EXECUTIVE SUMMARY
Utility Commission Meeting: November 18, 2019
AGENDA SECTION:
AGENDA ITEM: City Project Update Executive Director’s
Report
PREPARED BY: Brian Erickson, P.E. Director of Public Works
AGENDA NO. 8.c.
/ City Engineer
ATTACHMENTS: None APPROVED BY: BLE
RECOMMENDED ACTION: None, informational only
BACKGROUND
As the construction season is slowing down significantly the list of city and developer projects
is provided as an update to the Utility Commission. The following list is the current and
planned City of Rosemount projects.
132nd Street Improvements – Scope includes construction of utilities and paving
between MN Hwy 3 and Dodd Boulevard. Project is completed for the season with
utilities and base course in place. Wear course will be installed in 2020.
145th Street Sidewalk Improvements – Scope includes constructing sidewalk and
th
pedestrian ramps along the north side of 145 Street to the east of Brazil Ave. Project
is completed for the season. There is a portion of sidewalk across the Union Pacific
Railroad that has not been done as the crossing material was removed for rail
maintenance.
2019 Street Improvement Project – Scope includes mill and overlay of Connemara
Trail between Diamond Path and Shannon Parkway and restriping to a three-lane
section with some minor storm sewer improvements. Project is completed for the
season.
Adalyn Avenue – Scope includes construction of utilities and paving between Addison
Avenue and Connemara Trail. Project is completed for the season with utilities and
base course in place. Wear course will be installed in 2020.
st
Addison Ave – Scope includes construction of utilities and paving between 141 Street
East and a temporary cul-de-sac to the east. Project was completed except for wear
course in 2018 and because of additional 2019 construction in the area, the removal of
the cul-de-sac and road extension to the east this summer. Final wear course will be
done in 2020.
Autumn Path – Scope includes construction of utilities and paving from Bonaire Path
north approximately 2,500 feet. This project is planned for 2020 construction and is
currently in design.
Biscayne Ave – Scope includes construction of utilities and paving between Boulder
th
Trail 160 Street (CSAH 46). This project is planned for 2020 construction and is
currently in design.
Bonaire Path – Scope includes construction of utilities and paving between Akron
Avenue and Anderson Drive. Additionally, the installation of crossing arms at the
Union Pacific Railroad intersection are in the scope of the project and planned for
C:\\Users\\jab\\AppData\\Local\\Temp\\8.c. Project Update_576945\\8.c. Project Update.docx
2020. Ultimately, the city will request that this intersection become a quiet zone (i.e.
no train horns). Project is completed for the season with utilities and base course in
place. Wear course will be installed in 2020.
Chippendale Water Tower Rehab – Scope includes coating rehabilitation and minor
tank repairs along with the painting of the current Rosemount logo. Project is
completed except for restoration around the tower which will be performed in 2020.
Connemara Trail Extension – Scope includes construction of utilities and paving from
Akron Avenue east approximately 1,300 feet. This project is planned for 2020
construction and is currently in design.
Deepwoods Court – Scope includes pavement reclamation and minor curb repair from
McAndrews Road south approximately 1,900 feet. This project is planned for 2020
construction and is currently in design.
Dunmore Storm Lift Station – Scope includes the construction of a stormwater lift
station in the Dunmore subdivision and connection to existing force main.
Construction is ongoing and is planned for completion this year. Restoration will be
completed in 2020.
TH 3 Drainage Improvements – Scope includes improving the stormwater crossing at
MN Hwy 3 between Dunmore and Harmony subdivisions. This is a joint project
between the City of Rosemount and MnDOT. Design in completed and work is
planned for 2020.
Well 16 Pump House – Scope included the construction of the pump house and well
head. Construction is complete and well is in service, final acceptance of work will
happen this year.
The following list is the current and planned developer projects.
Bella Vista 6 – Scope includes construction of utilities and paving from Aulden Avenue
to the cul-de-sac approximately 850’ north east as well as 19 single family residential
(SFR) lots of a planned total 158. In addition, there is a temporary sanitary sewer lift
station that will be installed until trunk sewer is extended at a future date. Utilities and
base course are in place and the lift station is under construction now. Wear course is
planned for 2020.
Bella Vista 7 – Scope will include construction of utilities and paving from a temporary
connection to the Autumn Path extension (see above) west approximately 1500 feet
as well as 26 SFR lots of a planned total 158. Actual construction cannot occur until
Autumn Path is construction to allow access as this portion of Bella Vista is currently
‘land locked’. Grading is nearly completed.
Biscayne Business Park – Scope includes construction of utilities and paving from
Biscayne Avenue to the cul-de-sac approximately 750’ west as well as 8 commercial
lots and a temporary connection to the Metropolitan Council Environmental Services
(MCES) interceptor line. This connection will be changed once Biscayne Avenue is
reconstructed. Final wear course will be done in 2020.
Caramore Crossing – Scope includes construction of utilities and paving from Akron
Avenue and from Bonaire Path as well as 82 SFR lots of a planned total 177. This
project is planned for 2020 construction and is currently in design.
nd
Dunmore – Scope includes construction of utilities and paving from 132 Street as
well as 30 SFR lots of a planned total 87. This project is nearly complete, wear course
has been done.
nd
Dunmore 2 – Scope includes construction of utilities and paving from 132 Street as
well as 25 SFR lots of a planned total 87. Project is completed for the season with
utilities and base course in place. Wear course will be installed in 2020.
2
Greystone 7 – Scope includes construction of utilities and paving as well as 46 SFR
lots of a planned total 287. Project is completed for the season with utilities and base
course in place. Wear course will be installed in 2020.
Greystone 8 – Scope includes construction of utilities and paving as well as 56 SFR
lots of a planned total 287. Project is completed for the season with utilities and base
course in place. Wear course will be installed in 2020.
Harmony Parkview – Scope includes construction of utilities and paving as well as 22
townhomes. Utilities are city owned and the streets are private.
nd
Harmony Parkview 2 – Scope includes construction of utilities and paving as well as
26 townhomes. Utilities will be city owned and the streets are private. This project will
also fill temporary stormwater ponding on the east side of MN Hwy 3. This project is
planned for 2020 construction.
Harmony Villas – Scope includes construction of utilities and paving as well as 42
townhomes. Utilities are city owned and the streets are private. Utility construction is
complete.
Harmony Villas 2 – Scope includes construction of utilities and paving as well as 26
townhomes. Utilities are city owned and the streets are private. Utility construction is
complete.
Meadow Ridge – Scope includes construction of utilities and paving as well as 34 SFR
lots of a planned total 154. Project is completed and final acceptance of the project is
process.
nd
Meadow Ridge 2 – Scope includes construction of utilities and paving as well as 29
SFR lots of a planned total 154. Project is completed for the season with utilities and
base course in place. Wear course will be installed in 2020.
rd
Meadow Ridge 3 – Scope includes construction of utilities, paving and a temporary
sanitary sewer lift station as well as 28 SFR lots of a planned total 154. This project is
planned for 2020 construction.
Minea/ISD 196 Sanitary Extn – Scope includes construction of sanitary sewer from
Akron Avenue to the west. No additional construction is planned this was completed
to allow for future development to the west of Akron. Project is completed and final
acceptance of the project is process.
Prestwick 17 – Scope includes construction of utilities and paving, including the
completion of Addison Avenue to a temporary dead end to the east as well as 26
townhomes. Utilities will be city owned and the streets are private. Project is
completed for the season with utilities and base course in place. Wear course will be
installed in 2020.
Prestwick 18 – Scope includes construction of utilities and paving as well as 40
townhomes. Utilities will be city owned and the streets are private. Utilities have been
installed. Wear course will be installed in 2020.
Prestwick 19 – Scope includes construction of utilities and paving as well as 35 SFR
lots. Project is completed for the season with utilities and base course in place. Wear
course will be installed in 2020.
Prestwick 20 – Scope includes construction of utilities and paving as well as SFR lots.
This project is planned for 2020 construction.
Prestwick 21 – Scope includes construction of utilities and paving as well as 24
townhomes. Utilities will be city owned and the streets are private. This project is
planned for 2020 construction.
Prestwick 22 – Scope includes construction of utilities and paving as well as 64
townhomes. Utilities will be city owned and the streets are private. This project is
planned for 2020 construction.
3
The following is the list of Dakota County/City of Rosemount projects.
CR 73 (Akron Ave) – Scope includes the reconstruction of Akron Avenue from Bonaire
Path to the Rosemount city limit. It also includes the construction of a trail under pass
th
near Flint Hills Soccer Complex. Finally, it includes pavement rehabilitation for 124
st
Court and 121 Street. This project is planned for 2020 construction.
Roundabout Connemara Trail/Diamond Path – Scope preliminary engineering for the
construction of a roundabout at this intersection. This project is planned for
construction in 2022.
4