HomeMy WebLinkAbout09.b. Request by Anderson Companies for rezoning to BP PUD and Site Plan Approval for Indoor Field House at Community of Hope Property EXECUTIVE SUMMARY City Council Regular Meeting: May 15, 2018 AGENDA ITEM: Case 18-19 PUD- Anderson Companies request for rezoning to BP PUD and site plan approval for indoor field house at Community of Hope property AGENDA SECTION: New Business PREPARED BY: Kim Lindquist, Community Development Director AGENDA NO.: 9.b. ATTACHMENTS: Ordinance, Resolution, PUD Agreement, Location Map, Site Plan, Project Narrative, Planning Commission Minutes Excerpt from 4/24/2018, Existing Conditions Plan, Grading & Erosion Control Plan, Utility Plan, Civil Details Sheet, Landscape Plan, 2004 Approved Landscape Plan, Tree Inventory Plan, Proposed Drainage Plan, Colored Building Elevation, Interior Floor Plan, Building Elevations, Engineers Memo 4/17/2018, Council Resolution of Approval 2004, Planning Commission Minutes and Packet March 23, 2004 APPROVED BY: LJM RECOMMENDED ACTION: 1. Motion to adopt an Ordinance amending Ordinance B City of Rosemount Zoning Ordinance for 14401 Biscayne Avenue from BP Business Park to BP PUD Business Park PUD. 2. Motion to Adopt Resolution Approving the Planning Unit Development (PUD) Master Development Plan and Site Plan with Rezoning for an Indoor Recreation Facility at 14401 Biscayne Avenue, Community of Hope. 3. Motion to approve the Planned Unit Development Master Development Plan Agreement for 14401 Biscayne Avenue and Authorize the Mayor and City Clerk to enter into the Agreement. 2 SUMMARY The applicant Anderson Companies is asking for approval of a PUD and site plan review for approval of a 46,734 square foot indoor recreation building. The building will be located on the same property as the current Community of Hope church. The current ordinance does not permit two principal structures on one parcel, and therefore, staff is suggesting use of a PUD to permit the two independent buildings on one site. The general location of the building was foreseen in the 2004 approval and would be considered another phase of the church complex. A third phase could be constructed between the two, connecting the each building into one larger structure. Any future sale of either of the buildings to a different owner would require subdivision of the properties. The proposed structure is an indoor recreational use, or field house. The building footprint is 36,080 square feet with another 10,654 sq. ft. on the second floor. The first floor contains the 30,000 sq. ft. gymnasium with two additional tenant spaces. Also included are an office, concession stand, and two locker rooms. The upper level contains a viewing area, restrooms and a 1,453 sq. ft. fitness center. Similar to the church structure, the building is constructed so that retrofitting to a business park use could occur. The structure is 35’ in height and is comprised primarily of rib precast concrete panels with exposed aggregate that would match the existing building. The south elevation, the front of the building has enhancements to the entrance although other elevations are relatively unadorned. The site plan depicts additional parking added for the new use. Presently there are 205 stalls and another 185 will be added with the project. The landscaping and site work are consistent with the previous approval for the church from 2004. Applicant & Property Owner(s): Anderson Companies, Applicant Community of Hope Church, Owner Location: 14401 Biscayne Avenue Area in Acres: 8.08 Acres Comp. Guide Plan Design: BP-Business Park Current Zoning: BP-Business Park PLANNING COMMISSION The Planning Commission discussed this item at their April meeting. There were three neighbors who spoke during the public hearing. Their concerns dealt with issues associated with additional activity at the site, and that the activity would be later in the night. They were concerned about traffic, noise and lighting and also upset that the church had not reached out to the neighborhood regarding the proposal. The applicant and staff indicated that there are regulations relating to lighting and sound and the expectation is that any activity on the site will need to comply with current standards. The parking is a larger issue as the site plan indicates that parking required for the two uses occurring simultaneously does not exist on-site. For the most part, it is anticipated that parking demands for the Field House will be at differing times than the busy church times, although that might not always be the case. The applicant indicated they have a parking arrangement with School District 917 that allows them to use 3 the school lot during the weekend. They also indicated they are talking to MERC about a shared parking arrangement. Condition 5 of the recommended approval requires that an operational plan be put in place should parking become a problem at the site. This could include not allowing the third phase of the building project is parking demand is not met at the site. To be clear there is no expectation that any parking should occur in the surrounding residential neighborhoods. All parking should be accommodated on site, or the solution should be additional parking opportunities through a formal shared parking agreement. As part of the parking discussion, there was discussion about the entrance to the facility, from the south, and its inconvenient location from the greater parking field. The Planning Commission approved a condition requesting the applicant consider shifting the main entrance to the north to be more attractive for future users and direct them to the further away parking. Typically, staff does not require modifications to internal operations but at a minimum, the applicant should provide pedestrian access from the NW parking to the south entrance and should relook at the building entrances. However, staff is aware that the applicant will be requesting financial assistance from the City for construction of the project. Should the Council choose to provide some financial assistance, staff would strongly recommend that payment be predicated on modifications to the building entrance so that the field of parking is well served by the building entrance. Additional conditions of approval require more landscaping in the north and west, generally consistent with the 2004 approval and the applicant should modify the stormwater system which anticipated ponding within the parking lot. There has been recent discussion with the engineering department to remedy this situation and there are alternatives for stormwater rate control that will not adversely impact the current site plan. After discussions about parking, lighting, and sound, the Planning Commission unanimously approved the PUD rezoning and site plan approval. BACKGROUND In 2004, the City approved an administrative plat and conditional use permit to allow the combination of three lots into one property and construction of a church facility at the current site. The staff report indicates that the square footage would be 45,187 although that size is not what was ultimately constructed. The approved first phase was the interior diagonal section of the building which would combine the constructed church with the current proposal. After approval, the applicant chose to build the more northern section of the approved building. The conditions remained the same as the 2004 approval. More recently, a group has been working to construct an indoor recreation facility that includes gymnasium space. The first location was north of County Road 42, east of Akron Avenue. The present proposal is a striped down version of the larger facility and only includes court space. The facility will be a private facility although there may be a request for some public funding. That is not part of the discussion tonight and is the purview of the City Council. 4 SITE PLAN Zoning The zoning ordinance permits commercial indoor recreational uses in the Business Park district, which allows the field house use. It is staff’s opinion that the anticipated commercial tenants are consistent with the indoor recreation use so long as they are ancillary to the principal recreational use. The 2004 approval anticipated additional phases to the initial building and the current building footprint is consistent with that anticipated in the initial plans. The phasing is staged differently and the sizes of the phases altered slightly. However, it appears, with the possible exception of about 2,000 sq. ft. that the building footprint is the same size as that initially anticipated. However, the addition of the 2nd floor mezzanine area increases the square footage on the site by 10,654 sq. ft. Most of that space is assembly space and should not significantly alter the development standards for the site. However, should parking become an issue on the site, the 3rd phase may need to be reduced to reduce on-site demands. The main reason for use of a PUD is to permit two principal structures on the site. The field house introduces another principal use to the site, which is not dependent upon the church use at the facility. However, the two buildings represent two phases of an approved site plan. Staff believes the two uses can co-exist on the site and therefore can support the two uses on the site. Initially staff had recommended splitting the site, which negatively affects the long term development plan for the property. However, should the owner want to sell one of the buildings, the property would need to be split. The proposed structure meets all the setbacks required by the zoning ordinance, and no deviations from the setback standards are being requested by the applicant for this planned unit development. Setback Standard Increased Setback Total Setback Required Proposed Front (south) 30 feet 10 feet 40 feet 113.68 feet Side, west 10 feet n/a 10 feet 77.09 feet Side, east 30 feet 10 feet 40 feet 265.91 feet Rear 10 feet n/a 40 feet 342.42 feet Exterior Materials The building design and materials are consistent with the existing structure. The entrance to the facility will be located on the south which contains an entrance feature appearing very similar to the church entrance facing Biscayne Avenue. The doorway will have a glass curtain over the door frames, all delineated by rockface block columns and metal canopy. Windows at the second story are located on the south elevation along with a colored stripe to break up the long façade. However, the other three elevations do not have any articulation or modification in materials to break up the exterior walls. There is the stripping but additional articulation should be added. The existing building was constructed prior to the existing ordinance design standards. While the proposed building can complement the existing structure, it should be more consistent with the current ordinance design standards. The ordinance criteria are as follows: 5 Building Massing: Facades shall be articulated to reduce their mass and scale and provide visual interest consistent with Rosemount's identity, character, and scale. Large uninterrupted building walls or elevations are prohibited. Any wall more than one hundred feet (100') in length shall be divided into increments of no more than thirty five feet (35') through the articulation of the facade. This shall be achieved through combinations of the following techniques: Division or breaks in the materials. Arcades, entry features, window bays, or the like Variations in rooflines or slope plan Variation in building plan or setback Equivalent techniques approved by the city Access and Parking Site access will remain in the current locations; one from Biscayne Avenue and one from 145th Street. There are no changes proposed. The site currently has 205 parking stalls and the plan adds an additional 181 stalls for a total of 386. The 2004 plan depicted expansion of the parking are in the north similar to what is proposed, however, did not include the most western single parking row. The drawing indicated a landscaped parking island. Typically, staff is leery about stalls directly access a fairly busy drive aisle as indicated on the plan. Because the western row is only one stall, vehicles can head into the stalls and drive out without backing into the main circulation drive aisle. The ordinance requires 1 space for every 3 seats in the assembly space. Based upon the application information, the seating is 700 and the parking required for the existing structure would be 233. The new building is recreational which requires 1 parking stall for every 200 sq. ft. That calculation results in 234 spaces for a total parking requirement of 467 stalls. The site currently provides 386 stalls, a significant deficit. It is recognized that the two uses should have varying peak hours, although there are definitely tournaments anticipated one the weekends, including Sunday morning with would conflict with church hours. It does not appear that there is much programming on Saturday at the church and many of the other events are during weekday hours, such as the preschool. Staff believes that the offset programming will reduce the need for parking at the site by both uses simultaneously. This is always a concern since on street parking is not permitted on either Biscayne or 145th Street and the City does not encourage parking on other residential streets or adjoining private commercial properties. If the site experiences a parking problem, staff would work with the operator to modify the programming schedule to provide relief. Staff would also recommend that the third phase of the building be delayed indefinitely if parking demands persist. To address the potential for parking issues, staff is also recommending that the mezzanine area be used for assembly space only, as noted in the site plan application. A final issue of note is that the only entrance to the building is located on the south side of the building; however, the majority of the parking is located in the north. Due to the interior configuration, no space is available for entering at either side. This means most patrons will need to walk around the entire building to access the building entrance. A condition of approval requires installation of a sidewalk around the building to direct customers from the parking lot to the entrance. Staff strongly suggests either flipping the interior space, or modifying the north portion of the building to include a small entrance, for the convenience of future users. 6 Landscaping and Berming As depicted in the approved 2004 plans, there are berms along the two rights-of-ways and at the corner of 145th Street and Biscayne Avenue. There is a lot of landscaping located along the bermed areas and it is questionable if additional should be added. Construction of the addition prompts perimeter plantings and also plantings within parking lots islands. The 2004 plan depicts plantings along with trees to be planted along the west property line and in the north in the parking lot islands and adjacent to the building. Those have not been installed and are not proposed in the current plan submittal. Staff is recommending that the previously approved landscape plan be fulfilled and the tress installed along the western boundary adjacent to the drive aisle. Additionally, planting should be installed along the north property line. The previous plan also included trees along the west side of the building and a few should be added. For the most part, the landscaping proposed around the building are 29 spireas and 22 dogwoods. The ordinance requires one foundation planting for every 10 feet of the building façade. Additional plantings on the east and west are required to meet the ordinance criteria. Engineering The Engineering department has reviewed the plans and has minimal comments about the project. The one issue is that as currently proposed, the developer is ponding in the parking lots rather than ponding within a ponding area or sending drainage downstream. The City’s policies do not allow ponding standards to be met through parking lot ponding. This is not desirable as it creates safety hazards and negatively affects the pavement and storm sewer structures. The applicant should revise the storm water plan prior to final review by the City Council. Lighting All lighting must comply with ordinance standards for glare and fixtures. New lighting would be consistent with the existing lighting on site. Signage Similarly, an additional signage for the site and the recreational facility will require separate sign review and approval. CONCLUSION & RECOMMENDATION Staff is recommending approval of a PUD with conditions to permit an indoor recreational facility at the site. The site plan was initially approved in 2004, although the construction phasing prompts the need for a PUD due to two principal structures on one site. The primary concern regarding the site plan is the potential parking demand on the site. The applicant is aware of the concerns and if experienced, will have to find mitigative measures to satisfactorily address the issue so as to not adversely impact surrounding residential neighborhoods. Staff and the Planning Commission are recommending approval of the application with conditions. City of Rosemount Ordinance No. B-268 AN ORDINANCE AMENDING ORDINANCE B CITY OF ROSEMOUNT ZONING ORDINANCE Hope Field House at Community of Hope Property THE CITY COUNCIL OF THE CITY OF ROSEMOUNT, MINNESOTA, ORDAINS AS FOLLOWS: Section 1. Ordinance B, adopted September 19, 1989, entitled “City of Rosemount Zoning Ordinance,” is hereby amended to rezone property BP – Business Park to BP PUD – Business Park Planned Unit Development that is located at 14401 Biscayne Avenue within the City of Rosemount legally described as follows: Lot 1 Block 1 Hope Acres Plat Section 2. The Zoning Map of the City of Rosemount, referred to and described in said Ordinance No. B as that certain map entitled “Zoning Map of the City of Rosemount,” shall not be republished to show the aforesaid rezoning, but the Clerk shall appropriately mark the said zoning map on file in the Clerk’s office for the purpose of indicating the rezoning hereinabove provided for in this Ordinance and all of the notation references and other information shown thereon are hereby incorporated by reference and made part of this Ordinance. Section 3. This ordinance shall be effective immediately upon its passage and publication according to law. ENACTED AND ORDAINED into an Ordinance this 15th day of May, 2018. CITY OF ROSEMOUNT William H. Droste, Mayor ATTEST: Jeff May, Deputy City Clerk CITY OF ROSEMOUNT DAKOTA COUNTY, MINNESOTA RESOLUTION 2018-46 A RESOLUTION APPROVING THE PLANNED UNIT DEVELOPMENT (PUD) MASTER DEVELOPMENT PLAN AND SITE PLAN WITH REZONING FOR INDOOR RECREATION FACILITY AT 14401 BISCAYNE AVENUE, COMMUNITY OF HOPE WHEREAS, the Community Development Department of the City of Rosemount received a request for a Planned Unit Development Master Development Plan with Rezoning from Anderson Companies concerning property legally described as: Lot 1 Block 1 Hope Acres Plat WHEREAS, on April 24, 2018, the Planning Commission of the City of Rosemount held a public hearing and reviewed the PUD Master Development Plan with Rezoning to construct the Hope Fieldhouse, an athletic facility; and WHEREAS, on April 24, 2018, the Planning Commission recommended approval of the PUD Master Development Plan with Rezoning to construct the Hope Fieldhouse, an athletic facility, subject to conditions; and WHEREAS, on May 15, 2018, the City Council of the City of Rosemount reviewed the application and agreed with the Staff recommendation; NOW, THEREFORE, BE IT RESOLVED, the Council of the City of Rosemount hereby approves the Planned Unit Development (PUD) Master Development Plan and the Rezoning to BP PUD, subject to: 1. The applicant modify the landscape plan to include plantings approved in the 2004 plan including deciduous trees along the north and west side of the property and bring the site into compliance with required foundation plantings prior to issuance of a building permit. 2. The applicant submit final grading and drainage plan for staff review and approval prior to issuance of a building permit. 3. The applicant consider providing a public entrance on the north side of the building to allow customer parking in the NW to access the building more conveniently. 4. Include pedestrian access from the NW parking lot to the building and around the entire building. 5. If the site experiences a parking shortage, the owners of the recreational facility will work with staff to modify the event schedule to reduce parking demand on site. If a parking shortage continues to be experienced, the recreation facility owner will work to address the shortage. Construction of the third approved building phase will not be permitted if a parking shortage is regularly experienced on the site. Examples of a site parking shortage could be on-street parking occurring in adjoining residential neighborhoods, unauthorized parking in adjoining commercial parking lots, or parking on site in non- designated locations 6. The applicant modify the exterior materials of the building to bring the elevations into compliance with the business park ordinance standards. RESOLUTION 2018-46 2 7.Conformance with all requirements of the City Engineer as detailed in the attached memorandum dated April 17, 2018. ADOPTED this 15th day of May, 2018, by the City Council of the City of Rosemount. __________________________________________ William H. Droste, Mayor ATTEST: ___________________________________ Jeff May, Deputy City Clerk 1 DECLARATION OF COVENANTS AND RESTRICTIONS COMMUNITY OF HOPE MASTER DEVELOPMENT PLAN PLANNED UNIT DEVELOPMENT AGREEMENT THIS DECLARATION made this ______ day of _________________, 2018, by Community of Hope Lutheran Church (hereinafter referred to as the “Declarant”); WHEREAS, Declarant is the owner of the real property as described on Attachment One, attached hereto and hereby made a part hereof (hereinafter collectively referred to as the “Subject Property”); and WHEREAS, the Subject Property is subject to certain zoning and land use restrictions imposed by the City of Rosemount (hereinafter referred to as the “City”) in connection with the approval of an application for a master development plan planned unit development for a residential development on the Subject Property; and WHEREAS, the City has approved such development on the basis of the determination by the City Council of the City that such development is acceptable only by reason of the details of the development proposed and the unique land use characteristics of the proposed use of the Subject Property; and that but for the details of the development proposed and the unique land use characteristics of such proposed use, the master development plan planned unit development would not have been approved; and 2 WHEREAS, as a condition of approval of the master development plan planned unit development, the City has required the execution and filing of this Declaration of Covenants, Conditions and Restrictions (hereinafter the “Declaration”); and WHEREAS, to secure the benefits and advantages of approval of such planned unit development, Declarant desires to subject the Subject Property to the terms hereof. NOW, THEREFORE, the Declarant declares that the Subject Property is, and shall be, held, transferred, sold, conveyed and occupied subject to the covenants, conditions, and restrictions, hereinafter set forth. 1.The use and development of the Subject Property shall conform to the following documents, plans and drawings: a.City Resolutions No. 2018-46 and 2004-57, Attachments Two and Three b.Site Development Plan, Attachment Four d.Landscape Plan (Revised 02-17-2004), Attachment Five e.Preliminary Grading Plan, Attachment Six f.Utility Plan, Attachments Seven and Eight g.Exterior Elevations, Attachment Nine All of which attachments are copies of original documents on file with the City and are made a part hereof. 2.Development and maintenance of structures and uses on the Subject Property shall conform to the following standards and requirements: a.The applicant modify the landscape plan to include plantings approved in the 2004 plan including deciduous trees along the north and west 3 side of the property and bring the site into compliance with the required foundation plantings prior to issuance of a building permit. b. The applicant submit final grading and drainage plan for staff review and approval prior to issuance of a building permit. c.The applicant consider providing a public entrance on the north side of the building to allow customer parking in the NW to access the building more conveniently. d. Include pedestrian access from the NW parking lot to the building and around the entire building. e. If the site experiences a parking shortage, the owners of the recreational facility will work with staff to modify the event schedule to reduce parking demand on site. If a parking shortage continues to be experienced, the recreation facility owner will work to address the shortage. Construction of the third approved building phase will not be permitted if a parking shortage is regularly experienced on the site. Examples of a site parking shortage could be on-street parking occurring in adjoining residential neighborhoods, unauthorized parking in adjoining commercial parking lots, or parking on site in non- designated locations. f.The applicant modifies the exterior materials of the building to bring the elevations into compliance with the business park ordinance standards. 4 g.Conformance with all requirements of the City Engineer as detailed in the attached memorandum dated April 17, 2018. 3.The Subject Property may only be developed and used in accordance with Paragraphs 1 and 2 of this Declaration unless the owner first secures approval by the City Council of an amendment to the planned unit development plan or a rezoning to a zoning classification that permits such other development and use. 4.In connection with the approval of development of the Subject Property, the following deviations from City Zoning or Subdivision Code provisions were approved: a.Section 11-2-2.B. Lot Provisions: More than one principle structure may be located on the site. b.Section 11-6-1.H.Off Street Parking Required: Fewer parking stalls than required by the city code may be provided so long as a parking shortage does not occur. In the case of a parking shortage, the owners of the recreational facility will work with staff to modify the event schedule to reduce parking demand on site. In all other respects the use and development of the Subject Property shall conform to the requirements of the Paragraphs 1 and 2 of this Declaration and the City Code of Ordinances. 5.This Declaration of Covenants and Restrictions provides only the Subject Property only master development plan planned unit development approval. Prior to the improvement or development of the Subject Property, beyond the rough grading, a final development plan planned unit development approval pursuant to Zoning Code Section 11-10-6 C. 5. of the Subject Property is required and an addendum filed with County Recorder to this Declaration of Covenants and Restrictions. 5 6.The obligations and restrictions of this Declaration run with the land of the Subject Property and shall be enforceable against the Declarant, its successors and assigns, by the City of Rosemount acting through its City Council. This Declaration may be amended from time to time by a written amendment executed by the City and the owner or owners of the lot or lots to be affected by said amendment. IN WITNESS WHEREOF, the undersigned as duly authorized agents, officers or representatives of Declarant have hereunto set their hands and seals as of the day and year first above written. DECLARANT Community of Hope Church By Its STATE OF MINNESOTA ) ) ss. COUNTY OF __________ ) The foregoing instrument was acknowledged before me this ___ day of _________, 2018, by _____________________, the _________________, for and on behalf of _________________________, a ____________________, by and on behalf of said _______________________. _______________________________ Notary Public 6 This Planned Unit Development Agreement is approved and consented to by the City Council of the City of Rosemount. CITY OF ROSEMOUNT By: William H. Droste, Mayor And by: J eff May, Deputy City Clerk STATE OF MINNESOTA ) ) ss. COUNTY OF DAKOTA ) The foregoing instrument was acknowledged before me this ___ day of ___________, 2018, by William H. Droste and Jeff May, the Mayor and Deputy City Clerk, respectively, for and on behalf of the City of Rosemount, a Minnesota corporation, by and on behalf of said corporation. Notary Public THIS INSTRUMENT WAS DRAFTED BY: City of Rosemount 2875 145th Street West Rosemount, MN 55068 651-423-4411 Kim, I will break the narrative up by your two points listed in your email. 1.Breakdown about the type of recreational uses, the timing of the activities and the estimated amount of people. Recreational activities within the Hope Fieldhouse will consist of Youth/Adaptive activities such as Basketball, Volleyball, Futsal and Floor Hockey. Recreational activities will include Pickleball, Basketball, co-ed volleyball and personal training. Activity list will expand based on demand by the users, but all activities will be recreational in nature. As an example, we may find there is a need for indoor lacrosse practices, and if we have the space available we would rent out to a group like that. HF will also have space dedicated to CrossFit and a fitness center. These users will be consistent throughout the year, with a spike in the winter months. I am including a matrix that lists out what we believe is a schedule for Hope Fieldhouse. With this type of facility, we felt it was important to layout 4 different schedules. Peak/off-peak and then Weekend/Weekday. We are considering Peak to be October through March. I have included by hour the schedule and number of potential users. Peak/Weekday We would estimate no more than 140 people within the facility at one time. Gym time will not be rented to capacity on Wednesday nights as not to conflict with Community of Hope Church Services. Peak/Weekend We would estimate no more than 500 people within the facility at one time. Tournaments/Events will not be held on Sunday morning so not to conflict with Community of Hope Church Services. If no tournament or event is taking place within the facility most of traffic would be from open gym users, Fitness Center and CrossFit classes. Off-Peak/Weekday We would estimate no more than 110 people in the facility at one time. Gym time will not be rented to capacity on Wednesday nights as not to conflict with Community of Hope Church Services. Off-Peak/Weekend We would estimate no more than 500 people within the facility at one time. Tournaments/Events will not be held on Sunday morning so not to conflict with Community of Hope Church Services. If no tournament or event is taking place within the facility most of traffic would be from open gym users, Fitness Center and CrossFit classes. 2.I am also interested in a breakdown on the square footage associated with the various uses The breakdown in spaces is as follows: Recreation activities listed in #1 will be held in the gymnasium. The gymnasium is 30,000 sf. CrossFit tenant space will 2,673 sf Fitness Center space will be 1,435 There are areas for social spaces and bleachers for watching games etc. 6.b. Request by Anderson Companies for Rezoning to BP PUD and Site Plan approval for Indoor Field House at Community of Hope Property. (18-19-PUD) Community Development Director Lindquist gave a brief summary of the staff report for the Planning Commission. Commissioner VanderWiel inquired if the third phase building would require additional parking. Lindquist confirmed that it would. VanderWiel questioned how additional parking could be accommodated since the site is already short on parking. Lindquist stated that staff will review onsite parking when or if that third phase gets brought to staff. Commissioner Reed inquired if a contingency plan has been put into place for the future parking needs. Lindquist stated that the applicant would better be able to answer that question. Reed inquired if there are any changes proposed to the exterior. Lindquist stated that is condition number six. Commissioner Clements inquired if the South and East parking lot would be constructed now or at a later time. Lindquist stated that everything would be constructed at this time. Commissioner Kenninger inquired if the principal owner would sell the church and the lot would then have two principal structures. Lindquist confirmed that correct. Commissioner VanderWiel inquired if this building could potentially harm the future use for the site. Lindquist stated that the City would not approve a lot split if that would negatively affect either one of the lots. Commissioner Clements stated that when the third phase was complete it would attach the other two buildings. A lot split would not be possible. Chair Kenninger inquired what the traffic would look like and have conversations been had about the potentially increased traffic. City Engineer Hatcher confirmed that the adjacent roads, Biscayne and 145th Street, have been designed to handle the increase in traffic. The public hearing opened at 7:19 pm. Public Comments: Wayne Newbaur, SEH, Inc., 717 3rd Avenue South East, Rochester, MN, representing both the developer and the owners. Representatives are in attendance from both. Mr. Newbauer stated that they agree to all seven conditions. Per Nilsen, Lead Pastor at Community of Hope Church, 1185 Ivy Hill Drive, Mendota Heights, stated that the Church is in full support of the project. Regarding the parking, it would possibly be an issue on Sunday mornings and holiday’s. Community of Hope Church currently has a contract with ISD 917 that is located right across the street and they are currently in talks with MERC that is also located next door for additional parking spaces. Commissioner Mele questioned if the church runs out of parking during church services. Mr. Nilsen stated that they do not currently. Volunteers are asked to park across the street in the ISD 917 parking lot. Chair Kenninger inquired if a lot split has been discussed. Mr. Newbauer stated that after discussing with City staff the right approach to gain approval of the building, it was decided that a PUD was the better choice. Chair Kenninger inquired if they were in favor of adding an exterior door on the north side of the building and changing the exterior. Mr. Newbauer confirmed that they are in agreement to condition six. Mark Johnson, 14528 Blackberry Way, stated that Hope Field House is well established with Facebook, Twitter, and additional websites. Mr. Johnson suggested that any commercial vehicles leave the property onto Biscayne Ave. Mr. Johnson continued that the Commission should tread slowly because the new building will have a negative financial impact on his property. Jill Tutewohl, 2493 145th Street West, just moved into home 2 years ago and didn’t know anything about the planned project. Ms. Tutewohl inquired on where to get more information on the project. Ms. Tutewohl questioned if there are plans in the future for stoplights at the busy intersection of 145th Street West and Biscayne Ave. Kaye Richardson, 2454 Beech Street West, stated that she is concerned about the possible noise that this additional building will bring to the neighborhood. Ms. Richardson inquired what the facility hours are going to be. Mark Johnson, 14528 Blackberry Way, stated that adding additional traffic to this intersection may slow down emergency vehicles. Commissioner Mele questioned if the main tournament season for volleyball and basketball was during the warm spring and summer months. Scott Schoaf, 15124 Cimarron Way, stated that the tournament season for volleyball and basketball will run November through April. Tournaments will finish up around 9pm. Hours of operation for the facility will be about 8 am - 9 pm, 7 days a week. The facility will have 4 courts, a fitness center, and possibly a chiropractor or similar tenant. More information can be found at www.hopefieldhouse.org. Mr. Schoaf stated that site deliveries would be for concession stand items and vehicles will be at a smaller size; commercial vehicle deliveries shouldn’t be necessary. Mr. Schoaf stated that the traffic will look like a constant flow of people coming and going. He does not anticipate much hanging out in the parking lot, especially during the winter months. Commissioner Clements questioned why the direct neighbors were not contacted about the construction of the facility. Mr. Schoaf stated that is a valid point and he takes full responsibility for not communicating the plans to the surrounding neighbors. Kaye Richardson, 2454 Beech Street West, questioned what kind of lighting will the parking lots have and what use will the facility have during the summer months. Per Nilson, 1185 Ivy Hill Drive, Mendota Heights, stated that the lighting structures will be similar to the lighting currently in the church parking lot. Mr. Nilson stated that during the summer months the empty grass lot is currently used for youth soccer facilities. The summer will actually be quieter after construction because the sports will be moved inside. MOTION by Freeman to close the public hearing. Second by Mele. Ayes: 6. Nays: 0. Motion Passes. The public hearing was closed at 7:54 pm. Additional Comments: Chair Kenninger inquired what the lighting ordinance is for commercial buildings. Lindquist stated that the lights will be facing down and shielded so that the lights are not shining into the houses. Kenninger clarified that the zoning allows the proposed use. But the rezoning is needed because there will be two principal uses on the lot. Lindquist confirmed that is correct. She noted in 2004 the buildings were approved and because of how the phasing is being completed, the site plan approval is tricky. Kenninger stated that the neighborhood has concerns about parking on the street. Lindquist stated that it may be an enforcement issue but as long as there is enough parking in the lot they shouldn’t experience on street parking. On street parking is not allowed on Biscayne or 145th. Kenninger questioned if staff see’s the increase in traffic on 145th Street West and Biscayne Ave to be an issue for emergency vehicles. Asst. City Engineer Hatcher stated that he does not. Hatcher stated that 145th Street West and Biscayne Ave are already larger collector streets. These streets were designed to carry large amounts of traffic. Kenninger questioned if this item will be coming back to the commission. Lindquist stated that it will not. Commissioner Clements inquired as to how the use of the soccer fields will compare to the new building’s use. Mr. Nilsen stated that RAAA purchased a block of time for the fields. The total volume is unknown for Hope Field House at this time. Commissioner Clements stated that the applicants end game would be to have their third phase completed and that would be a new sanctuary hall. If the parking is an issue and they are receiving complaints, then they would potentially not get their third phase. MOTION by Clements to recommend the City Council rezone the property at 14401 Biscayne Avenue to BP PUD and approve the Master Development Plan and Site Plan for an indoor recreation facility subject to the following conditions: 1.The applicant modifies the landscape plan to include plantings approved 2004 plan including deciduous trees along the north and west side of the property and bring the site into compliance with required foundation plantings. 2.The applicant modifies the storm water plan to remove required ponding from the parking lots prior to City Council review. 3.The applicant considers providing a public entrance on the north side of the building to allow customers parking in the NW to access the building more conveniently. 4.Include pedestrian access from the NW parking lot to the building and around the entire building. 5.If the site experiences a parking shortage, the owners of the recreational facility will work with staff to modify the event schedule to reduce parking demand on site. If a parking shortage continues to be experienced, the recreation facility owner will work to address the shortage. Construction of the third approved building phase will not be permitted if a parking shortage is regularly experienced on the site. 6.The applicant modifies the exterior materials of the building to bring the elevations into compliance with the business park ordinance standards. 7.Conformance with all requirements of the City Engineer as detailed in the attached memorandum dated April 17, 2018. Second by Mele. Ayes: 6. Nays: 0. Motion Passes. PROPOSED DECIDUOUS SHRUBMULCH (SEE NOTE 4)SOD (SEE NOTE 7)PROPOSED EVERGREEN SHRUB PROPOSED DECIDUOUS TREESHEET NUMBEROFSHEETSPROJECTNUMBERCOMPUTERFILEDATEDRAWN BYCHECKED BYREVISIONSC4 LANDSCAPE PLANROSEMOUNT, MINNESOTANUMBERTHE STATE OF MINNESOTA.DATECOMMUNITY OF HOPE LUTHERAN CHURCH PLANT LEGENDCONSTRUCTION NOTESSEED (SEE NOTE 7)TREE PLANTING DETAILSHRUB PLANTING DETAILPROPOSED CONIFERUOUS TREE MEMORANDUM DATE: April 17, 2018 TO: Kim Lindquist, Community Development Director CC: Kyle Klatt, Planner Stacy Bodsberg, Planning & Personnel Secretary Brian Erickson, Director of Public Works/City Engineer FROM: Mitch Hatcher, Project Engineer RE: Hope Fieldhouse Engineering Review SUBMITTAL: The plans for Hope Fieldhouse have been prepared by SEH dated March 27, 2018. Engineering review comments were generated from the following documents included in the submittal:  Civil Plan Set  Drainage Analysis  Project Narrative GENERAL COMMENTS: 1. Street and utility construction shall be installed in accordance with the 2015 City of Rosemount General Specifications and Standard Detail Plates and the Engineering Guidelines. 2. City inspection of public street and utility connection is required during construction. 3. Maximum allowable slope is 4:1 and minimum slopes of 2% are allowed. Maximum slopes of 3:1 are only allowed below the 10:1 maintenance bench for NURP basins. 4. The developer is required to obtain a NPDES Construction Stormwater Permit and provide a copy of the approved SWPPP to the City prior to the issuance of a grading permit and start of any construction activity. 5. Upon completion of the street, sanitary sewer, watermain, and storm sewer construction, the City requires record drawings. See Engineering Guidelines for submittal and formatting requirements. STORMWATER COMMENTS: 6. The City will not allow stormwater ponding of water to be done on parking lots or other paved areas. The number of inlets and/or size of inlets should be designed to eliminate ponding on paved areas. Ponding in a parking lots creates safety concerns with falling, hydroplaning, and ice buildup. The applicant will need to find another way to manage discharge rates to the existing storm sewer system. 7. Regional basin EP-2030 has been designed for the water quality and quantity requirements. In 2004, offsite ponding fees were paid for the site and additional offsite ponding fees with not be required. 8. The City’s standards require storm sewer to be RCP and a minimum of 15” diameter. 9. All local low points (both paved and unpaved) need to have EOFs called out with flow arrows on the grading plan. At least one foot of freeboard must be maintained from the EOF to all adjacent building low openings. 10. Use Table 8.8 Minimum Grades in the MnDOT drainage manual to determine the minimum allowable pipe slope. Increase the slope of the pipe between CB11 and CB9. Should you have any questions or comments regarding the items listed above, please contact me at 651-322-2015. CITY OF ROSEMOUNT DAKOTA COUNTY, MINNESOTA RESOLUTION 2004-57 A RESOLUTION APPROVING AN ADMINISTRATIVE PLAT AND CONDITIONAL USE PERMIT FOR COMMUNITY OF HOPE LUTHERAN CHURCH WHEREAS, the Planning Department received an application for approval of an Administrative Plat and a Conditional Use Permit for Community of Hope Lutheran Church to combine three lots into one and construct a 45,187 square foot church building, located on the three parcels legally described as follows: Parcel A. The East 633.00 feet of Lot 2, Auditor’s Subdivision No. 1 Rosemount, except that part lying north of the following described line: Commencing at the intersection of the southerly right of way line of a Railroad and the east line of said Lot 2, thence south along the east line of said Lot 2 a distance of 625.3 feet to the point of beginning of the line to be described; thence deflect 90 degrees right a distance of 633 feet and there terminating. Also except that described as beginning at a point 2596.5 feet south and 33 feet west of the northeast corner of Section 29, Township 115, Range 19; thence North 125 feet; thence West 50 feet; thence South 125 feet; thence East 50 feet to the place of beginning. Parcel B. That part of Lot 2, Auditor’s Subdivision No. 1, Rosemount, being described as follows: Commencing at the intersection of the southerly right of way of a Railroad and the easterly line of said Lot 2; thence southerly along said east line a distance of 275.30 feet to the point of beginning of the property to be described; thence deflecting 90 degrees right a distance of 633 feet more or less to its intersection with the southerly line of said Railroad; thence deflecting 90 degrees left a distance of 350 feet; thence deflecting 90 degrees left a distance of 633 feet more or less to its intersection with east line of said Lot 2; thence defecting 90 degrees left along said east line a distance of 350.00 feet to the point of beginning. Parcel C. All that part of Lot 2 of Auditor’s Subdivision No. 1, Rosemount, according to the plat thereof now on file and record in the office of the Register of Deeds within and for Dakota County, State of Minnesota, described as follows: Commencing at a point of beginning which said point is 2471.5 feet south and 33 feet west of the Northeast corner of Section 29, Township 115 North, Range 19 West, thence South 75 feet, thence West 50 feet, thence North 75 feet, thence East 50 feet to the point of beginning, Dakota County, Minnesota. WHEREAS, the Planning Commission of the City of Rosemount conducted a public hearing as required by ordinance for the purpose of receiving public comment regarding the proposed Administrative Plat and Conditional Use Permit on March 23, 2004; and, WHEREAS, the Planning Commission reviewed the application March 23, 2004 and found it consistent with the criteria for administrative plat review outlined in the Subdivision Ordinance; and, WHEREAS, the Planning Commission also found this application consistent with the performance standards for church facilities in the Business Park District; and, Resolution 2004-57 WHEREAS, the Planning Commission adopted a motion to recommend approval of the application for an Administrative Plat and Conditional Use Permit for Community of Hope Lutheran Church on March 23, 2004 with conditions. NOW, THEREFORE, BE IT RESOLVED, The Council of the City of Rosemount does hereby approve the Administrative Plat and Conditional Use Permit for Community of Hope Lutheran Church subject to the following conditions: 1. Issuance of a building permit. 2. Submittal of a plat illustrating the new combined property including a new legal description, all necessary easements, and dedication of rights-of-way prior to City Council action on this application. 3. Conformance with the landscaping revisions outlined in the March 23, 2004 staff report as well as the revision to the April 7, 2004 landscape plan as follows: a. Installation of an irrigation system in all areas except those designated for future expansion and the parking lot islands not containing trees or shrubs. b. Increase the number of overstory trees along Biscayne Avenue and 145th Street to equal one (1) tree every fifty (50) feet in conformance with the zoning ordinance. c. All coniferous trees shall be planted in a triangular pattern with 10-foot spacing to create a more natural appearance. At least 50 percent of these trees shall be at least six (6) feet tall and the remaining 50 percent shall be at least 4 feet tall. d. Add 1 deciduous overstory tree to each of the landscape islands on either side of the building’s southeast entrance. 4. Install a 5 foot wide sidewalk on the east property line along Biscayne Avenue and provide the City with a sidewalk easement around the Northern Natural Gas substation to connect the sidewalks along 145th Street and Biscayne Avenue. 5. Payment of park dedication fees in the amount of $36,450 on the 8.12 acre parcel. 6. Payment of all applicable development fees including SAC, WAC, storm water, and GIS fees based upon the fee schedule in place when the building permit is issued and compliance with all conditions of the City Engineer. 7. Conformance with all requirements from the Fire Marshall including: Resolution 2004-57 a.This building will be required to have an automatic fire suppression and a automatic fire alarm system installed through the facility. These systems shall be monitored by an approved monitoring company. b. A Post Indicator Valve (PIV) will be required on the water main service to this building. This valve shall be monitored also. c.All water mains that provide fire hydrants to this facility shall be looped. d.No “Parking Fire Lane” signs will be required on all fire department access roads. e.An approved key box for fire department access shall be provided. NOW, THEREFORE, BE IT FURTHER RESOLVED, The Council of the City of Rosemount does hereby recognize the new legal description of the plat as follows: Hope Acres, Section 29, Township 115, Range 19, Dakota County, Minnesota. ADOPTED this 20th day of April, 2004 by the City Council of the City of Rosemount. __________________________________________ William H. Droste, Mayor ATTEST: ___________________________________ Linda Jentink, City Clerk Motion by:______Riley_______________Second by:_______DeBettignies_______________ Voted in favor:_____DeBettignies, Droste, Riley________________________________ Voted against:______None______________________________________________________ Member absent:______Strayton, Shoe-Corrigan__________________________________ 1 Excerpt from the minutes of the March 23, 2004 Planning Commission Meeting Public Hearing: Community of Hope Lutheran Church – Simple Plat & CUP Assistant City Planner Jason Lindahl presented the application from Community of Hope Lutheran Church, requesting administrative plat and conditional use permit approvals to combine three lots into one property and allow construction of a 45,187 square foot church building on the property located on northwest corner of Biscayne Avenue and 145th Street. A church use is a conditional use in the Business Park Districts. This building will contain the new church facilities for the Community of Hope Lutheran Church. As designed, the site has the potential to accommodate two additional expansions which could more than double the size of the building. The applicant plans to combine Parcels A, B, and C into one property totaling approximately 8.64 acres (including right-of-way). Staff recommends a condition of approval require the applicant to submit a plat of the new combined property including a new legal description, all necessary easements, and dedication of rights-of-way prior to City Council action on this application. The proposed plat conforms with the lot performance standards for properties in the BP-4 District. The proposed church use is consistent with the current land use and zoning designations for the subject property. Staff finds that the proposed building meets the exterior materials standards for properties in the BP-4 District outlined in Section 7.2.A of the Zoning Ordinance. The proposed building will have precast concrete panel walls with two smooth cast-in accent bands along the front three sides of the building and along the northeast (back) entrance. The building will have three main entrances each accented with a spandrel glass system and two colors of rock faced block. The building will need roof top equipment and the applicant should provide staff with a plan illustrating how the equipment will be screened prior to City Council action on this item. The site exceeds the parking requirements of the zoning ordinance. The applicant proposes a 700 seat sanctuary building and the site does meet the minimum requirements for that. The landscape plan meets the minimum landscape and plantings requirements for a permitted use within the BP District. However, churches are a conditional uses in the BP District and subject to higher standards. As a result, staff recommends minor changes to increase screening and the overall year-round appearance of the site. The Zoning Ordinance requires all area not occupied by building or hardcover be landscaped with sod, rock, or mulch. The landscape plan calls for sod in the green areas between the front parking lot and Biscayne Avenue and 145th Street. The remaining 2 green areas will be seeded except the parking lot islands, which will contain mulch. Staff recommends that sod replace seed between the building and the parking lot along the northwest, east, and south sides of the buildings and that all areas not planned for future building expansion be irrigated. The plan calls for a mixture of Maple and Honeylocust overstory trees with spirea, dogwood, and junipers foundation plantings. In addition to the overstory trees, the plan calls for 60 ornamental (Crabapple) trees. Staff is concerned about the balance of deciduous and coniferous trees and its effect on screening and the year-round appearance of the site’s landscaping. Therefore, staff recommends that a condition of approval require the applicant to replace Crabapples trees with coniferous tree on the following basis: 2/3 of the Crabapples along Biscayne Avenue and 1/3 of those in the southeast corner of the site and along 145th Street. The grading plan illustrates three foot berms along both Biscayne Avenue and 145th Street as well as a two foot berm in the southeast corner of the site. Together, the proposed landscaping and berming conforms with the minimum parking lot screening requirements for the BP District. The Director of Parks and Recreation recommends a condition of approval require the developer to install a 5 foot wide sidewalk on the east property line along Biscayne Avenue. The applicant should also provide the City with a sidewalk easement around the Northern Natural Gas substation to connect the sidewalks along 145th Street and Biscayne Avenue. The commissioners asked about the parking requirements, and if the planned parking will meet the needs of the site. Assistant City Planner Lindahl explained that in the BP district, this site can be commercial or church use with the conditional use permit, and either way, the parking meets requirements of both uses. Chairperson Weisensel asked for comments from the applicants. Pat Qualley with Anderson Builders was present to answer questions. He stated that one thing that may need to change in the future, based on the limitations of the sanctuary/church use is the parking requirements. Currently, parking is adequate. He explained the intentions of the applicant as far as the expansions planned. Chairperson Weisensel opened the public hearing. Chairperson Weisensel asked for public comments. There were no public comments. MOTION by Weisensel to close the Public Hearing. Second by Messner. Ayes: Napper, Weisensel, Messner and Zurn. Nays: None. Motion carried. MOTION by Zurn to recommend approval of an administrative plat and conditional use permit to allow the combination of three lots into one property and the construction of a 3 45,187 square foot church building on the property located on the northwest corner of Biscayne Avenue and 145th Street, subject to the conditions outlined below. 1.Issuance of a building permit. 2.Submittal of a plat illustrating the new combined property including a new legal description, all necessary easements, and dedication of rights-of-way prior to City Council action on this application. 3. Replace seed between the building and the parking lot along the northwest, east, and south sides of the buildings with sod and demonstrate that all areas not planned for future building expansion will be irrigated. 4. Replace Crabapples trees with coniferous tree on the following basis: 2/3 of the Crabapples along Biscayne Avenue and 1/3 of those in the southeast corner of the site and along 145th Street. 5.Install a 5 foot wide sidewalk on the east property line along Biscayne Avenue and provide the City with a sidewalk easement around the Northern Natural Gas substation to connect the sidewalks along 145th Street and Biscayne Avenue. 6.Payment of park dedication fees in the amount of $36,450 on the 8.12 acre parcel. 7. Payment of all applicable development fees including SAC, WAC, storm water, and GIS fees based upon the fee schedule in place when the building permit is issued and compliance with all conditions of the City Engineer. 8.Conformance with all requirements from the Fire Marshall including: a.This building will be required to have an automatic fire suppression and a automatic fire alarm system installed through the facility. These systems shall be monitored by an approved monitoring company. b.A Post Indicator Valve (PIV) will be required on the water main service to this building. This valve shall be monitored also. c.All water mains that provide fire hydrants to this facility shall be looped. d.No “Parking Fire Lane” signs will be required on all fire department access roads. e.An approved key box for fire department access shall be provided. Second by Napper. Ayes: Weisensel, Messner, Zurn, and Napper. Nays: None. Motion carried. 4 Assistant City Planner Lindahl advised that this item will move on for consideration of approval by the City Council on April 20, 2004, providing all required items are submitted by the applicant as required. CITYOFROSEMOUNT EXECUTIVESUMMARYFORACTION Planning CommissionMeetingDate: March23, 2004 AGENDA ITEM: Community ofHopeLutheran ChurchAdministrativePlat AGENDASECTION: PublicHearing andConditionalUsePermit. PREPAREDBY: JasonLindahl, ALCP. AGENDA NO. C Assistant CityPlanner (d ATTACHMENTS: SiteLocationMap, SitePlan, APPROVED BY: FloorPlan, BldgElevations, ExistingConditions, Prelim Grading Plan, PrelimUtility Plan, PrelimLandscapePlan, LiohtinoPlan MOZI RECOMMENDED ACTION: MotiontorecommendtheCityCouncilapprovalofan administrative platandconditionalusepermittoallowthecombinationofthreelotsintoone propertyandtheconstruction ofa45,187squarefootchurchbuildingontheproperty located onthenortheastcornerofBiscayneAvenue and145Street, subjecttothe conditionsoutlinedbelow. 1. Issuance ofabuildingpermit. 2. Submittal ofaplatillustrating thenewcombined propertyincludinganewlegal description, allnecessary easements, anddedicationofrights -of -waypriortoCity Council actiononthisapplication. 3. Replaceseedbetweenthebuildingandtheparking lotalongthenorthwest, east, andsouthsidesofthebuildings withsodanddemonstrate thatallareas notplanned forfuturebuildingexpansion willbeirrigated. 4. ReplaceCrabapplestreeswithconiferous treeonthefollowingbasis: 2/3ofthe CrabapplesalongBiscayne Avenueand1/3ofthoseinthesoutheastcornerofthe siteandalong145Street. Installa5footwidesidewalk ontheeastpropertylinealongBiscayneAvenueand providetheCitywithasidewalkeasement aroundtheNorthernNaturalGas substation toconnectthesidewalksalong145StreetandBiscayne Avenue. 6. Paymentofparkdedicationfeesintheamountof $36,450onthe8.12acreparcel. 7. PaymentofallapplicabledevelopmentfeesincludingSAC, WAC, storm water, and GISfeesbaseduponthefeescheduleinplacewhenthebuildingpermitisissued andcompliancewithallconditionsoftheCityEngineer. 8. Conformance withallrequirements fromtheFireMarshallincluding: Thisbuildingwillberequiredtohaveanautomaticfiresuppression anda automaticfirealarmsysteminstalledthroughthefacility. Thesesystemsshall bemonitoredbyanapprovedmonitoringcompany. APostIndicator Valve (PIV) willberequiredonthewatermainservicetothis building. Thisvalveshallbemonitored also. c. Allwater mains thatprovide firehydrantstothisfacilityshallbelooped. d. No `ParkingFireLane" signswillberequired onallfiredepartmentaccess roads. e. Anapprovedkeyboxforfiredepartmentaccessshallbeprovided. ACTION: ISSUE BACKGROUND Applicant Property Owner(s) Location: AreainAcres: Comp. Guide PlanDesig: CurrentZoning: SUMMARY Community ofHopeLutheranChurch NortheastcornerofBiscayneAvenueand145Street 8.64 BPBusinessPark BP4, BusinessPark4 Theapplicant, Community ofHopeLutheran Church, requestsadministrative platand conditionalusepermitapprovalstocombinethreelotsintoonepropertyandallow construction ofa45,187squarefootchurchbuildingonthepropertylocatedon northeastcornerofBiscayneAvenue and145Street. Achurchuseisaconditional useintheBusiness ParkDistricts. Thisbuilding willcontainthenewchurch facilitiesfor theCommunity ofHopeLutheranChurch. Asdesigned, thesitehasthepotentialto accommodatetwoadditionalexpansionswhichcouldmorethandoublethesizeofthe budding. ANALSIS Administrative Plat Theapplicantwishestocombinethreeexisting lotsintoonepropertythroughthe administrative plattingprocess. Thisprocesscombinesthepreliminaryandfinalplat proceduresintoonereviewandapprovalsequencebeforethePlanningCommission 2 andCityCouncil. Initially, whentheapplicationwasfirstmade, theapplicant was intending tocombinethethree lotsandsplittheparcelintotwo. Afterdiscussions with staffthelotsplitportionoftherequesthasbeenomitted. Therefore, inthiscase, the administrativeplatfunctionslikealotcombinationprocess. However, therearebenefits fortheapplicantandcitybyfollowingthroughontheplattingprocess. Therearefourcriteriatoweighwhenreviewing anadministrativeplat. Thesecriteria andstaffsfindingsforeachareoutlinedbelow. Basedonthematerialssubmittedby theapplicant andthesefindings, staffrecommendsapproval oftheadministrativeplat request. 1. Theresultingsubdivisionshallcontainnomorethanthreelots. Finding: Theapplicantplans tocombineParcelsA, B, andCintooneproperty totaling approximately 8.64acres (includingright -of -way). Staff recommendsa condition ofapprovalrequire theapplicanttosubmitaplatofthenewcombined propertyincludinganewlegaldescription, allnecessary easements, and dedicationofrights -of -waypriortoCityCouncil actiononthisapplication. 2. Theproposedsubdivisionshallbeinareaswheremunicipalstreetsand utilities arealreadyinplaceandcapableofservicingtheplat. Finding: Thesubjectproperty islocated withintheCity'sMetropolitan Urban ServiceArea (MUSA). Inaddition, streetsaccessandmunicipalutilitiesare availablefrombothBiscayneAvenue and145Street. 3. Futurestreetsshallnotbeconstructedandtheproposedsubdivisionshall notinterferewithproperdevelopmentofneighboring adjacentproperties. FindingThemunicipalinfrastructure andsurroundingdevelopment pattern aroundthisdevelopmentarefirmlyestablished Therefore, thisplatwillnot interfere withdevelopmentofneighboringproperties. 4. Resultingparcelsshallconformwithallzoningordinancerequirements. FindingTheproposedplatconformswiththelotperformancestandardsfor propertiesintheBP -4District. Thesestandards areshowninthetablebelow. LotPerformanceStandardsfortheBP-4District Standard Requirement Proposed Status LotWidth 120ft 610ft Conformin LotArea 20,000sq. ft. 8.12Acres 353,660sq.ft.Conforming LotDepth N/A N/A N/A Density N/A N/A N/A 3 Conditional UsePermit Section615oftheZoning Ordinance designateschurchesasconditionaluseswithin theBusinessParkDistrict. Thepurposeofaconditional usepermitistomitigate any adverse effectsthatmayresultfromlanduseconflictsorsitedesign. Section 127of theZoning Ordinance outlinesthestandardsforconditional usesandgrantstheCitythe authoritytoadjustthetypical performancestandardsinagivezoningdistricttolessen potentiallyadverseeffectsoftheconditionaluse. SitePlan LandUse Zoning. Theproposedchurchuseisconsistent withthecurrent landuse andzoningdesignations forthesubject property. The2020LandUsePlanguidesthe propertyasBPBusinessParkwhiletheZoningMapdesignatesthesiteasBP-4, BusinessPark4. ChurchesareconditionalusesintheBP -4District. Thefollowing tablecompares thesestandardswiththoseproposed bythisdevelopment BuildinPerformanceStandardsfortheBP-4District Standard Requirement Proposal Status FrontYard 40ft.117ft 113ft.Conformin SideYard 10ft.208ft.Conformin RearYard 10ft.256ft Conforming BuildingHeight 35ft.30ft.Conformin Maximum Lot Coverage 75%68 Conforming 1SetbacksforbothBiscayneAvenueand145" Steet. 2representsmaximumlotcoverageincludingfutureexpansion. ExteriorBuilding Materials. Stafffindsthattheproposedbuildingmeetstheexterior materialsstandards forproperties intheBP -4DistrictoutlinedinSection7.2.Aofthe ZoningOrdinance. Theordinance requires 100percentofallexteriorwallstobefaced withoneoracombinationofthefollowingmaterials: brick, decorativeblock, glass, stucco, stone, orarchitecturalconcretepanels Theproposedbuildingwillhaveprecast concretepanelwallswithtwosmoothcast -inaccentbandsalongthefrontthreesidesof thebuildingandalongthenortheast (back) entrance Thebuildingwillhavethreemain entrances eachaccentedwithaspandrelglasssystemandtwocolorsofrockfaced block. Thebuildingwillneedrooftopequipment andtheapplicantshouldprovidestaff withaplanillustratinghowtheequipment willbescreenedpriortoCityCouncilaction onthisitem. S Access Parking Stafffindstheproposedaccessandparkingdesignconsistentwith thezoningordinancestandards, Theparkingareawillhaveabituminoussurface surrounded byconcrete curbandcutter. Theparkingareawillbeaccessed fromtwo curbcuts. Thenortheast curbcutislocatedalongBiscayneAvenueandalignswith BeechStreetwhilethesouthwestcurbcutislocatedalong145Streetandalignswith BlancaAvenue. Parking standardsforchurchfacilities areoutlinedinSection8.1.Handrequireonestall foreverythreeseatsinthelargestassemblyroom. Inthiscase, the700seatsanctuary requires234stalls. Inaddition, thebuildingwillhave12,800squarefeetofofficespace. Theordinancerequires1stallforevery200squarefeetofofficeoranadditional64 stalls. Alltotaled, theproposed churchusemustprovide298offstreetparkingstalls. Thesiteplanshows347totalstallsor49morethanrequiredbyordinance. More importantly, asdesignedthesiteisonlyonestallshortofwhatcouldbethemaximum parkingrequirement forthissite (office 1/200squarefeet) givenitscurrentBP -4 zoning Loading. Stafffindsthattheexistingaccessandparking areasufficient to accommodatetheloadingneedsofachurchuse. Shouldthebuildingchange to anotherusepermittedintheBPDistrict, theapplicant wouldberequiredtorevisethe parkingareatomeettheapplicableloadingareaandmaneuveringstandards TrashEnclosure. Stafffindstheproposed trashenclosure consistentwiththe performancestandardsforwastecontainerenclosures. Thesiteplanillustratesatrash enclosure atthesouthern endoftheparkingareabehindthebuilding. Theenclosure willbeconstructedofconcrete blockpaintedtomatchtheprincipalbuildingandhavea concreteslabwithaCedargate. Landscaping Berming. Thelandscape planmeetstheminimumlandscapeand plantings requirementsforapermittedusewithintheBPDistrict. However, churches areaconditionalusesintheBPDistrictandsubjecttohigherstandardsAsaresult, staffrecommendsminorchangestoincreasescreeningandtheoverallyear -round appearance ofthesiteTheserecommendationsandabreakdown ofthelandscape planareprovidedbelow. TheZoningOrdinance requiresallareanotoccupiedbybuildingorhardcoverbe landscapedwithsod, rock, ormulch. Thelandscapeplancallsforsodinthegreen areasbetween thefrontparkinglotandBiscayneAvenueand145Street The remaining greenareaswillbeseededexcepttheparkinglotislands, whichwillcontain mulch. Staffrecommends thatsodreplaceseedbetweenthebuildingandtheparking lotalongthenorthwest, east, andsouthsidesofthebuildingsandthatallareas not plannedforfuturebuildingexpansionbeirrigated. Theplantingsinthelandscape planmeetorexceedtheminimumrequirementsfora permitted usewiththeBPDistrict. Thetablebelowcomparesthesestandardswiththe 5 applicant'sproposal. TheplancallsforamixtureofMapleandHoneylocust overstory treeswithspirea, dogwood, andjunipersfoundationplantings. Inadditiontothe overstorytrees, theplancallsfor60ornamental (Crabapple) treesStaffisconcerned aboutthebalanceofdeciduousandconiferoustreesanditseffectonscreeningandthe year -roundappearance ofthesite'slandscaping Therefore, staffrecommends thata conditionofapprovalrequiretheapplicanttoreplaceCrabapples treeswithconiferous treeonthefollowingbasis: 2/3oftheCrabapples alongBiscayneAvenueand1/3of thoseinthesoutheastcornerofthesiteandalong145Street. LandscapePlantingsPerformanceStandardsfortheBP-4District Category Requirement Building Required Proposed Measurement Plantings Plantings OverStory 8Treesor 113,118 Trees 1/3,000Sq.Sq. Ft 38Trees 61 Ft. Foundation 1/10Linear 886 87 101 Plantings FeetofBldg.*LinearFeet RequiredGreenAreaofSite Thegradingplan illustrates threefootbermsalongbothBiscayneAvenueand145 Streetaswellasatwofootberminthesoutheastcornerofthesite. Together, the proposedlandscaping andbermingconformswiththeminimumparking lotscreening requirementsfortheBPDistrict. Signage. Asshow, theproposedmonument signsdonotconformwiththezoning Ordinance Thesiteplanillustratestwomonumentsigns. Byordinance, propertiesin theBPDistrictarelimitedtoonegroundmonumentsign. Bycomparison, theproposed wallsignage appearstomeetthezoningordinancestandardwhichallowsasignto cover20percentofthewallonwhichitisplacedAllsignage mustconformwiththe currentsignstandardsfortheBPDistrictandreceiveapprovalofaseparatesignpermit fromtheCity. ExteriorLighting. Theexteriorlightingplanappearstomeetthelightingperformance standardsfortheBPDistrict. Theplanillustrates sixpolelightsintheparkingareasand fivewalllightsonthesoutheast, north, andwestelevations. Allexteriorlightingshall directlighttoward theground andmaynotexceed 05lumensatthepropertyline. Engineering Engineering hadpreliminarily reviewedthesiteplanforthisprojectWhile theremaybedetailsthatneedtobeaddressed, thedonotseeanysubstantialissues thatwouldresultinsignificantmodificationstothesiteplan. PedestrianCirculation Stafffindsthesubjectpropertyhassufficienton -site pedestriancirculation. Thesiteplanshows5footwidesidewalksalong theinsideedge oftheparkingareasleading tothethreemainentrances. Inadditiontotheseon -sitesidewalks, theDirectorofParksandRecreation C recommends aconditionofapproval requirethedevelopertoinstalla5footwide sidewalkontheeastproperty linealongBiscayneAvenue. Theapplicantshouldalso providetheCitywithasidewalkeasementaroundtheNorthernNaturalGassubstation toconnect thesidewalksalong145StreetandBiscayneAvenue. ParkDedicationStaffrecommendstheapplicant payparkdedication feesinthe amountof $36,450areonthe8.12acreparcel. 7 I City Hall of Hope 0 n C 0 M M U N I f Y 0 E H 0 P E L U T H E R A N C H I I1 I 1 11s 1 s I II R11 eY i II A II II a III I AC CE5591E PARK L IR N Y t ryry s II K N_ i III I I 1 j I al I 9c I ACCESSIBLE CURB COT a COMMERCIAL PLAN REVI 'ORCORECOMPLIANCE r.moawl A Anc Ennxc t A. RTx T, s w j I N rtE PLpN A. ECO l I C 1£ m aw m L: 11IT LAA L xieaiJw,4by I LI LI. Ill 1111 f. l e° a COMMERCIAL PLAN REVI 'ORCORECOMPLIANCE r.moawl A Anc Ennxc A. RTx rtE PLpN A. ECO l m aw m L: 11IT LAA L M—: f1 x c' a a m A pi• 4w 0611 C ON IECORD =1 o. L__ unn...e IT BEECH ST W i nwaw4vLs a 145TH STREET WEST r.moawl A A. RTx rtE PLpN m aw 11IT L M—: f1 x c' a a IT Y ILI. pi• 1 0611 C ON IECORD =1 c mwm. Nn xou. en J "O Z. T b ENCL05URE OETALS 1 16- a r.moawlA4P- A _ AAA 11IT IT Y ILI.TIILIIAI1, ivA n..w ., d. e[.... x c mwm. Nn xou. en Z.1 16- 11111-1. a... °x „.1 S Ilf L. LT IA13 I INIIFRSONi fillses 0 EI- Uo z Q W ZW oF— m 0Jo UW a O z oILA CO INDETAIANDDETAILS Fu, x.mmv, Al L. op.Ixo0] 1313 3dA1MOQNIM mwy .mM. m. dA1 „w 7FJ N000 NvldenJ nnxir F` siiviaanw of rvriaaoos F0 r z D z on c C7 51801 L1H NOSM( LUYl 51 1tl]dwYl TV a F E j nl cuk wR- 1 so a AST 11VAPON NLRTH E iiON i mm Im 10111111111111= 11 " ImMiloul I mil WANUERSON Elf e, ulu F v U ov z€ 2 ZW o c L J N Oo U W D O HUILOING FIEVAiIONS I f NOR iXWE EYALION Ax' 3 rvpe xa0]iP3i WE9 ELEVAi -O n) sa ipe cb' omsoiIu. i mm Im 10111111111111= 11 "ImMiloul Imil WANUERSON Elf e, ulu F v U ov z€ 2 ZW o c L J N Oo U W D O HUILOING FIEVAiIONS I f NOR iXWE EYALION Ax' 3 rvpe xa0]iP3i WE9 ELEVAi -O n) sa ipe cb' WANUERSON Elf e, ulu F v U ov z€ 2 ZW o c LJ N Oo UW D O HUILOING FIEVAiIONS I f NOR iXWE EYALION Ax' 3 rvpe xa0]iP3i WE9 ELEVAi -O n) sa ipe cb' B NCA I z J l 9 g g y cag pi g a S as g s q fir gg Lii ; Ism 8 111 a Egg s4 IF piia ° t g g 84g I Fa 8 ; if g5 a gl H iggEd& r i COMMUNITY L e I ` s 3 x E) HOPE LUTHER CHURCH bC F 9 2 OVNT M'NNESCTA aSSMCB IG CONDITIONS I F S892221' E63310 0 a4a N i SYMBOLSLEGEND PARCL8 caMrz' I e owfrvm [u,wxs Y av .x_ CtRiNO1430 cafe 4 IAEY Al lwIns VPQd DETAILoz ffE9] Op SILTFENCE caxmmfw[ 21 rN8922 21'Wfix. Y IIi W 0z C. 9 p a IPARCELA vO IGERTNO92429 41 u Ll s1AeILIZEOVEHICLEEXIT z I 1c o ppoz- op 8I 8 3ICB [xuECr sII nfl5sr r' sI 4 5THTEEi_ =W —S ' r vnv: rsszs- ia- ss— 'rtersnn'rsndo> I a. x.. sEcmy.un.wx zi f I I rI 1 w1 1 I S17 1 rt t l 1Ii L i PaRC Le1g3a30 ifE .91Yw PARCt c42 cEFTN< z 1 111TY fj r\ ICONNECTIONSNOTE 0. ex ao. 5u ¢w( cro M1qw ct WOROO IIRI-itp rtRCS I F 1 V AGGY OLBY SSOQA' FES e c L 0 w 7n O z a d w a a U Q J Q Z r J a 8922' 21'E63310e w w.. R. Q11 —IL µ...,. µ^w euYnwcaeE¢• .nox nuue.. ssrrv::aw. eun ov.. 5 e rw 5 usvx., umzrwnw,..P AR C(CB CERT NO iw+wc oyut exsuus1 I WCWO'MGevENGllMxi'iowrnOnnxcmuusIgopvur.ovcnuws... e .nc.ra l upiw[PLANT SCI ICD fu922' 13310 PN54 MRIe..,. PARCEL Aa..CERT NO 92429 1 i YrTflEE P SMfl1:9P LA. NLINCk a f r V AGGY OLBY SSOQA' FES e c L 0w 7 n O z a d w a a U Q J Q Z r 145THSTREETWEST oxix u 0lwrvnrvA m l I I BEECHSiw m it ly la A rAVIERSON uuLne¢ x fl 4 LiU o Om Q ZW CO GF UW 0- O LIGHTINGPLAN I: nL: l, Ia• Iilli' tillllL: L1y B, it 145THSTREETWEST oxix u0lwrvnrvA m l I I BEECHSiw m it ly la A rAVIERSON uuLne¢ x fl 4 LiU o O m Q ZW C O GF U W 0- O LIGHTINGPLAN I: nL: l,