HomeMy WebLinkAbout9.c. Receive Feasibility Report, Call for Improvement Hearing and Order Plans and Specifications for the 2019 Street Improvement Project, City Project 2019-01i:\city clerk\agenda items\approved items\9.c. receive feasibility report, call for improvement hearing and order plans and specifications for the 2019 street
improvement project, city project 2019-01.docx
EXECUTIVE SUMMARY
City Council Meeting: March 19, 2019
AGENDA ITEM: Receive Feasibility Report, Call for
Improvement Hearing and Order Plans
and Specifications for the 2019 Street
Improvement Project, City Project 2019-
01
AGENDA SECTION:
New Business
PREPARED BY: Brian Erickson, PE, Director of Public
Works / City Engineer
Stephanie Smith, MN PE, Assistant City
Engineer
AGENDA NO. 9.c.
ATTACHMENTS: Resolution APPROVED BY: LJM
RECOMMENDED ACTIONS: Motion to Adopt a Resolution Receiving the Feasibility
Report, Calling for the Improvement Public Hearing, and Order Plans and Specifications for
2019 Street Improvement Project, City Project 2019-01.
BACKGROUND
The 2019 Street Improvement Project, City Project 2019-01, is proposed to consist of an asphalt mill and
overlay on the majority of the streets, with full depth reclamation on Dodd Boulevard and the southern
section of Chippendale Avenue. Minor utility work and rehabilitation of pedestrian ramps to meet current
ADA requirements within the project limits will also be included. Pavement mill and overlay on both sides
of the Connemara Trail bridge and the Fire Station #1 Parking Lot were also evaluated for inclusion in the
project.
On January 15, 2019 the Council approved a contract for engineering services with TKDA for 2019 Street
Improvement Project, City Project 2019-01. TKDA authored a report on the feasibility of this project.
Detailed project information is included in the Feasibility Report available on file in the Engineering
Department. The report found this project, as proposed, to be feasible, cost effective, and necessary.
The resolution calls the Public Improvement Hearing on April 16, 2019, which is a necessary step under
the Minnesota Statutes Chapter 429. A full presentation of the proposed improvements will be made at the
Hearing.
COSTS & FUNDING
The Feasibility Report estimated the project cost at $2,411,000 as tabulated below. Table 2 has separated
out the portions of the project that are not anticipated to be assessed.
2
This project is scheduled in the 2019-2028 CIP. The estimated cost from the Feasibility Report is
approximately 41% higher than the CIP estimate. Some of the cost increase is due to the change in scope
of work on Dodd Boulevard and the southern portion of Chippendale Avenue. The geotechnical
investigation of the roadway recommended more intensive rehabilitation for these roadways. This
additional cost will be funded by a combination of MSA and assessments. Other increased costs include
adding the parking lot maintenance (to be paid with the general fund) and pedestrian improvements.
The project is proposed to be funded by a combination of MN State-Aid funds, general funds, utility
funds, and special assessments of benefitting properties. A preliminary assessment roll is included in the
Feasibility Report.
3
SCHEDULE
Should the Council approve this resolution, the proposed project schedule is shown below. Items marked
“CC” will require City Council approval in order to move forward.
CC Receive Feasibility Report and Set Improvement Hearing March 19, 2019
Public Open House March/April, 2019
CC Improvement Hearing, Order Improvement and April 16, 2019
Authorize Preparation of Plans & Specs
CC Approve Plans & Specs and Order Advertisement for Bid Jun 2019
Bid Opening June 2019
CC Set Assessment Hearing July 2019
Public Open House July 2019
CC Award Contract July 2019
Construction Start May 2019
Substantial Completion September 2019
CC Set Costs and Schedule Assessment Hearing September 2019
CC Assessment Hearing, Approve Assessment Roll October 2019
RECOMMENDATION
Staff recommends Council adoption of the attached resolution receiving the feasibility report, calling for
the improvement public hearing and ordering plans and specifications for the 2019 Street Improvement
Project, City Project 2019-01.
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2019 - 28
A RESOLUTION ACCEPTING THE FEASIBILITY REPORT AND
CALLING A PUBLIC HEARING FOR IMPROVEMENT AND
ORDERING THE PREPARATION OF PLANS AND SPECIFICATIONS FOR THE
2019 STREET IMPROVEMENT PROJECT, CITY PROJECT 2019-01
WHEREAS, a report has been prepared by TKDA with reference to proposed Improvement No.
2019-01 for the improvement of:
• Connemara Trail between Diamond Path (CSAH 33) and Shannon Parkway;
• Dodd Boulevard between Shannon Parkway and Chippendale Avenue;
• Chippendale Avenue between 145th Street and 160th Street (CSAH 46);
• 151st Street between Shannon Parkway and Chippendale Avenue;
• Cimarron Avenue between 151st Street and 150th Street (CSAH 42);
• Claret Avenue; and
• Crestone Avenue
WHEREAS, this report was received by the council on March 19, 2019, and
WHEREAS, the report provides information regarding whether the proposed improvement is
necessary, cost-effective, and feasible; whether it should best be made as proposed or in connection
with some other improvement; the estimated cost of the improvement as recommended; and a
description of the methodology used to calculate individual assessments for affected parcels.
NOW THEREFORE IT BE RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ROSEMOUNT, MINNESOTA:
1. The Council will consider the improvement of such street in accordance with the report and
the assessment of abutting property for all or a portion of the cost of the improvement
pursuant to Minnesota Statutes, Chapter 429 at an estimated total cost of the improvement
of $2,412,000.
2. A public hearing shall be held on such proposed improvement on the 16th day of April,
2019, in the Council Chambers of the City Hall at 7:00 p.m. and the clerk shall give mailed
and published notice of such hearing and improvement as required by law.
3. TKDA is hereby designated as the engineer for this improvement. The engineer shall
prepare plans and specifications for the making of such improvement.
ADOPTED this 19th day of March, 2019.
William H. Droste, Mayor
ATTEST:
_______________________________
Erin Fasbender, City Clerk