EXECUTIVE SUMMARY
City Council Meeting: August 5, 2019
AGENDA ITEM: Dunmore Lift Station, City Project 2019-
12: Receive Bids and Award Contract
AGENDA SECTION:
Consent
PREPARED BY: Brian Erickson, PE, Director of Public
Works/City Engineer
Stephanie Smith, PE, Assistant City
Engineer
AGENDA NO. 6.k.
ATTACHMENTS: Resolution, Letter of Recommendation APPROVED BY: LJM
RECOMMENDED ACTION: Motion to Adopt a Resolution Receiving Bids and Awarding
the Contract for Dunmore Lift Station, City Project 2019-12.
BACKGROUND
As part of the City of Rosemount’s surface water management program, stormwater lift stations have
either been constructed or are planned at various locations throughout the city. Staff has worked with
developers to extend infrastructure as appropriate during initial construction to reduce future impacts to
existing streets and homes.
As part of the Dunmore 1st Addition, Copper Creek Development, LLC (Copper Creek) constructed
regional ponding for the city and received a credit toward the stormwater fees as a result of that
construction. The Dunmore 2nd Addition constructed the necessary force main connection to an existing
force main stub installed in 2006 as part of the Glendalough 7th Addition. The construction of this lift
station will provide that planned stormwater management of high water levels in Dunmore area. This lift
station is necessary to comply with concerns that MnDOT has regarding the removal and filling of
stormwater ponds located in the Harmony Parkview 2nd subdivision. WSB, the City’s consultant for this
project, is currently working with the MnDOT permit and drainage offices on permitting for this lift
station.
At their May 7, 2019 meeting, Council approved engineering services for the design, bidding and contract
administration of Dunmore Lift Station, City Project 2019-12. On July 2, 2019, the Council received plans
and specifications and authorized advertisement for bids for Dunmore Lift Station, City Project 2019-12.
Construction is proposed to begin in August 2019.
COSTS & FUNDING
On July 30, 2019, six bids were received for Dunmore Lift Station, City Project 2019-12, and were read
aloud publicly. The low bidder is Minger Construction Company, Inc., who submitted a bid in the amount
of $388,500.00. The engineer’s estimated construction cost at $492,000.00 was approximately 127% of the
low bid. Minger Construction has completed work in the City previously and their work has been
acceptable.
I:\City Clerk\Agenda Items\Approved Items\6.k. Dunmore Lift Station, City Project 2019-12 Receive Bids and Award Contract.docx
Bidder Total Bid Percentage of
Low Bid
Engineer’s Estimate $492,000.00 127%
Minger Construction* $388,500.00 100%
Pember Companies, Inc. $462,040.00 119%
Kuechle Underground,
Inc. $620,950.00 160%
Northdale Construction
Co., Inc. $660,369.00 170%
Meyer Contracting, Inc. $719,168.00 185%
Geislinger & Sons $807,200.00 208%
* - Low Bidder
The funding for this lift station will come from both the Storm Utility (603) and Storm Core (607) Funds.
This project was not included in the 2019 – 2028 Capital Improvement Plan; however, based the available
fund balance and planned future projects, there is sufficient funding to allow this project to proceed.
The amount in the Equipment line shown in the table below is for the purchase of the control panel and
antenna mast required for the lift station. The city will purchase this separately in an effort to save the
overhead cost and shorten the delivery timeframe.
RECOMMENDATION
Staff recommends Council adopt the attached resolution receiving the bids and awarding the contract for
Dunmore Lift Station, City Project 2019-12.
Item
Engineering 69,638.00$
Construction (Low Bid)388,500.00$
Contingency (5%)19,425.00$
Construction Subtotal 407,925.00$
Equipment (Estimate)70,000.00$
TOTAL PROJECT COST 547,563.00$
Storm Utility Fund (603)275,000.00$
Storm Core Fund (607)275,000.00$
TOTAL PROJECT FUNDING 550,000.00$
Amount
Total Project Cost and Funding Breakdown
Total Project Cost
Total Project Funding
2
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2019 – 66
A RESOLUTION RECEIVING BIDS AND AWARDING CONTRACT
FOR DUNMORE LIFT STATION, CITY PROJECT 2019-12.
BE IT RESOLVED, by the City Council of the City of Rosemount, Minnesota, as follows:
1. All bids on construction of Dunmore Lift Station, City Project 2019-12, are hereby received
and tabulated.
2. Based on the Total Bid, the bid of Minger Construction Company, Inc. in the amount of
$388,500.00 for the construction of said improvements is in accordance with the plans and
specifications and advertisement for bids, and is the lowest responsible bid and shall be and
hereby is accepted.
3. The Mayor and Clerk are hereby authorized and directed to enter into a contract with said
bidder for the construction of said improvements for and on behalf of the City of Rosemount.
4. The City Clerk is hereby authorized and directed to return forthwith to all bidders the deposits
made with their bids, except that the deposit of the successful bidder and the next two lowest
bidders shall be retained until a contract has been executed.
ADOPTED this 5th day of August, 2019.
William H. Droste, Mayor
ATTEST:
Erin Fasbender, City Clerk
K:\014142-000\Admin\Construction Admin\Bidding\014142-000 LOR 073119.docx 178 E 9TH STREET | SUITE 200 | SAINT PAUL, MN | 55101 | 651.286.8450 | WSBENG.COM July 31, 2019
Honorable Mayor and City Council
City of Rosemount
2875 145th Street West
Rosemount, MN 55068
Re: Dunmore Stormwater Lift Station
City of Rosemount
City Project No. 2019-12
WSB Project No. R-014142-000
Dear Mayor and Council Members:
Bids were received for the above-referenced project on Tuesday, July 30, 2019, and were
opened and read aloud. Six bids were received. The bids were checked for mathematical
accuracy. Please find enclosed the bid summary indicating the low bid as submitted by Minger
Construction Co., Inc., Jordan, Minnesota in the amount of $388,500.00. The Engineer’s Estimate
was $492,000.00.
We recommend that the City Council consider these bids and award a contract in the amount of
$388,500.00 to Minger Construction Co., Inc. based on the results of the bids received.
Sincerely,
WSB
Greg Johnson, PE
Water/Wastewater Group Manager - Principal
Attachments
cc: Mitch Hatcher, WSB
Ursinio Puga, WSB
kkp