EXECUTIVE SUMMARY
City Council Regular Meeting: November 5, 2018
AGENDA ITEM: Accept Quotes for Well 1 & 2 Sealing and
Award Contract
AGENDA SECTION:
Consent
PREPARED BY: Brian Erickson, PE, Director of Public
Works/City Engineer AGENDA NO. 6.i.
ATTACHMENTS: Letter of Recommendation; Bid
Summary; Bid Tabulation APPROVED BY: LJM
RECOMMENDED ACTION: Motion to accept quotes and award contract for Well 1 & 2
Sealing, City Project 2018-04.
BACKGROUND
For the final stage of sealing Wells 1 & 2, quotes were solicited from three licensed well drilling companies
to perform the final sealing operations. To date, Kimmes-Bauer has completed the previous two phases
which included:
• Exposing the well casings and extending them above grade.
• Drilling/cleaning the casing to facilitate an examination by the Minnesota Department of Health
(MDH).
The final phase required for sealing the wells includes grouting the casing as directed by the MDH. Once
completed the casings will be cut below grade and the parking lot will be repaired via separate contractor.
During this process, the property owner has been informed as to the status of work.
The three quotes are as follows:
• E.H. Renner and Sons - $39,569.00
• Kimmes-Bauer - $39,863.00
• Keys Well Drilling - $49,100.00
The engineer’s estimate was $32,795.00. The low quote was $6,774.00 more or approximately 21% above
the estimate. Upon completion of this work, staff and the engineer will be able to request reimbursement
from the MDH for up to 50% (not to exceed $50,000). This project was included in the 2018 Water
Budget in the amount of $150,000, and to date approximately $48,500 has been expended.
RECOMMENDATION
Staff recommends Council accept the low quote from and award the contract to E.H. Renner and Sons.
178 East 9th Street, Suite 200| St. Paul, MN 55101 | (651) 286-8450
Building a legacy – your legacy.
Equal Opportunity Employer | wsbeng.com
K:\010497-000\Admin\Construction Admin\010497-000 LOR 103118.docx
October 31, 2018
Honorable Mayor and City Council
City of Rosemount
2875 145th Street W
Rosemount, MN 55068
Re: Rosemount Wells No. 1 & 2 Abandonment
City of Rosemount Project No. 2018-04
WSB Project No. 010497-000
Dear Mayor and Council Members:
Quotes were received for the above-referenced project on Tuesday, October 30, 2018. Three quotes
were received. The quotes were checked for mathematical accuracy. Please find enclosed the bid
summary indicating the low bid as submitted by E.H. Renner & Sons, Inc., Elk River, Minnesota in the
amount of $39,569.00. The Engineer’s Estimate was $32,795.00.
We recommend that the City Council consider these bids and award a contract in the amount of
$39,569.00 to E.H. Renner & Sons, Inc. based on the results of the bids received.
Sincerely,
WSB & Associates, Inc.
Ray Theiler
Project Manager
Attachment
kkp
PROJECT:
City Project No. 2018-04
OWNER:
City of Rosemount, MN
WSB PROJECT NO.:
010497-000
Quotes Received: October 30, 2018 by 3:00 pm
Contractor Total Bid
1 E.H. Renner & Sons, Inc. $39,569.00
2 Kimmes-Bauer Well Drilling, Inc. $39,863.00
3 Keys Well Drilling Co. $49,100.00
Engineer's Opinion of Cost $32,795.00
Denotes corrected figure
Ray Theiler, Project Manager
BID TABULATION SUMMARY
I hereby certify that this is a true and correct tabulation of the quotes as received on October 30, 2018.
Rosemount Wells No. 1 & 2 Abandonment
K:\010497-000\Admin\Construction Admin\010497-000 Bid Tab Summary 103018
*No.ItemUnits Qty Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total PriceSCHEDULE A: WELLS NO. 1 & 2 ABANDONMENT1MOBILIZATION / DEMOBILIZATION: LUMP SUM 12,000.00$ 2,000.00$ 8,359.00 $8,359.00 $1,800.00 $1,800.00 $7,500.00 $7,500.002WELL NO. 1: INSTALL GROUT PIPE TO BOTTOM OF OPEN HOLE, 231' BY CLEANING/AGITATING MATERIAL WITHIN OPEN HOLELUMP SUM 12,000.00$ 2,000.00$ 600.00$600.00 $1,200.00 $1,200.00 $4,500.00 $4,500.003WELL NO. 1: GROUT ANNUALR SPACE FROM 231' TO 4' CU YDS 5600.00$ 3,000.00$ 500.00 $2,500.00 $525.00 $2,625.00 $600.00 $3,000.004WELL NO. 2: INSTALL GROUT PIPE TO BOTTOM OF OPEN HOLE, 425' BY CLEANING/AGITATING MATERIAL WITHIN OPEN HOLELUMP SUM 12,000.00$ 2,000.00$ 1,000.00 $1,000.00 $6,000.00 $6,000.00 $7,500.00 $7,500.005WELL NO. 2: GROUT ANNUALR SPACE FROM 425' TO 4'CU YDS 25600.00$ 15,000.00$ 500.00 $12,500.00 $525.00 $13,125.00 $600.00 $15,000.006MOBILIZATION/DEMOBILIZATION OF VACUUM TRUCK OR CONTAINMENT VESSEL TO COLLECT CUTTINGS /DEBRIS/DRILL AND HAUL OFF SITE.LUMP SUM 15,000.00$ 5,000.00$ 5,500.00 $5,500.00 $9,260.00 $9,260.00 $6,000.00 $6,000.007REMOVE EXPOSED SECTIONS OF CASINGS TO 3' BELOW GRADELIN FT 8225.00$ 1,800.00$ 150.00 $1,200.00 $250.00 $2,000.00 $50.00 $400.008AGGREGATE BASE CLASS 5TON 1520.00$ 300.00$ 135.00 $2,025.00 $15.00 $225.00 $130.00 $1,950.009BITUMINOUS MATERIAL FOR TACK COATGALLON 55.00$ 25.00$ 15.00$75.00 $10.00$50.00 $100.00 $500.0010TYPE SP 12.5 WEARING COURSE MIXTURE (2,C) TON 1075.00$ 750.00$ 495.00 $4,950.00 $250.00 $2,500.00 $200.00 $2,000.0011SEALING PERMITS AND SUBMITTALSLUMP SUM 1700.00$ 700.00$ 360.00$360.00 $728.00 $728.00 $250.00 $250.0012FURNISH AND INSTALL PEA ROCK IN WELL. INCLUDE MATERIAL FOR PROPER SEALING MANDATED BY MDH.CU YDS 2110.00$ 220.00$ 250.00$500.00 $175.00 $350.00 $250.00 $500.0032,795.00$ $39,569.00$39,863.00$49,100.00I hereby certify that this is an exact reproduction of quotes received.DATE: October 31, 2018KeysBID TABULATIONROSEMOUNT WELLS NO. 1 & 2 ABANDONMENTCITY OF ROSEMOUNT PROJECT NO. 2018-04TOTAL SCHEDUL A: WELLS NO 1&2 ABANDONMENTDenotes Corrected FigureDate: October 30, 20182875 145th Street West178 East 9th Street, Suite 200Rosemount, MN 55068OWNER:PROJECT CONSULTANT:City of RosemountWSB & Associates, Inc.St. Paul, MN 55101ENGINEERS ESTIMATE E.H. Renner and SonsQUOTE SUBMITTAL TIME:Time: 3:00 PMKimmes-BauerPage 1K:\010497-000\Admin\Construction Admin\010497-000 bid tab 103118