EXECUTIVE SUMMARY
City Council Regular Meeting: September 17, 2019
AGENDA ITEM: Family Resource Center Project -
Change Order #1
AGENDA SECTION:
Consent
PREPARED BY: Dan Schultz, Parks and Recreation
Director
AGENDA NO. 6.h.
ATTACHMENTS: Change Order #1 APPROVED BY: LJM
RECOMMENDED ACTION: Motion to approve Change Order #1 for the Family resource
Center Project.
BACKGROUND
In the summer of 2019, the City Council awarded a bid for the expansion of the Family Resource Center.
The expansion plans will add 3,320 square feet to the facility. During the construction of the project a few
changes have been requested that have resulted in staff requesting the City Council to consider approving
change order #1.
The first alteration to the project is a request by the City’s Planning Department for the addition of shrubs
along the new trash enclosure to better screen it from the street. The second alteration is rerouting of the
exterior lighting circuit. It was discovered during construction that the existing parking lot lighting circuit
was routed underground through the area being excavated for the building addition. The third part of
change order #1 is the addition of electrical floor boxes. This item adds in-floor electrical boxes in the
multi-purpose room as required by the interpretation of the electrical inspector. The total of the three
requests is $10,152.57.
RECOMMENDATION
Staff is recommending the City Council approve Change Order #1 for the Family Resource Center
expansion project.
P:\PROJECTS\2017\17068\5 - CONSTRUCTION ADMIN\CHANGE ORDERS & PAY APPS\CHANGE ORDER #01 RECOMMENDATION TO COUNCIL.DOCX
7300 WEST 147TH STREET SUITE 504 APPLE VALLEY, MN 55124-7580 (952) 431-4433
MEMORANDUM:
PROJECT: Rosemount Family Resource Center
CNH NO: 18071
DATE: August 30, 2019
TO: City of Rosemount – Mayor and City Council
SUBJECT: Change Order #01 Review
The following is a summary of the items being submitted as Change Order #01 for the Rosemount
Family Resource Center project.
Background:
The construction on the Rosemount Family Resource Center project is progressing well and is
currently a little ahead of schedule. The addition is fully framed with and the roof is shingled. The
exterior is moving along with windows installed and siding work currently starting.
During the past few months several items have come up to improve the facility or address items
requested by planning or inspection staff. These items are summarized below.
Description of Changes:
The changes that are incorporated in the attached Change Order #01 are the following:
A. Landscape upgrades: This item added additional shrubs along the new trash enclosure to
better screen it from the street.
B. Reroute exterior lighting circuit: This change addressed the discovery during construction
that the existing parking lot lighting circuit was routed underground through the area being
excavated for the building addition.
C. Additional Floor Boxes: This item adds in-floor electrical boxes in the multi-purpose room
as required by the interpretation of the electrical inspector.
P:\PROJECTS\2017\17068\5 - CONSTRUCTION ADMIN\CHANGE ORDERS & PAY APPS\CHANGE ORDER #01 RECOMMENDATION TO COUNCIL.DOCX
Pricing:
The following are the pricing for each group of Proposal Request items listed above and included in
this Change Order. All prices have been reviewed by CNH Architects and our consultant team and
have been determined to be within appropriate unit costs for the work proposed.
A. Landscape Upgrades Add $1,751.20
B. Exterior Lighting Circuit Replacement Add $3,160.97
C. In-floor Electrical Boxes Add $5,240.40
Total Add $10,152.57
New Contract Total $992,952.57
Original Contingency (10%) $98,280.00
Contingency Balance $88,127.43
Conclusion:
The items in the Change Order represent recommended upgrades to best serve the city and staff
using this facility. As noted above CNH Architects, our team, and staff have reviewed the pricing
shown above and are comfortable as being appropriate for the work involved. CNH Architects
recommends approval of this Change Order as in the best interest of staff operations and long-term
City value.
Respectfully Submitted,
Quinn S. Hutson, AIA, LEED AP
Principal
CNH Architects, Inc.