThis development will be done in two phases, with 16 townhomes in the first phase and 26 townhomes in the second phase. Both phases will be designed and constructed privately. The subdivision agreement for the first phase was approved at the June 20 City Council meeting.2017-03RCC and Cameo Ave Parking Lot ImprovementsN/A N/A 05/25/17 06/06/17 06/19/17 N/A Hardrives, Inc. $530,687 $75,304 14%The Rosemount Community Center and National Guard parking lot will receive a full-depth pavement replacement. Parking improvements along Cameo Avenue will include angled parking to replace the existing parallel parking. The Cameo avenue improvements are complete. The National Guard portion of the Community Center lot is complete. The City portion began August 1 and will be completed by September 15.2017-07Prestwick Place 14thN/A N/A N/AThis development includes 38 single-family homes by developer KRB Development I, Inc. The developer will administer the contract privately. The site is currently being mass graded with street and utility construction to follow in September. PRIVATEPRIVATEPRIVATEPRIVATEPRIVATEPRIVATEPRIVATEPRIVATEPRIVATECity Projects UpdatePRIVATEPRIVATEPRIVATEPRIVATEPRIVATE\\rosemount9\Data\PWorks\ENGPROJ\Project Tracking\Project UpdateUpdated: 8/10/2017