EXECUTIVE SUMMARY
City Council Meeting: January 16, 2018
AGENDA ITEM: Accept Project and Authorize Final
Payment, City Project ENG 0180
AGENDA SECTION:
Consent
PREPARED BY: Brian Erickson, P.E., Director of Public
Works/City Engineer AGENDA NO. 6.i.
ATTACHMENTS: Payment Voucher APPROVED BY: LJM
RECOMMENDED ACTION: Motion to Approve Payment 5 and Final to Max Steininger,
Inc. for the Safe Routes to School Project, City Project ENG 0180 and Accepting it for
Perpetual Maintenance
BACKGROUND:
This item is on the agenda to request approval for Payment 5 and Final to Max Steininger, Inc. for the Safe
Routes to School. Project, City Project ENG 0180.
The final construction amount of $490,263.25 is 8.8% greater than the original contract amount of
$450,549.57. The increase in contract amount is due to the following:
• Unit quantity adjustments during construction – $26,040.61
o Additional tree removal/clearing
o Additional walk removal
o Additional excavation
• Contract change for retaining wall along 144th St. - $13,673.07
SUMMARY:
Staff recommends that Council approve Payment 5 and Final for the Safe Routes to School Project, City
Project ENG 0180 and accept the project for perpetual maintenance subject to the following conditions.
1. Satisfactorily showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax.
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured.
3. Consent of Surety to Final Payment certification from the contractor’s surety.
4. Two-year Maintenance Bond.
Contract Amounts
Original Contract $450,549.57
Contract Changes $13,673.07
Revised Contract $464,222.64
Funds Encumbered
Original $450,549.57
Additional N/A
Total $450,549.57
Work Certified To Date
Base Bid Items $476,590.18
Backsheet $0.00
Change Order $0.00
Supplemental Agreement $0.00
Work Order $13,673.07
Material On Hand $0.00
Total $490,263.25
Amount Paid This Final Pay Voucher $24,513.16
01928-92 $0.00 $490,263.25 $0.00 $465,750.09 $24,513.16 $490,263.25
Percent Retained: 0%
Work Certified
This Pay Voucher
Work Certified
To Date
Less Amount
Retained
Less Previous
Payments
Amount Paid
This Pay Voucher
Total Amount
Paid To Date
I hereby certify that a Final Examination has been made of the noted Contract, that the Contract has been completed, that the
entire amount of Work Shown in this Final Voucher has been performed and the Total Value of the Work Performed
in accordance with, and pursuant to, the terms of the Contract is as shown in this Final Voucher.
CITY OF ROSEMOUNT
2875 145th Street West
Rosemount, MN 55068-4941
Project 01928-92 - Safe Routes to School (144th Street)
Final Pay Voucher No. 5
Contractor: Max Steininger, Inc.
3080 Lexington Avenue South
Eagan, MN 55121
Contract No.
Vendor No.
For Period: 10/31/2017 - 11/30/2017
Warrant # __________ Date ___________
1
Construction Observer:Recommended for Approval by:
WSB & Associates, Inc.
__________________________________ __________________________________
Approved by Contractor:
Max Steininger, Inc.
__________________________________
Approved by Owner:
City of Rosemount
__________________________________
__________________________________
Date:
__________________________________
Specified Contract Completion
Date: 9/30/2016
Comment:
1 08/01/2016 08/31/2016 $246,692.69 $12,334.63 $234,358.06
2 09/01/2016 10/07/2016 $175,625.10 $8,781.26 $166,843.84
3 10/08/2016 11/18/2016 $63,060.02 $3,153.00 $59,907.02
4 11/19/2016 10/30/2017 $4,885.44 $244.27 $4,641.17
5 10/31/2017 11/30/2017 $0.00 ($24,513.16) $24,513.16
Totals: $490,263.25 $0.00 $490,263.25
01928-92 Payment Summary
No. From Date To Date
Work Certified
Per Pay Voucher
Amount Retained
Per Pay Voucher
Amount Paid
Per Pay Voucher
001 450,583.33 0.00 428,054.16 22,529.17 450,583.33
002 26,006.82 0.00 24,706.48 1,300.34 26,006.82
003 13,673.07 0.00 12,989.42 683.65 13,673.07
Totals: $490,263.22 $0.00 $465,750.06 $24,513.16 $490,263.22
01928-92 Funding Category Report
Funding
Category
No.
Work
Certified
To Date
Less
Amount
Retained
Less
Previous
Payments
Amount Paid
This
Pay Voucher
Total
Amount Paid
To Date
01 State 23,829.51 450,549.56 450,549.56 476,590.15
02 Local 683.65 13,673.07 0.00 13,673.07
Totals: $24,513.16 $464,222.63 $450,549.56 $490,263.22
01928-92 Funding Source Report
Accounting
No.
Funding
Source
Amount Paid
This
Pay Voucher
Revised
Contract
Amount
Funds
Encumbered
To Date
Paid To
Contractor
To Date
CITY OF ROSEMOUNT
2875 145th Street West
Rosemount, MN 55068-4941
Project No. 01928-92
Final Pay Voucher No. 5
2
Base Bid
1 2021.501 MOBILIZATION LS $54,923.00 1 0 $0.00 1 $54,923.00
2 2101.501 CLEARING ACRE $5,350.44 0.02 0 $0.00 0.02 $107.01
3 2101.502 CLEARING TREE $802.57 4 0 $0.00 12 $9,630.84
4 2101.506 GRUBBING ACRE $5,350.44 0.02 0 $0.00 0.02 $107.01
5 2101.507 GRUBBING TREE $802.57 4 0 $0.00 12 $9,630.84
6 2104.501
REMOVE WATER
MAIN L F $107.01 13 0 $0.00 13 $1,391.13
7 2104.501
REMOVE CURB &
GUTTER L F $11.64 823 0 $0.00 823 $9,579.72
8 2104.501
REMOVE
RETAINING WALL L F $161.48 3 0 $0.00 3 $484.44
9 2104.501
REMOVE
CONCRETE
RETAINING WALL
L F $158.27 6 0 $0.00 4 $633.08
10 2104.501
REMOVE WOOD
RETAINING WALL L F $28.26 26 0 $0.00 26 $734.76
11 2104.501
REMOVE WOOD
FENCE L F $34.99 21 0 $0.00 21 $734.79
12 2104.503
REMOVE
CONCRETE
WALK
S F $2.93 1379 0 $0.00 2092.5 $6,131.03
13 2104.503
REMOVE
BITUMINOUS
WALK
S F $2.93 729 0 $0.00 1042 $3,053.06
14 2104.503
REMOVE
CONCRETE
DRIVEWAY
PAVEMENT
S F $3.52 2916 0 $0.00 2171 $7,641.92
15 2104.503
REMOVE
BITUMINOUS
PAVEMENT
S F $5.92 1521 0 $0.00 1526 $9,033.92
16 2104.503
REMOVE
BITUMINOUS
DRIVEWAY
PAVEMENT
S F $3.52 235 0 $0.00 234 $823.68
17 2104.509
REMOVE
CONCRETE
STEPS
EACH $484.65 2 0 $0.00 2 $969.30
18 2104.509
REMOVE LIGHT
FOUNDATION EACH $277.01 2 0 $0.00 2 $554.02
19 2104.509
REMOVE
HYDRANT EACH $1,070.09 1 0 $0.00 1 $1,070.09
20 2104.509
REMOVE GUARD
POST EACH $53.50 4 0 $0.00 2 $107.00
21 2104.509
REMOVE SIGN
TYPE C EACH $37.46 4 0 $0.00 3 $112.38
01928-92 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF ROSEMOUNT
2875 145th Street West
Rosemount, MN 55068-4941
Project No. 01928-92
Final Pay Voucher No. 5
3
22 2104.511
SAWING
CONCRETE
PAVEMENT (FULL
DEPTH)
L F $5.83 175 0 $0.00 374 $2,180.42
23 2104.513
SAWING
BITUMINOUS
PAVEMENT (FULL
DEPTH)
LIN
FT $2.39 864 0 $0.00 917.5 $2,192.83
24 2104.523
SALVAGE
LIGHTING UNIT EACH $1,153.66 2 0 $0.00 2 $2,307.32
25 2104.523
SALVAGE SIGN
TYPE C EACH $37.46 10 0 $0.00 12 $449.52
26 2104.523
SALVAGE SIGN
TYPE SPECIAL EACH $37.46 2 0 $0.00 2 $74.92
27 2104.523
SALVAGE
CASTING EACH $374.53 6 0 $0.00 6 $2,247.18
28 2104.523
SALVAGE MAIL
BOX SUPPORT EACH $37.46 18 0 $0.00 37 $1,386.02
29 2104.601
REMOVE
MISCELLANEOUS
STRUCTURES
LS $565.93 1 0 $0.00 1 $565.93
30 2104.602
REMOVE EDGER
BLOCK EACH $16.79 33 0 $0.00 0 $0.00
31 2104.601
SALVAGE
LANDSCAPE
ROCK
SY $53.50 15 0 $0.00 9.5 $508.25
32 2104.618
REMOVE BRICK
PAVERS S F $39.58 14 0 $0.00 10 $395.80
33 2104.618
SALVAGE BRICK
PAVERS S F $32.11 11 0 $0.00 10 $321.10
34 2105.501
COMMON
EXCAVATION C Y $27.72 1417 0 $0.00 1417 $39,279.24
35 2105.507
SUBGRADE
EXCAVATION C Y $27.72 447 0 $0.00 581 $16,105.32
36 2105.522
SELECT
GRANULAR
BORROW (CV)
C Y $30.52 150 0 $0.00 284 $8,667.68
37 2105.522
SELECT
GRANULAR
BORROW MOD
10% (CV)
C Y $34.79 44 0 $0.00 44 $1,530.76
38 2105.523
COMMON
BORROW (CV)C Y $37.97 15 0 $0.00 0 $0.00
39 2123.610
STREET
SWEEPER (WITH
PICKUP BROOM)
HOUR $75.00 30 0 $0.00 28.5 $2,137.50
40 2123.610
1.5 CU YD
BACKHOE HOUR $158.11 5 0 $0.00 0 $0.00
01928-92 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF ROSEMOUNT
2875 145th Street West
Rosemount, MN 55068-4941
Project No. 01928-92
Final Pay Voucher No. 5
4
41 2130.501 WATER MGAL $38.61 20 0 $0.00 20 $772.20
42 2211.503
AGGREGATE
BASE (CV) CLASS
5
C Y $15.00 446 0 $0.00 373 $5,595.00
43 2360.501
TYPE SP 12.5
WEARING
COURSE MIX
(2,B)
TON $149.83 52 0 $0.00 75.7 $11,342.13
44 2402.585 PIPE RAILING L F $135.90 64 0 $0.00 82 $11,143.80
45 2411.511
STRUCTURE
EXCAVATION
CLASS U
C Y $22.67 59 0 $0.00 59 $1,337.53
46 2411.607
CONCRETE
STEPS C Y $481.53 0.2 0 $0.00 0.2 $96.31
47 2411.618
MODULAR
BLOCK
RETAINING WALL
S F $36.65 293 0 $0.00 295 $10,811.75
48 2502.601
IRRIGATION
SYSTEM
PROVISION
LS $3,210.26 1 0 $0.00 1 $3,210.26
49 2502.602
CONNECT TO
EXISTING PIPE
DRAIN
EACH $588.55 2 0 $0.00 2 $1,177.10
50 2503.511
4" PVC PIPE
SEWER L F $80.26 55 0 $0.00 41 $3,290.66
51 2503.541
12" RC PIPE
SEWER DES 3006
CL V
L F $53.50 117 0 $0.00 111 $5,938.50
52 2503.602
CONNECT INTO
EXISTING
DRAINAGE
STRUCTURE
EACH $802.57 2 0 $0.00 2 $1,605.14
53 2504.602 HYDRANT EACH $6,420.52 1 0 $0.00 1 $6,420.52
54 2504.602
ADJUST
HYDRANT EACH $802.57 1 0 $0.00 3 $2,407.71
55 2504.602
6" GATE VALVE &
BOX EACH $2,140.17 1 0 $0.00 1 $2,140.17
56 2504.602
CONNECT TO
EXISTING WATER
MAIN
EACH $1,605.13 1 0 $0.00 1 $1,605.13
57 2504.603
6" WATERMAIN
DUCTILE IRON CL
52
L F $160.51 16 0 $0.00 16 $2,568.16
58 2506.502
CONST
DRAINAGE
STRUCTURE
DESIGN SPECIAL
EACH $2,675.21 2 0 $0.00 2 $5,350.42
CASTING
01928-92 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF ROSEMOUNT
2875 145th Street West
Rosemount, MN 55068-4941
Project No. 01928-92
Final Pay Voucher No. 5
5
59 2506.516 ASSEMBLY EACH $615.30 2 0 $0.00 2 $1,230.60
60 2506.521
INSTALL
CASTING EACH $374.53 6 0 $0.00 6 $2,247.18
61 2521.501
4" CONCRETE
WALK S F $4.98 8620 0 $0.00 9208 $45,855.84
62 2521.501
6" CONCRETE
WALK S F $7.87 2107 0 $0.00 819.9 $6,452.61
63 2521.511
3" BITUMINOUS
WALK S F $1.93 3491 0 $0.00 3360 $6,484.80
64 2531.501
CONCRETE
CURB & GUTTER
DESIGN B618
L F $29.43 879 0 $0.00 823.5 $24,235.61
65 2531.507
6" CONCRETE
DRIVEWAY
PAVEMENT
S Y $66.34 211 0 $0.00 261.4 $17,341.28
66 2531.618
TRUNCATED
DOMES S F $64.20 169 0 $0.00 116 $7,447.20
67 2540.602
INSTALL MAIL
BOX SUPPORT EACH $107.01 18 0 $0.00 31 $3,317.31
68 2540.604
INSTALL
LANDSCAPE
ROCK
S Y $53.50 15 0 $0.00 9.5 $508.25
69 2540.618
INSTALL BRICK
PAVERS S F $32.11 11 0 $0.00 10 $321.10
70 2545.515
LIGHT
FOUNDATION
DESIGN P MOD
EACH $3,108.80 2 0 $0.00 2 $6,217.60
71 2545.602
INSTALL
LIGHTING UNIT EACH $1,912.64 2 0 $0.00 2 $3,825.28
72 2563.601
TRAFFIC
CONTROL LS $3,477.78 1 0 $0.00 1 $3,477.78
73 2564.531
SIGN PANELS
TYPE C S F $42.81 44.5 0 $0.00 47.75 $2,044.18
74 2564.537
INSTALL SIGN
TYPE C EACH $107.01 10 0 $0.00 14 $1,498.14
75 2564.537
INSTALL SIGN
TYPE SPECIAL EACH $133.76 2 0 $0.00 3 $401.28
76 2565.616
PEDESTRIAN
CROSSWALK
FLASHER
SYSTEM
SYS $12,922.78 1 0 $0.00 1 $12,922.78
77 2571.502
DECIDUOUS
TREE 3" CAL B&B TREE $695.56 3 0 $0.00 3 $2,086.68
78 2572.505 PRUNE TREES HOUR $214.02 20 0 $0.00 20.25 $4,333.91
79 2573.502
SILT FENCE,
TYPE MS L F $1.87 3249 0 $0.00 757 $1,415.59
STORM DRAIN
01928-92 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF ROSEMOUNT
2875 145th Street West
Rosemount, MN 55068-4941
Project No. 01928-92
Final Pay Voucher No. 5
6
80 2573.530
INLET
PROTECTION EACH $125.00 10 0 $0.00 10 $1,250.00
81 2573.533
SEDIMENT
CONTROL LOG
TYPE WOOD
FIBER
L F $3.80 1835 0 $0.00 1713 $6,509.40
82 2574.525
BOULEVARD
TOPSOIL
BORROW
C Y $49.66 60 0 $0.00 44 $2,185.04
83 2575.505
SODDING TYPE
LAWN S Y $5.89 2925 0 $0.00 4229.44 $24,911.40
84 2575.571
RAPID
STABILIZATION
METHOD 3
MGAL $428.03 3.9 0 $0.00 0 $0.00
85 2582.503
CROSSWALK
PREF THERMO S F $17.61 311 0 $0.00 764 $13,454.04
Totals For Section Base Bid: $0.00 $476,590.18
Work Order 1 - Ret Wall Construction
86 2411.601
RETAINING
WALLS LS $13,673.07 1 0 $0.00 1 $13,673.07
Totals For Work Order 1 - Ret Wall Construction: $0.00 $13,673.07
Project Totals: $0.00 $490,263.25
01928-92 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
WO1 Work
Order 11/18/2016
This contract includes a retaining wall to be constructed
along 144th Avenue West at 201+79.67 to 202+72.07. The
engineer, in conjunction with the owner, determined that the
safety of pedestrians would be increased if the location of
the wall and sidewalk were changed to a different offset from
the back of curb. This changed condition forced the wall
construction to be halted, the constructed wall section to be
removed, then the wall was constructed in the newer, safer
location. This changed condition also extended the length of
the contract time necessary for the work to be completed.
The Engineer agreed this constituted extra work. Payment
for this work will be as outlined in the estimated quantity
tabulation listed below, which includes all mobilization, labor,
materials, disposal, equipment cost, and Prime Contractor
mark-up where applicable.
$13,673.07 $13,673.07
Contract Change Totals: $13,673.07 $13,673.07
01928-92 Contract Changes
No. Type Date Explanation
Estimated
Amount
Amount
Paid
To Date
CITY OF ROSEMOUNT
2875 145th Street West
Rosemount, MN 55068-4941
Project No. 01928-92
Final Pay Voucher No. 5
7