EXECUTIVE SUMMARY
City Council Regular Meeting: October 15, 2019
AGENDA ITEM: Horseshoe Lake Park Project - Change
Orders #1 and #2
AGENDA SECTION:
Consent
PREPARED BY: Dan Schultz, Parks and Recreation
Director
AGENDA NO. 6.f.
ATTACHMENTS: Change Orders #1 and #2 APPROVED BY: LJM
RECOMMENDED ACTION: Motion to approve Change Orders #1 and #2 for the
Horseshoe Lake Park Project.
BACKGROUND
In the fall of 2018, the City started the construction on the neighborhood park, Horseshoe Lake Park, in
the Bella Vista development. The park adjacent to Horseshoe Lake includes a playground, paved and
gravel trails, wood dock, sun shelter. During the construction process a few changes were made to the
project. The changes requested in change order #1 includes using a different supplier for the wood dock.
Just after the bid was approved Minncor stopped making the dock that was specified and we had to find
another supplier. The first change order also added additional silt fence and bio rolls that were requested
for erosion control. Change order #1 is for $7,400. Change order #2 added some additional concrete to
the site for better access and also added top soil and seed to the boulevard in front of the park. Change
order #2 is for $7,160.50.
RECOMMENDATION
Staff is recommending the City Council approve change order #1 and change order #2 for the Horseshoe
Lake Park Project.