HomeMy WebLinkAbout4.b. Request by Lennar
EXECUTIVE SUMMARY
Planning Commission Meeting: January 22, 2019
Tentative City Council Meeting: February 19, 2019
AGENDA ITEM: 19-1-FP Request by Lennar for Final Plat
Approval of Bella Vista 6th Addition
AGENDA SECTION:
Consent
PREPARED BY: Kyle Klatt, Senior Planner AGENDA NO. 4.b.
ATTACHMENTS: Location Map; Preliminary Plat Area;
Final Plat; Updated Construction Plans
(Grading, Streets, Details); Landscape
Plan; Parks and Recreation Memo Dated
January 17, 2019; Engineer’s Memo
Dated January 17, 2019
APPROVED BY: KL
RECOMMENDED ACTION: Motion to recommend that the City Council approve the Final
Plat for Bella Vista 6th Addition subject to the following conditions:
1. Execution of a Subdivision Agreement.
2. Drainage and utility easements with storm sewer infrastructure may contain fences
but shall be required to include gates to provide truck access; shall prohibit sheds or
other accessory structures; and shall prohibit landscaping that would impede
drainage.
3. The storm water management plan shall be revised to eliminate any infrastructure
from the Autumn Path right-of-way.
4. The final plat shall include all easements as requested by City, including those
required by the storm water plan changes in the preceding condition.
5. Provision of $14,700 for landscaping surety.
6. Payment of $2,100 for landscaping to be installed following construction of Autumn
Path.
7. Submission of a revised landscape plan that takes includes the location of the
temporary lift station.
8. Payment of $64,600 for Fee-In-Lieu of Park Dedication.
9. A grading and landscaping easement shall be dedicated on the eastern 30 feet of
lots adjacent to the future Autumn Path.
10. Compliance with the conditions and standards within the City Engineer’s
Memorandum dated January 17, 2019.
2
SUMMARY
Applicant: Lennar Corporation
Comp. Guide Plan Designation: LDR – Low Density Residential
Current Zoning: R-1, Low Density Residential with the Bella Vista Planned Unit
Development (R-1: PUD)
Gross Area: 9.4 Acres
Net Area: 9.4 Acres
Lots/Units: 19 Single Family Lots
Gross Density: 2.02 units/acre
Net (Met Council) Density: 2.02 units/acre
The applicant, Lennar Corporation (Lennar), requests approval of a Final Plat for Bella Vista 6th Addition
to allow development of 19 single family lots. This plat represents the latest addition to a multi-phase
preliminary plat first approved by the City in 2013. The final plat is necessary to facilitate subdivision of
the subject property into individual residential lots, outlots, and public streets. Staff finds the application
consistent with the Bella Vista Preliminary Plat and recommends approval of this application subject to the
conditions detailed in the attachments and the motion above.
BACKGROUND
In July 2013, the City Council approved a preliminary plat, Planned Unit Development (PUD) master
development plan with rezoning, and zoning ordinance amendment for the 158 single family lot Bella
Vista development. In November 2013, the City approved the first phase of Bella Vista, a 28 lot
subdivision named Bella Vista 2nd Addition. The City approved the first half of Phase 2, Bella Vista 3rd
Addition in April 2015 and the second half of Phase 2, Bella Vista 4th Addition, in March of 2016. The
third phase of Bella Vista (5th Addition) with 41 additional single family lots was platted in the latter
portion of 2016. At this time, the applicant would like to begin construction in the fourth phase of the
project with the 19 lots within Bella Vista 6th Addition.
Please note that the 6th Addition is the last final plat within the overall Bella Vista project that may
approved before Autumn Path is constructed for access to the northern portion of the preliminary plat
area.
ISSUE ANALYSIS
Legal Authority . This application is a Quasi-Judicial action. The final plat application is Quasi-Judicial
because the City has a set of standards and requirements for reviewing this type of application that is
described in detail below. Generally, if the final plat meets the ordinance requirements it must be
approved.
Land Use and Zoning . The proposed 19 lot single family final plat is consistent with the current land
use and zoning classifications. The subject property is guided LDR – Low Density Residential and zoned
R-1PUD, Low Density Residential Planned Unit Development. As a result, the property is subject to all
the standards of the R-1, Low Density Residential zoning districts as well as the standards for detached
single family units contained in the approved PUD. While this development is subject to all of the
conditions and development standards contained in the PUD, the most notable deviations from the
requirements of the Low Density Residential zoning districts are provided below. All these items were
anticipated in the preliminary plat approval and were part of the initial PUD approval.
1. Section 11-4-5 F. 1. R-1 Minimum Lot Area: The minimum lot area shall be 9,250 square feet.
3
2. Section 11-4-5 F. 2. R-1 Minimum Lot Width: The minimum lot width shall be 75 feet.
3. Section 11-4-5 F. 4. R-1 Minimum Front Yard Setback: The minimum front yard setback shall be 25
feet.
4. Section 11-4-5 F. 5. R-1 Minimum Side Yard Setback: The minimum side yard setback shall be 7.5
feet.
5. Comprehensive Wetland Management Plan Section IX. B. Structural Setback from Wetland
Buffers: The structural setback for lots containing wetland buffers shall be a minimum of 20 feet.
6. Section 11-4-5 F. 9. R-1 Maximum Lot Coverage: The maximum lot coverage shall be 40% for lots
below 11,250 square feet and 35% for lots between 11,250 and 15,000 square feet. The maximum lot
coverage for lots over 15,000 square feet remains at 30%.
Final Plat. Standards for reviewing subdivision requests are detailed in Title 12 of the Rosemount City
Code. This section of the Code outlines the two-step Preliminary and Final Plat process for land
subdivision. In this case, the preliminary plat was approved in July 2013 consisting of 158 single family lots
and various outlots. The Bella Vista Final Plat included subdividing into outlots to permit transfer of
property to the City and Lennar. The 6th Addition final plat will subdivide Outlot A of Bella Vista 5th
Addition into 19 buildable lots.
Streets & Access. The final plat are will include an extension of 131st Court West from its existing
connection point along Aulden Avenue to a cul-de-sac that terminates at the eastern edge of the Bella
Vista property. All lots within the subdivision will have direct access to the cul-de-sac street, and will be
able to exit the subdivision via internal neighborhood connection streets to either Bacardi Avenue to the
west or Bonaire Path to the south. The southern connection to Bonaire is a temporary access point that
will be realigned when an adjoining parcel is developed. No connection is planned from 131st Street Court
to the future Autumn Path alignment due to the spacing of existing or planned connections along this
road. No dedication of Autumn Path is required within the 6th Addition plat because the planned road
alignment falls entirely on the adjacent parcel in this area.
Water and Sanitary Sewer. The plans for Bella Vista 6th Addition must be modified to include the
construction of a temporary lift station to serve this subdivision until the permanent trunk sewer line is
installed in Autumn Path. The developer is proposing to install the temporary lift station on Lot 11, Block
1, which is sized appropriately to accommodate the lift station and proposed building pad. The City will
require a financial security to ensure the timely removal of the temporary lift station when the Autumn
Path project is complete.
Landscaping and Berming . The approved landscape plan is consistent with the minimum number of
plantings required by City Code (one per interior lot and two per corner lot). The plan includes 40
boulevard trees, 7 buffer/boulevard trees along the future Autumn Path alignment in the southeastern
portion of the plat, and an additional 9 trees near the end of the 131st Court West cul-de-sac. The
additional trees were included in the preliminary landscape plan as part of the required tree replacement
for trees removed by the developer during grading activity. Unless the developer wishes to install the trees
along the future site of Autumn Path prior to the construction of the street, the cost of the trees must be
provided to the City for future installation. The trees would then be planted by the City following
construction of Autumn Path. At $300 per tree based on the City fee schedule, the landscaping security
totals $14,700. The cost of the trees and landscaping along the future Autumn Path totals $2,100.
The landscape plan will need to be revised to account for the temporary lift station on Lot 11 since some
of the required replacement trees are depicted in the lift station area. Staff is recommending that these
trees be placed either around the lift station or in other open areas on the site.
Storm Water Management. The original storm water plans for this section Bella Vista anticipated that
storm water from the 6th Addition would be directed to pipes within Autumn Path and then sent into a
4
larger retention basin directly north of the subdivision. Because Autumn Path and any corresponding
infrastructure within the roadway have yet to be constructed, the developer will not be able to fully
implement the storm water plan as approved (at least in the near-term). As an alternative, the developer is
proposing to reroute all storm water infrastructure internal to the 6th Addition via wider easements
between some of the proposed lots. This alternative should be feasible because some of the easternmost
lots in the subdivision are slightly wider than the 75-foot minimum within the PUD. The developer will
need to amend the storm water management plan to accommodate the proposed re-routing of storm water
runoff in the project area, and staff has drafted a condition of approval that requires approval of the
revised plan by the City Engineer.
Grading . Due to poor soils on the site, the roadway section will likely need to be increased. The road
section should be reviewed in final design and verified during construction. The road section used in the
earlier Bella Vista additions was 4 inches of pavement, 6 inches of class 5, 36 inches of select granular, and
geotextile fabric. Also, because it is unclear when Autumn Path will be constructed, a grading and
landscaping easement should be placed upon the eastern 30’ of the lots backing up to the future Autumn
Path. The easement will allow future grading and installation of the road and planting of landscaping unto
private property.
Parks and Open Space. Parks and Recreation staff reviewed the plans for final plat of Bella Vista 6th
Addition and found them to be consistent with the previous Bella Vista plans. The park dedication
requirement for 19 single family lots is 0.76 acres of land (19 units x .04 acres) or cash in-lieu of land.
Because no more land is required for parks within Bella Vista, staff is recommending that the City collect
cash in-lieu of land for the 19 units. This amount totals $64,600 (19 x $3400).
Sidewalks, Trails, and Pathway. The applicant’s plan indicate sidewalks will be placed consistent with
the requirements of the preliminary plat. The plans include a sidewalk along the northern side of 131st
Court West that includes a stub to the eastern properly for a future connection to Autumn Path. A section
of regional trail running through the area immediately north of Bella Vista 6th Addition will be constructed
when funding allows and will provide a connection to the trail in Meadows Park to the south and
eventually into Erickson Park and Downtown Rosemount.
Engineering Comments. The Project Engineer has reviewed the proposed Bella Vista 6th Addition final
plat and has provided comments in the Engineer’s Memo dated January 17, 2019. Notable comments
include: updating the construction plans to reflect the correct naming for all project phases, providing
adequate dedication of easements for the proposed lift station, storm water pipes, and other infrastructure
based on proposed revisions to the plans, final siting and construction of a temporary lift station, and
modification to the grading plan to address engineering concerns.
Development fees as detailed in the Engineer’s Memo dated January 17, 2018, are due with the final plat
and subdivision agreement.
CONCLUSION & RECOMMENDATION
Staff recommends approval of the Final Plat for Bella Vista 6th Addition creating 19 single family lots. This
recommendation is based on the information submitted by the applicant, findings made in this report, and
the conditions detailed in the attached memorandums.
Dakota County, MN
Property Information
Ja nuary 1 8, 2019
0 875 1,750437.5 ft
0 270 540135 m
1:9,600
Disclaimer: Map and parcel data are believed to be accurate, but accuracy is not guaranteed. This is not a legal document and should not be substituted for a title search,appraisal, survey, or for zoning verification.
Phone (952) 937-5150 7699 Anagram Drive
Fax (952) 937-5822 Eden Prairie, MN 55344
Toll Free (888) 937-5150
Phone (952) 937-5150 7699 Anagram Drive
Fax (952) 937-5822 Eden Prairie, MN 55344
Toll Free (888) 937-5150
Phone (952) 937-5150 7699 Anagram Drive
Fax (952) 937-5822 Eden Prairie, MN 55344
Toll Free (888) 937-5150
Phone (952) 937-5150 7699 Anagram Drive
Fax (952) 937-5822 Eden Prairie, MN 55344
Toll Free (888) 937-5150
Phone (952) 937-5150 7699 Anagram Drive
Fax (952) 937-5822 Eden Prairie, MN 55344
Toll Free (888) 937-5150
Phone (952) 937-5150 7699 Anagram Drive
Fax (952) 937-5822 Eden Prairie, MN 55344
Toll Free (888) 937-5150
Phone (952) 937-5150 7699 Anagram Drive
Fax (952) 937-5822 Eden Prairie, MN 55344
Toll Free (888) 937-5150
Phone (952) 937-5150 7699 Anagram Drive
Fax (952) 937-5822 Eden Prairie, MN 55344
Toll Free (888) 937-5150
Phone (952) 937-5150 7699 Anagram Drive
Fax (952) 937-5822 Eden Prairie, MN 55344
Toll Free (888) 937-5150
Phone (952) 937-5150 7699 Anagram Drive
Fax (952) 937-5822 Eden Prairie, MN 55344
Toll Free (888) 937-5150
Phone (952) 937-5150 7699 Anagram Drive
Fax (952) 937-5822 Eden Prairie, MN 55344
Toll Free (888) 937-5150
MEMORANDUM
To: Kyle Klatt, Senior Planner
CC: Kim Lindquist, Community Development Director
Stacy Bodsberg, Planning & Personnel Secretary
Brian Erickson, Director of Public Works/City Engineer
From: Stephanie Smith, Assistant City Engineer
Date: January 22, 2019
Subject: Bella Vista 6th Final Plat- Engineering Review
SUBMITTAL:
The plans for Bella Vista 6th have been prepared by Westwood dated December 6, 2018.
Engineering review comments were generated from the following documents included in the
submittal:
▫ Grading and Drainage Plan
▫ Final Plat
GENERAL COMMENTS:
This area of Bella Vista was referred to as Phase 4 South when the Bella Vista development was
originally reviewed by staff in 2013, so this title may be used interchangeably with “6th Addition”
in this memorandum.
1. The development fees below are estimated based on the current Schedule of Rates and
Fees. These fees are due with the final plat and subdivision agreement.
Sanitary Sewer Trunk Charge: $1075/acre
Watermain Trunk Charge: $6500/acre
Storm Sewer Trunk Charge: $6865/acre
2. The 2013 Feasibility Report for Bella Vista estimated the cost for the western half of the
Autumn Path street improvement in the amount of $576,000. This western half is to be
paid with the development of Bella Vista. The amount was divided among the 86 lots for
Bella Vista 5th Addition and the future phases 4 South and 4 North. The amount due
with the final plat for the 19 lots in Bella Vista 6th is 19 lots * $6,698/lot = $127,262.00.
3. The plan shall be revised to clearly show proposed work in Bella Vista 6th Addition vs.
work that has been completed in previous additions vs. work that will be completed in
future additions.
4. The plan shall be updated to call the phases by their platted addition numbers. The area
proposed to be platted as Bella Vista 6th is called out as 5C in the submitted grading plan.
5. Lot 20, Block 1 shall be relabeled as Lot 1, Block 1 of Bella Vista 5th.
6. The developer is required to obtain a NPDES Construction Stormwater Permit and
provide a copy of the approved SWPPP to the City prior to the start of any construction
activity.
7. Due to poor soils on the site, the roadway section may need to be increased. The road
section should be reviewed in final design and verified during construction.
RIGHT OF WAY AND EASEMENTS:
The plat includes dedication of right-of-way for 131st Street cul-de-sac. The plat shows the
location of an existing, gas pipeline easement through the back yards of Lots 11-19, Block 1.
Public drainage and utility (D&U) easements are shown over the ponding area in the back yards
of Lots 11-19, Block 1. D&U easement is also shown on the east side of Lot 11, Block 1 for a
proposed lift station.
8. Crossing permits and grading permits are likely required from the gas companies for the
proposed improvements. The developer is required to work with the gas companies to
execute any required permits.
9. The drainage and utility easement in the front yard of Lot 10, Block 1 may be reduced as
the lift station location has been moved to Lot 11, Block 1.
10. City staff anticipates additional D&U easement will be required to accommodate
stormwater pipe between Lots 11 & 12 and Lots 9 & 10, Block 1.
STREET AND SIDEWALK
This development consists of extending 131st Street, which was stubbed off Aulden Avenue in
Bella Vista 5th. 131st Street will end in a cul-de-sac at the eastern edge of the plat. It is not
anticipated to connect to Autumn Path when that road is constructed in the future. A sidewalk
will be constructed on the north side of the street and will connect to the Horseshoe Park trail
constructed in 2018.
11. The applicant shall grade the trail north of Lots 1-10, Block 1.
12. The applicant shall submit a signage and street lighting plan for review.
WATER AND SANITARY SEWER
The Feasibility Report for Bella Vista, dated
November 19, 2013 included construction of a
temporary sanitary sewer lift station to service this
addition until the construction of a trunk sewer line
on Autumn Path (see figure to the right). The
submittal did not include proposed design for
watermain or sanitary sewer.
13. This addition shall include construction of a
temporary sanitary lift station on Lot 11,
Block 1 and construction of forcemain along 131st Street to tie-in to gravity sewer along
Aulden Avenue at the developer’s cost. This location has been modified from the
Feasibility Report to allow Phase 4 South to be constructed separately and prior to the
platting of Phase 4 North.
14. The developer shall escrow funds for the removal of the temporary lift station and the
sanitary connection to Autumn Path.
15. No City Core funds or credits are anticipated for this phase of Bella Vista.
16. The applicant shall submit plans for watermain and sanitary sewer that are consistent
with City of Rosemount Engineering Guidelines and Standard Specifications and Detail
Plates.
GRADING AND DRAINAGE
The proposed grading includes the front half of lots drain stormwater to the street and the back
half of the lot would flow away from the street. The back of Lots 11-16, Block 1 include a
drainage swale to collect the runoff in a backyard storm system.
17. Lots 14-16, Block 1 shall have draintile in the backyard swale that shall be owned by a
Homeowners Association (HOA).
18. The plan shall be revised to show driveway locations and label the driveway grades for
city staff review.
19. The plan shall be revised to show spot elevations between lots to prevent runoff towards
the proposed building pads.
20. The basement floor elevation of Lots 11-14, Block 1 do not meet the 1-foot freeboard
requirement from the 100-year High Water Level (HWL) of the pond south of these
lots. The design must be revised to meet this requirement or the applicant must
demonstrate that this standard creates a hardship and, if a hardship is demonstrated,
meet the requirements for a waiver in the Rosemount Engineering Guidelines.
STORMWATER
The stormwater design for this development cannot be reviewed at this time. The proposed
design, consistent with the preliminary design, routes stormwater through catch basins in
Autumn Path.
21. As Autumn Path will not be constructed with Bella Vista 6th, the stormwater will need to
be redesigned prior to final plat approval by Council. Staff has been in discussion with
the applicant’s engineer regarding a new alignment that would route stormwater to Pond
5 between Lots 9 and 10, Block 1 and Horseshoe Lake without entering the Autumn
Path storm system.
22. The catch basin at the end of the cul-de-sac bubble shall have a 3-foot sump.
Should you have any questions or comments regarding the items listed above, please contact
me at 651-322-2015.
MEMORANDUM
To: Kim Lindquist, Community Development Director
Kyle Klatt, Senior Planner
Anthony Nemcek, Planner
From: Dan Schultz, Parks and Recreation Director
Date: January 17, 2019
Subject: Bella Vista 6th Addition – Final Plat
The Parks and Recreation Department recently received a final plat for the Bella Vista 6th Addition.
After reviewing the plat, the Parks and Recreation Department staff has the following comments:
Parks Dedication
Staff is recommending that the City collect cash dedication for this final plat to satisfy the parks
dedication requirement for the Bella Vista 6th Addition. The cash dedication will be $64,600 (19 units
x $3,400 per unit).
Please let know if you have any questions about this memo.