EXECUTIVE SUMMARY
City Council Regular Meeting: November 4, 2019
AGENDA ITEM: Autumn Path Improvement Project, City
Project 2019-07: Receive Feasibility
Report Update and Call Improvement
Hearing
AGENDA SECTION:
Consent
PREPARED BY: Brian Erickson, PE, Director of Public
Works/City Engineer
Stephanie Smith, PE, Assistant City
Engineer
AGENDA NO. 6.g.
ATTACHMENTS: Resolution; Map APPROVED BY: LJM
RECOMMENDED ACTION: Motion to Adopt a Resolution Receiving the Feasibility Report
Update for the Autumn Path Improvement Project, City Project 2019-07 and Call the
Improvement Public Hearing for the Autumn Path Improvement Project, City Project 2019-
07.
BACKGROUND
On November 19, 2013, the City Council received the Feasibility Report for public improvements
related to the Bella Vista development. One of the roads identified in the report was Autumn Path.
Autumn Path’s alignment is proposed to weave between the Bella Vista property and the
neighboring property (PID 34-02200-25-010). As the neighboring property has not dedicated
needed right-of-way, Autumn Path has not yet been constructed. The developer does not have
access to the future Bella Vista 7th Addition until Autumn Path is constructed.
On June 4, 2019, the City Council approved the final plat for Caramore Crossing on the neighboring
property (PID 34-02200-25-010). A condition of approval for this plat is the dedication of a
roadway, drainage and utility easement to allow construction of Autumn Path to the northern
property line. The Caramore Crossing developer, DR Horton, intends to plat and dedicate the
easement in spring of 2020. In order to begin construction of Autumn Path early spring/summer of
2020, the design work would be scheduled for winter 2019.
On October 15, 2019, the City Council approved a contract for engineering services with WSB and
ordered an update of the Feasibility Report for Autumn Path that was included with the Bella Vista
development. Detailed project information is included in the Feasibility Report available on file in
the Engineering Department. The report found this project, as proposed, to be feasible, cost
effective, and necessary.
The Autumn Path Improvement Project, City Project 2019-07, would consist of construction of a
42-foot wide asphalt collector roadway with curb and gutter. Pedestrian facilities will include trail
and sidewalk on each side of the road. Storm pipe will be constructed to ponds within the Bella
2
and sidewalk on each side of the road. Storm pipe will be constructed to ponds within the Bella
Vista development. Watermain will be installed the full length of the road and some sanitary sewer.
The resolution calls the Public Improvement Hearing on December 3rd, 2019, which is a necessary
step under the Minnesota Statutes Chapter 429. A full presentation of the proposed improvements
will be made at the Hearing.
COSTS & FUNDING
The estimated cost for the project is $1,738,000. This amount includes a 10% increase for
contingency and 25% increase for incidentals such as engineering, legal, financing and administrative
costs. The cost by improvement type is shown in the table below:
PROJECT COST ESTIMATE
Surface Improvements $1,267,100
Sanitary Sewer Improvements $24,500
Watermain Improvements $345,100
Storm Sewer Improvements $101,300
TOTAL $1,738,000
The design and construction costs for the Autumn Path Improvement Project, City Project 2019-07,
are budgeted in the proposed 2020-2029 CIP in the amount of $1,510,000 for 2022. The funding
anticipated for the project is shown in the table below. The street improvements will be funded by
developer fees and assessment of abutting property. The City is ordering a special benefit appraisal
of the benefitting property to assist with determination of the assessment amount. The Street
Improvement Project (SIP) fund would cover shortfall from assessments. Utility work would be
funded by the respective utility core funds.
PROJECT FUNDING ESTIMATE
Developer Fees (collected with Bella Vista) $684,200
Special Assessment $684,200
Sanitary Core Fund $24,500
Water Core Fund $345,100
TOTAL $1,738,000
3
SCHEDULE
Should the Council approve this resolution, the proposed project schedule is shown below. Items
marked “CC” will require City Council approval in order to move forward.
CC Receive Feasibility Report and Set Improvement Hearing November 4, 2019
CC Improvement Hearing, Order Improvement and December 3, 2019
Authorize Preparation of Plans & Specs
CC Approve Plans & Specs and Order Advertisement for Bid February 4, 2020
Bid Opening March 3, 2020
CC Award Contract March 17, 2019
CC Set Assessment Hearing April 21, 2020
Public Open House April 2020
CC Assessment Hearing, Approve Assessment Roll May 19, 2020
Construction Start May/June 2020
Substantial Completion September 2020
RECOMMENDATION
Staff recommends Council adoption of the attached resolution receiving the feasibility report and
calling for the improvement public hearing for the Autumn Path Improvement Project, City Project
2019-07.
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2019 - 86
A RESOLUTION ACCEPTING THE FEASIBILITY REPORT AND
CALLING A PUBLIC HEARING FOR IMPROVEMENT AND
ORDERING THE PREPARATION OF PLANS AND SPECIFICATIONS FOR THE
AUTUMN PATH IMPROVEMENT PROJECT, CITY PROJECT 2019-07
WHEREAS, a report has been prepared by WSB with reference to proposed Improvement No.
2019-07 for the improvement of Autumn Path.
WHEREAS, this report was received by the council on November 4, 2019, and
WHEREAS, the report provides information regarding whether the proposed improvement is
necessary, cost-effective, and feasible; whether it should best be made as proposed or in connection
with some other improvement; the estimated cost of the improvement as recommended; and a
description of the methodology used to calculate individual assessments for affected parcels.
NOW THEREFORE IT BE RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ROSEMOUNT, MINNESOTA:
1. The Council will consider the improvement of such street in accordance with the report and
the assessment of abutting property for all or a portion of the cost of the improvement
pursuant to Minnesota Statutes, Chapter 429 at an estimated total cost of the improvement
of $1,738,000.
2. A public hearing shall be held on such proposed improvement on the 3rd day of December,
2019, in the Council Chambers of the City Hall at 7:00 p.m. and the clerk shall give mailed
and published notice of such hearing and improvement as required by law.
3. WSB is hereby designated as the engineer for this improvement. The engineer shall prepare
plans and specifications for the making of such improvement.
ADOPTED this 4th day of November, 2019.
William H. Droste, Mayor
ATTEST:
_______________________________
Erin Fasbender, City Clerk
Autumn PathAutumn PathPhase 1
Phase 2
Phase 3
Phase 4N
Phase 4S
Phase 2Bacardi AveBonaire Path W Document Path: K:\01928-060\GIS\Maps\Figure1_ProjectLayout.mxd Date Saved: 11/13/2013 1:39:32 PMProje ct L oca tion
1 inch = 400 feet
Bella VistaFigure 1 - Project Layout/PhasesCity of Rosemount MN