HomeMy WebLinkAbout5.b. Renewal of the Vesterra, LLC and Stonex, LLC, Small Scale Mineral Extraction Permit for 2018
EXECUTIVE SUMMARY
Planning Commission Meeting: November 28, 2017
Tentative City Council Meeting: December 19, 2017
AGENDA ITEM: Case 17-42-ME Renewal of the Vesterra,
LLC, and Stonex, LLC, Small Scale
Mineral Extraction Permit for 2018
AGENDA SECTION:
Public Hearing
PREPARED BY: Anthony Nemcek, Planner AGENDA NO. 5.b.
ATTACHMENTS: Location Map, Draft 2018 Mining Permit,
Site Plan, Applicant’s Narrative APPROVED BY: K.L.
RECOMMENDED ACTION: Motion to recommend the City Council renew the Vesterra,
LLC., and Stonex, LLC., Small Scale Mineral Extraction Permit for 2018 and extend the
permit expiration date by two years.
SUMMARY
Applicant: Jonathan Wilmshurst of Vesterra, LLC and Stonex, LLC
Property Owner: Flint Hills Resources
Operator: Solberg Aggregates
Location: South of Bonaire Path, ¼ mile west of Blaine Ave.
Area in acres: Vesterra – Northern 75 Acres along Bonaire Path
Stonex – Southern 80 Acres directly south of Vesterra.
Comp Plan Designation: LI, Light Industrial
Current zoning: AG, Agriculture
Material removed in 2017: approx. 70,000 through October
The applicant, Jonathan Wilmshurst of Vesterra LLC/Stonex LLC, requests renewal of the Vesterra and
Stonex mineral extraction permit for 2018. The subject properties are located south of Bonaire Path, ¼ mile
west of Blaine Avenue (County Road 71). The properties are owned by Flint Hills Resources which leases
them back to the applicant for mineral extraction. While Flint Hills Resources and Vesterra, LLC/Stonex,
LLC are parties to this application, the responsibility for securities and compliance with the conditions
remains with Vesterra and Stonex as the property lessee. Upon review of the mineral extraction standards,
police records and the information submitted by the applicant, staff recommends renewal of the permit for
2018.
BACKGROUND
The applicant received their last annual permit renewal in January of 2017. At that time there were no
issues associated with the activity at the mine, which is still the case. According to the applicant, the 2017
activity increased due to the improved market for construction aggregates. Approximately 70,000 tons
were removed from the site in 2017 compared to 35,000-40,000 tons removed in 2016. No fill was
brought into the site during 2017. Mining will continue moving northwest and southwest in Phases 2, 3, 4,
and 7, but no activity is expected to the east. Solberg intends to install an above-ground scale once
business levels justify it.
2
The permit states that completion date for mineral extraction, including reclamation, shall be no later than
December 31, 2018 for the northern 75 acres and December 31, 2022 for the southern 80 acres. The
applicant does not expect to meet that deadline, and staff is recommending the completion date be
extended an additional 2 years for both the northern and southern sections of the site. At that time, the
applicant and staff will have a better understanding of where the market is for construction aggregates and
how long the extraction process can realistically be expected to take.
ISSUE ANALYSIS
Standards for Small Scale Mineral Extraction are detailed in Section 11-10-4 of the City Code. A summary
review of the subject property is provided below with more detailed conditions of operation listed in the
attached Draft 2018 Conditions for Mineral Extraction Permit. This use meets or exceeds the applicable
performance standards for small scale mineral extraction subject to the conditions listed in the attached
permit. Staff has toured the site and checked with the police to assess whether there were any complaints
relating to the mining operation. The site visit illustrated that the mine appears to be operating in
compliance with the permit; there were no public complaints cataloged with the police for 2017.
The subject property is zoned AG - Agriculture. Small scale mineral extraction is listed as an interim use
within this district. The table below details the zoning, current land use, and future land use information
for the surrounding properties. The sites to the west, south, and east are located within the current
Metropolitan Urban Service Area (MUSA). It should be noted that some of the agriculture uses include
associated residential uses and the applicant has a farming tenant operating on a portion of the subject
property outside the active mining area.
Surrounding Land Use and Zoning Information
Direction Current Land
Use
Guided Land Use Zoning
North Agriculture Agriculture Agriculture
South Agriculture Medium Density Residential (west half)
Business Park (east half) Agriculture
East Agriculture Light Industrial Agriculture
West Agriculture Low Density Residential Agriculture Preserve
Currently, access to both properties comes through a gated entrance at the northeast corner of the
Vesterra property along Bonaire Path. In the future, the applicant plans to shift access from Bonaire Path
to Blaine Avenue (County Road 71) via an internal driveway that crosses the 80 acre parcel to the east
owned by Flint Hills Resources. This will reduce truck traffic on Bonaire Path (a gravel road) and provide
more direct access to County Road 42. When this change is necessary in the future, the applicant will come
back to the City to amend their permit.
CONCLUSION AND RECOMMENDATION
Upon review of these standards, police records, and the information submitted by the applicant, staff
recommends renewal of the Vesterra LLC. and Stonex LLC. Mineral Extraction Permit for 2018. Staff is
also recommending extending the completion date for mineral extraction on the site by two years. The
request is subject to the conditions outlined in the attached permit.
Site
Mineral Extraction Permit
20168 Conditions for Mineral Extraction
Permit VESTERRA, LLC and STONEX, LLC
A. By their signatures below, Vesterra, LLC and Stonex, LLC (hereinafter collectively
referred to as the “Property Lessee") and Flint Hills Resources (herein after “the
Property Owner”) consent to these conditions, binding themselves and their
successors, heirs or assigns to the conditions of this permit. Vesterra, LLC and
Stonex, LLC are jointly and severally liable and responsible for compliance with all
conditions of this permit and all requirements of law relating to the licensed
activities. Mineral Extraction is an Interim Use in the Agriculture District of which
the permit area is a part according to Ordinance B, the City of Rosemount Zoning
Ordinance Regulations. Property Owner consents to entry onto the Subject Property
by the City, the City’s employees, agents, and contractors, as needed to inspect the
work of the permit, enforce the conditions of the permit and undertake any wo rk
needed to comply with permit conditions including mine closing and reclamation.
B. This permit is granted for the area designated as Phases 1, 2, 3, 4, and 7 on
Exhibit 21 Present Conditions and 20168 Mine Plan.
C. The completion date of the overall mineral extraction process including site reclamation shall be no later than December 31, 201208 for the northern 75 acres, the Vesterra site. The completion date of the overall mineral extraction process including site restoration shall be no later than December 31, 2024 for the southern 80 acres, the Stonex site. The term of this permit shall extend from January 1, 20168 until December 31, 20168 unless revoked prior to that for failure to compl y with the permit requirements. A mining permit fee of $370.00 shall be paid to the City of Rosemount.
D. All required permits from the State of Minnesota, County of Dakota and City of
Rosemount (hereinafter "City") or any of their agencies shall be obtained and
submitted to the City prior to the issuance of the permit. Failure by the Property
Lessee to comply with the terms and conditions of any of the permits required under
this paragraph shall be grounds for the City to terminate said mining permit.
E. The final grading for the permit area shall be completed in accordance with the
grading plan labeled Exhibit 2, which is attached hereto, or as approved b y the City
Engineer, and any other conditions that may be imposed by the City from time to
time.
F. All gravel trucks and other mining related traffic shall enter and exit the mining area
from Bonaire Path (County Road 38). It shall be the Property Lessee’s
responsibility to obtain any access permits or easements necessary for ingress and
egress. The location of the accesses and/or easements for ingress and egress shall be
subject to approval by the City, as well as the Dakota County Highway Department
or the Minnesota Department of Transportation if applicable or if any changes occur
Formatted: Highlight
2018 Mining Permit
Vesterra, LLC / Stonex, LLC
2 of 6
relative to the mining process. The current location of the access driveway is indicated on
the Present Conditions and 2018 Mining PlanLocation Map, Exhibit 1. Warning signs
including “Trucks Hauling” shall be installed at the Property Owner’s expense as needed
in accordance with Dakota County requirements. Any street improvements to Bonaire
Path, County Road 71 or CSAH 42 necessary to accommodate the generated traffic shall
be the sole responsibility of the Property Lessee.
G. A plan for dust control shall be submitted to and subject to approval by the City.
The Property Lessee shall clean dirt and debris from extraction or hauling operations
related to the Mineral Extraction Permit from streets. After the Property Lessee has
received 24-hour verbal notice, the City may complete or contract to complete the
clean-up at the Property Lessee’s expense. In the event of a traffic hazard as
determined by the City Administrator (or their designee) or Rosemount Police
Department, the City may proceed immediately to complete or contract cleanup at
Property Lessee’s expense without prior notification.
H. The surface water drainage of the mining area shall not be altered so as to interfere,
contaminate, or otherwise impact the natural drainage of adjacent property.
I. No topsoil shall be removed from the site and the Property Lessee shall take
necessary measures to prevent erosion of the stockpiled topsoil. The location of the
stockpiled topsoil is located on shall be indicated on Exhibit 2, Present Conditions
and 20168 Mine Plan.
J. Any costs incurred now or in the future in changing the location of existing public or
private utilities including but not limited to pipelines, transmission structures and
sewer infrastructure located within the permit area shall be the sole obligation and
expense of the Property Lessee.
K. All costs of processing the permit, including but not limited to planning fees,
engineering fees and legal fees, shall be paid by the Property Lessee prior to the
issuance of the permit. The Property Lessee shall reimburse the City for the cost of
periodic inspections by the City Administrator or any other City employee for the
purpose of insuring that conditions of the permit are being satisfied. The Property
Lessee agrees to reimburse the City for any other costs incurred as a result of the
granting or enforcing of the permit.
L. The daily hours of operation for the mining area shall be limited to 7:00 a.m. to 7:00
p.m., Monday through Saturday subject to being changed by the City Council.
M. The Property Lessee shall deposit with the Planning Department a surety bond or
cash deposit in the amount of Seven Thousand, Five Hundred Dollars per acre
($7,500.00/acre) for any active phase in favor of the City for the cost of restoration,
regrading and/or revegetating land disturbed by mining activities and to ensure
performance of all requirements of this agreement and City ordinances by Property
Lessee. The required surety bonds must be:
2018 Mining Permit
Vesterra, LLC / Stonex, LLC
3 of 6
(1) With good and sufficient surety b y a surety company authorized to do
business in the State of Minnesota.
(2) Satisfactory to the City Attorney in form and substance.
(3) Conditioned that the Property Lessee will faithfully comp ly with all the
terms, conditions and requirements of the permit; all rules, regulations and
requirements pursuant to the permit and as required by the City and all
reasonable requirements of the City Administrator (or his designee) or any
other City officials.
(4) Conditioned that the Property Lessee will secure the City and its officers
harmless against any and all claims, or for which the City, the Council or any
City officer may be made liable by reason of any accident or injury to
persons or property through the fault of the Property Lessee.
(5) The surety bond or cash deposit shall remain in effect from January 1,
20167 until July 31, 20178.
Upon thirty (30) days’ notice to the Property Lessee and surety company, the
City may reduce or increase the amount of the bond or cash deposit during the
term of this permit in order to insure that the City is adequately protected.
N. The Property Lessee shall furnish a certificate of comprehensive general liability
insurance issued b y insurers duly licensed within the State of Minnesota in an
amount of at least Five Hundred Thousand and no/100 ($500,000.00) Dollars for
injury or death of any one person in any one occurrence, and at least One Million
Five Hundred Thousand and no/100 ($1,500,000.00) Dollars for injury or death of
more than one person arising out of one occurrence and property damage liability in
an amount of at least Two Hundred Fifty Thousand and no/100 ($250,000.00)
Dollars arising out of any one occurrence. The policy of insurance shall name the
City as an additional insured and shall remain in effect from January 1, 2018 until
July 31, 2019.
O. No processing or mixing of materials shall occur on the site, except as approved by
the Dakota County Environmental Management Department as incidental to a sand
and gravel mining operation. Any such activities will be enclosed with snow or
cyclone fencing or as approved by City staff. Construction of any ponding areas,
wash plants or other processing or equipment brought to the site shall require
additional site and grading plan information subject to review and approval of the
City Engineer.
P. The Property Lessee and the Property Owner shall hold the City harmless from all
claims or causes of action that may result from the granting of the permit. The
Property Lessee shall indemnify the City for all costs, damages or expenses,
including but not limited to attorney's fees that the City ma y pay or incur in
consequence of such claims.
2018 Mining Permit
Vesterra, LLC / Stonex, LLC
4 of 6
Q. The Property Lessee and the Property Owner shall comply with such other
requirements of the City Council as it shall from time to time deem proper and
necessary for the protection of the citizens and general welfare of the community.
R. Complete mining and reclamation is required in all phases before any additional
mining is authorized. Modifications or expansion of the mining areas must be
approved in writing to the City. Property Lessee shall submit to the City semi-
annually a written report indicating the amount of material extracted from the site
for the prior si12x-month period.
S. The Property Lessee shall incorporate best management practices for controlling
erosion and storm water runoff as specified by the Minnesota Pollution Control
Agency and the United States Environmental Protection Agency.
T. The City of Rosemount shall have the ability to collect independent soil samples
U. Reclamation shall include the replacement of the entire stockpile of topsoil on the
mined area, reseeding and mulching necessary to re-establish vegetative cover for
permanent slope stabilization and erosion control. The minimum depth of topsoil
shall not be less than two inches after reclamation. Topsoil for reclamation shall
conform to specifications on file with the City. No restored slopes may exceed a
gradient of 25% or four to 1 (4:1).
V. The Property Lessee must show how materials stockpiled for recycling will be
processed and inform the City of all stockpiled materials.
W. The Property Lessee may not assign this permit without written approval of the City. The Property Lessee will be responsible for all requirements of this permit and all City ordinances on the licensed premises for the permit period unless the Property Lessee gives sixty (60) days prior written notice to the City of termination and surrenders the permit to the City. The Property Lessee shall identify all Operators prior to their commencement of mineral extraction-related activities in the pit area. The City shall have the authority to cause all mineral extraction activities to cease at any time there is an apparent breach of the terms of this Permit. X. The Property Lessee shall maintain a “stock” gate (or equivalent) at the entrance to the property where the mining operation is located. The gate must be secured at 7:00 p.m. and at any time the pit is not in use. Y. There shall be no “haul-back” of materials from any other property or job site that would be imported to the property for fill or other purposes other than incidental concrete recycling as referred to in paragraphs O, V and FF; and topsoil imported for the purpose of re-establishing turf as accepted by the City. Z. Truck operators within the pit area shall not engage in practices involving slamming tailgates, vibrating boxes, using of “jake” or engine brakes (except in emergency situations) or other such activities that result in excessive noise.
2018 Mining Permit
Vesterra, LLC / Stonex, LLC
5 of 6
AA. The Property Lessee shall comply with directions from the City Engineer. BB. A landscaping plan shall be prepared subject to approval by City Staff, for the purpose of providing vegetative screening within the setback areas of the various phases of the mining area. Said landscaping shall be installed according to City standards, prior to commencement of operations within an adjacent phase area. CC. No retail activity is permitted on the site. Materials imported to the site are limited to materials to be recycled and mixed with aggregate extracted from the site and topsoil for reestablishing ground cover or turf. DD. Off-site mining connected with the reconstruction of County Road 38 or construction of Connemara Trail shall require separate project approval by the City Council. The site reclamation plan with proposed grades and future street alignments is subject to approval by the City Engineer. EE. The storage of equipment (unrelated to the sand and gravel mining and processing), manure, construction debris, or hazardous materials of any kind shall not be permitted on site. The placement of construction debris, manure, asphalt or hazardous materials in any form within the pit as fill shall be strictly prohibited.
FF. The fill area re-grading and reclamation shall follow the procedures described in the Stonex LLC and Vesterra LLC Reclamation Protocol Rosemount, Minnesota. Stonex, LLC and Vesterra, LLC shall compact the entire reclamation site to a minimum compaction of 95% of maximum dry density. Reports shall be submitted
to the City by August 1st and February 1st describing any fill importation from
January 1st through June 30th and July 1st through December 31st respectively. The bi-annual reports submitted shall describe the quantities of material brought in, where the material came from, and the test results, including supporting analytical results of the materials.
IN WITNESS WHEREOF, Vesterra, LLC and Stonex, LLC hereby consents and agrees to the foregoing conditions of said mining permit this day of , 20 .
Vesterra, LLC and Stonex, LLC
By: Jonathan J. Wilmshurst, Owner
2018 Mining Permit
Vesterra, LLC / Stonex, LLC
6 of 6
STATE OF MINNESOTA ) ) ss COUNTY OF DAKOTA )
The foregoing instrument was ackno wledged before me this day of , 20 , by Jonathan J. Wilmshurst, the Owner of Vesterra, LLC and Stonex, LLC
Notary Public
IN WITNESS WHEREOF, Flint Hills Resources, hereby consents and agrees to the foregoing conditions of said mining permit this day of , 20 .
Flint Hills Resources
Its
STATE OF MINNESOTA ) )ss COUNTY OF DAKOTA )
The forgoing instrument was acknowledged before me this day of , 20 , by_ , Flint Hills Resources, Its , the Property Owner, on behalf of the company.
Notary Public