EXECUTIVE SUMMARY
City Council Regular Meeting: February 5, 2018
AGENDA ITEM: Approve Consulting Contract for
Connemara Trail – East Extension, City
Project 2018-09
AGENDA SECTION:
Consent
PREPARED BY: Brian Erickson, PE, Director of Public
Works/City Engineer AGENDA NO. 6.j.
ATTACHMENTS: Resolution; Agreement APPROVED BY: LJM
RECOMMENDED ACTION: Motion to Adopt a Resolution Approving a Consulting
Contract for Engineering Services with WSB and Associates, Inc. for the Connemara Trail –
East Extension, City Project 2018-09.
BACKGROUND
Staff has been reviewing development in the area to the east of Akron Avenue and in the vicinity of the
future extension of Connemara Trail. As a result, the 2018-2027 Capital Improvement Plan included the
design of Connemara Trail east of Akron Avenue. The City Engineer requested a proposal from WSB, as
a member of the previously selected engineering pool, to perform the design work on this project. WSB is
very familiar with this area as that firm prepared a Feasibility Report detailing the estimated costs for
various road and utility extension throughout the Prestwick Place development.
WSB and Associates, Inc.’s proposal in the amount of $69,918 provides necessary work to complete
design and bidding of the Connemara Trail – East Extension. Funding for this work will come from the
Street CIP (203-49003-001-536.00) which has a current budget of $170,000. A follow up contract for
construction oversight would be required should the Council decide to construct this project. It should be
noted the funding for the construction is currently shown in the 2019 Capital Improvement Plan.
SUMMARY
Staff recommends Council approval of the attached resolution approving the award of a consulting
contract for engineering services to WSB and Associates for the Connemara Trail – East Extension.
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2018 –
A RESOLUTION APPROVING A CONSULTING CONTRACT
FOR ENGINEERING SERVICES FOR THE
CONNEMARA TRAIL – EAS T EXTENSION
CITY PROJECT 2018-09
WHEREAS, the City Council approved the 2018 – 2027 Capital Improvement Plan and the 2018
Budget Report which included the design of Connemara Trail – East Extension, and;
WHEREAS, the City Engineer requested a proposal to provide engineering services for this project
from WSB and Associates, Inc., and;
WHEREAS, the WSB and Associates, Inc. proposal in the amount of $69,918 that was provided is
within the existing budget for this project.
NOW THEREFORE BE IT RESOLVED, by the City Council of the City of Rosemount,
Minnesota, as follows:
1. The WSB and Associates, Inc. proposal for providing engineering services associated with
the Connemara Trail – East Extension, City Project 2018-09 in the amount of $69,918 is
accepted.
2. The City Administrator is hereby authorized and directed to enter into a contract with said
firm to provide engineering services associated with the Connemara Trail – East Extension.
ADOPTED this 5th day of February, 2018.
William H. Droste, Mayor
ATTEST:
Erin Fasbender, City Clerk
540 Gateway Boulevard | Suite 100 | Burnsville, MN 55337 | (952) 737-4660
Equal Opportunity Employer
wsbeng.com
G:\00-MUNICIPAL\Clients - Cities - Counties\Rosemount\Proposals\Connemara Trail Extension\20180111LTR Proposal - Rosemount Connemara Trail Extension.docx
January 12, 2018
Mr. Brian Erickson
Director of Public Works/City Engineer
City of Rosemount
2875 145th Street West
Rosemount, MN 55068
Re: Scope and Estimated Fee to Provide Professional Engineering Services for
Final Design of the Connemara Trail Extension Project
Dear Mr. Erickson:
We appreciate the opportunity to present this proposal for professional services related to the extension of
Connemara Trail, from its current terminus at the intersection with Akron Avenue (CSAH 73), to the easterly
limits of Outlot K within the Prestwick Place development. This letter proposal outlines the services required
to prepare all necessary documents to complete final design of the Connemara Trail Extension Project.
PROJECT UNDERSTANDING
The city desires to complete the extension of Connemara Trail, from its current terminus at the intersection
with Akron Avenue (CASH 73). The extension of Connemara Trail will traverse through Outlot K of the
Prestwick Place development, which is east of and adjacent to Akron Avenue. WSB & Associates, Inc.
(WSB) will work with City staff to design and construct Connemara Trail in accordance with the City’s
General Specifications and Standard Detail Plates for Street and Utility Construction . WSB understands
that development in the area will impact the final design schedule for the project, and that 100% plans will
be delivered to the City in 2018 or early 2019.
PROJECT APPROACH/SCOPE OF SERVICES
WSB’s project scope and proposed work plan are based on our understanding of the project as previously
described. To complete the project, we propose the following scope of services:
Task 1: Final Design
WSB will provide detailed design services for the extension of Connemara Trail. The plans and
specifications developed for the project will adhere to both the MnDOT 2018 Specifications for Construction
and the City of Rosemount General Specifications and Standard Detail Plates for Street and Utility
Construction.
Mr. Brian Erickson
January 12, 2018
Page 2
G:\00-MUNICIPAL\Clients - Cities - Counties\Rosemount\Proposals\Connemara Trail Extension\20180111LTR Proposal - Rosemount Connemara Trail Extension.docx
Subtask 1: Survey
WSB will provide survey work as needed for preparation of design documents. This work may include
elevations and locations (both public and private) and right-of-way location limits. Under this task, WSB
will also complete a Gopher State One Call request for private utility maps within the project area.
Cost: $5,552
Subtask 2: Drawings
WSB will complete all necessary plan sheets for the project, which will include:
• Title Sheet
• Standard Details
• SEQ
• Removals
• Street Plans (plan and profile, including storm sewer improvements)
• Utility Plans
• Erosion control
• SWPPP
• Deliverables:
o 90% Submittal: Draft plan set for review and comment
o 100% Submittal: Five (5) 11 X 17 final plan sets and five (5) specifications for your
files
Cost: $9,848
Subtask 3: Design
WSB will design and prepare plans consistent with City, ADA and local regulatory standards. WSB will
work with the City to finalize the alignment of the Connemara Trail extension in conjunction with the
development of Prestwick Place. At least one review and comment period is anticipated. With this
proposal, WSB assumes that Connemara Trail will be constructed using local funds, only, and that no
State Aid review will be required.
Cost: $23,092
Subtask 4: Specifications
WSB will Prepare the project specifications consistent with City, ADA, and local regulatory standards.
Cost: $7,320
Mr. Brian Erickson
January 12, 2018
Page 3
G:\00-MUNICIPAL\Clients - Cities - Counties\Rosemount\Proposals\Connemara Trail Extension\20180111LTR Proposal - Rosemount Connemara Trail Extension.docx
Subtask 5: Quantity Tabulations and Cost Estimate
WSB will prepare an Engineer’s Opinion of Probable Cost with the 90% and 100% submittals to the City.
Cost: $5,144
Subtask 6: Quality Assurance/Quality Control
WSB will perform quality control reviews regularly throughout the duration of the design to ensure all City
and other regulatory agency standards are being satisfied.
Cost: $3,122
Subtask 7: Meetings
WSB will attend two project meetings with City staff and design team (WSB staff) at times deemed most
effective by the City.
Cost: $2,438
Subtask 8: Utility Coordination
WSB will coordinate with all utilities in the area identified with the Gopher State One Call ticket for the
project. This will include conducting a utility coordination meeting. If crossing or encroachments
agreements are needed between the city and private utility companies, WSB will assist with in securing
these agreements. This proposal does not assume any gas pipeline relocation/lowering work will be
required to construct the project. WSB can provide the City with a separate proposal to facilitate relocation
work if it is determined necessary to construct the project.
Cost: $4,184
Subtask 8.1: Gas Pipeline Potholing
WSB is familiar with the project area, and is aware of gas pipeline utilities that exist beneath the
proposed Connemara Trail extension. As such, WSB is proposing to coordinate the collection of
potholed elevations for the existing pipeline to understand the elevation of the existing pipeline in
relation to the proposed roadway improvements.
Cost: $2,000
Mr. Brian Erickson
January 12, 2018
Page 4
G:\00-MUNICIPAL\Clients - Cities - Counties\Rosemount\Proposals\Connemara Trail Extension\20180111LTR Proposal - Rosemount Connemara Trail Extension.docx
Subtask 9: Permits
WSB will obtain the following permits in conjunction with the project:
• NPDES Permit for Construction Activities
• MDH permit for watermain extension
• MPCA permit for sanitary sewer extension and MCES approval for any MCES Interceptor
connections, if necessary
Cost: $2,400
Subtask 10: Bidding
The WSB project team will complete all necessary work to bid the project, including:
• The preparation of an advertisement for bids.
• Publishing the advertisement for bids in both the Rosemount Town Pages and Finance &
Commerce.
• Uploading the project plans and specifications for electronic purchase.
• Delivery of hard copy plans and specifications to the City for sale at City Offices .
• Responding to contractor bidding questions.
• Issuing addenda as needed.
• Attendance at the bid opening.
• Preparation of a bid tabulation and a bid summary.
• Preparation of a letter of recommendation regarding the bid award.
• Preparation of contract documents and the Notice of Award to the contractor once authorized by
the City Council.
Cost: $3,378
Subtask 11: City Coordination
Mitch Hatcher, PE will facilitate all necessary coordination between WSB and the City of Rosemount. Mitch
will be responsible for communicating all necessary project schedules and City and developer comments
to WSB during the final design of the project, as Mitch does for every developer -led public improvement
project.
Cost: $1,440
SCHEDULE
WSB will work with the City to develop a schedule for final design services that will support the timeline for
development within Prestwick Place. It is anticipated that final design work for the project will commence
in Spring/early Summer 2018, and may not be completed until early 2019.
Mr. Brian Erickson
January 12, 2018
Page 5
G:\00-MUNICIPAL\Clients - Cities - Counties\Rosemount\Proposals\Connemara Trail Extension\20180111LTR Proposal - Rosemount Connemara Trail Extension.docx
We propose to conduct the work listed above on an hourly basis for an estimated total fee of $69,918.
We will review our progress weekly and will not exceed this amount without your prior approval should the
scope of the project change.
This letter represents our entire understanding of the project scope. If you are in agreement, please sign
on the space provided and return one original signed copy to us for our records. We will start immediately
upon receipt of the signed agreement.
If you have any questions concerning the work plan or fee as discussed, please feel free to contact me at
(952) 737-4675. We look forward to working with you and greatly appreciate the opportunity to assist you
and your staff in the completion of this project.
Sincerely,
WSB & Associates, Inc.
Monica Heil, PE
Senior Project Manager
Enclosures
cc: Mitch Hatcher, PE, WSB & Associates, Inc.
Andy Brotzler, PE, WSB & Associates, Inc.
ACCEPTED BY: CITY OF ROSEMOUNT, MN
Signature:
Name/Title:
Date:
Task Description
1
1.1 Survey 8 24 32 $5,552.00
1.2 Drawings 12 16 8 40 76 $9,848.00
1.3 Design 28 36 60 60 184 $23,092.00
1.4 Specifications 8 16 24 8 4 60 $7,320.00
1.5 Quantity Tabulations and Cost Estimate 8 16 16 40 $5,144.00
1.6 QA / QC 2 8 8 8 26 $3,122.00
1.7 Meetings 2 4 4 4 4 18 $2,438.00
1.8 Utility Coordination 8 12 12 32 $4,184.00
1.8.1 Gas Pipeline Potholing $2,000.00
1.9 Permit Application 8 8 4 20 $2,400.00
1.10 Bidding Preperation 6 8 8 6 28 $3,378.00
1.11 City Coordination 24 24 $1,440.00
Task 1 Total Estimated Hours and Fee 4 70 112 148 24 84 48 18 24 8 540 $69,918.00
Average Hourly Billing Rate 173.00 163.00 128.00 112.00 60.00 120.00 139.00 80.00 185.00 104.00
Total Fee by Labor Classification $692.00 $11,410.00 $14,336.00 $16,576.00 $1,440.00 $10,080.00 $6,672.00 $1,440.00 $4,440.00 $832.00 $67,918.00
Total Fee for Gas Pipeline Potholing $2,000.00
TOTAL PROJECT COST $69,918.00
Andy Brotzler Monica Heil Mitch Hatcher Mitch Hatcher
Project Engineer
Adam Gadbois
Senior Project
Manager Project Engineer Project Engineer
(City Billing Rate)
Engineering
Technician AdminProject Engineer
Final Design
Principal
Estimate of Cost
City of Rosemount, Minnesota
Professional Engineering Services
Connemara Trail Improvement Project
Estimated Hours
Bruce Fournier
Two Person
Survey Crew
Construction
Specialist
Bill Alms Dan Bailey
CostTotal
Hours