HomeMy WebLinkAbout8.a. Project Update EXECUTIVE SUMMARY Utility Commission Meeting: January 13, 2020 AGENDA SECTION: AGENDA ITEM: City Project Update Executive Director’s Report PREPARED BY: Brian Erickson, P.E. Director of Public Works AGENDA NO. 8.a. / City Engineer ATTACHMENTS: None APPROVED BY: BLE RECOMMENDED ACTION: None, informational only BACKGROUND With winter now upon the city, the staff’s focus is on preparing for the 2020 constuction season. The following list is the current and planned City of Rosemount projects. In an effort to improve readability, changes since the last report are shown as strike out for deletions and underlined for additions as well as a bar along the left margin to indicate the changes.  132nd Street Improvements – Scope includes construction of utilities and paving between MN Hwy 3 and Dodd Boulevard. Project is completed for the season with utilities and base course in place. Wear course will be installed in 2020.  145th Street Sidewalk Improvements – Scope includes constructing sidewalk and th pedestrian ramps along the north side of 145 Street to the east of Brazil Ave. Project is completed for the season. There is a portion of sidewalk across the Union Pacific Railroad that has not been done as the crossing material was removed for rail maintenance.  2019 Street Improvement Project – Scope includes mill and overlay of Connemara Trail between Diamond Path and Shannon Parkway and restriping to a three-lane section with some minor storm sewer improvements. Project is completed for the season. Phase 2 of this project has the bid opening planned for February 5, 2020. The scope includes mill and overlay or reclamation of:  Chippendale Avenue from 145th Street W to 160th Street W  Dodd Boulevard from Shannon Parkway to Chippendale Avenue  151st Street W from Shannon Parkway to Chippendale Avenue  Crestone Ave, Claret Ave and Cimarron Ave from CSAH 42 to 151st Street W  Adalyn Avenue – Scope includes construction of utilities and paving between Addison Avenue and Connemara Trail. Project is completed for the season with utilities and base course in place. Wear course will be installed in 2020. st  Addison Ave – Scope includes construction of utilities and paving between 141 Street East and a temporary cul-de-sac to the east. Project was completed except for wear course in 2018 and because of additional 2019 construction in the area, the removal of the cul-de-sac and road extension to the east this summer. Final wear course will be done in 2020. C:\\Users\\jab\\AppData\\Local\\Temp\\8.a. Project Update_583684\\8.a. Project Update.docxG:\\MEETINGS\\UTILITY COMMISSION\\UC Items and Packets\\2020\\20200113\\8.a. Project Update.docx  Autumn Path – Scope includes construction of utilities and paving from Bonaire Path north approximately 2,500 feet. This project is planned for 2020 construction and is currently in design. Bid opening is planned for March 3, 2020.  Biscayne Ave – Scope includes construction of utilities and paving between Boulder th Trail 160 Street (CSAH 46). This project is planned for 2020 construction and is currently in design. Bid opening is planned for March 10, 2020.  Bonaire Path – Scope includes construction of utilities and paving between Akron Avenue and Anderson Drive. Additionally, the installation of crossing arms at the Union Pacific Railroad intersection are in the scope of the project and planned for 2020. Ultimately, the city will request that this intersection become a quiet zone (i.e. no train horns). Project is completed for the season with utilities and base course in place. Wear course will be installed in 2020.  Chippendale Water Tower Rehab – Scope includes coating rehabilitation and minor tank repairs along with the painting of the current Rosemount logo. Project is completed except for restoration around the tower which will be performed in 2020. This project will be removed from future reports.  Connemara Trail Extension – Scope includes construction of utilities and paving from Akron Avenue east approximately 1,300 feet. This project is planned for 2020 construction and is currently in design. Bid opening is planned for February 28, 2020.  Deepwoods Court – Scope includes pavement reclamation and minor curb repair from McAndrews Road south approximately 1,900 feet. This project is planned for 2020 construction and is currently in design. Bid opening is planned for March 12, 2020.  Dunmore Storm Lift Station – Scope includes the construction of a stormwater lift station in the Dunmore subdivision and connection to existing force main. Construction is ongoing and is plannednearly completed for completion thisthe year. Restoration will be completed in 2020.  TH 3 Drainage Improvements – Scope includes improving the stormwater crossing at MN Hwy 3 between Dunmore and Harmony subdivisions. This is a joint project between the City of Rosemount and MnDOT. Design in completed and work is planned for 2020. Bid opening is planned for February 6, 2020.  Well 16 Pump House – Scope included the construction of the pump house and well head. Construction is complete and well is in service, final acceptance of work will happen this yearis in process. This project will be removed from future reports. The following list is the current and planned developer projects.  Bella Vista 6 – Scope includes construction of utilities and paving from Aulden Avenue to the cul-de-sac approximately 850’ north east as well as 19 single family residential (SFR) lots of a planned total 158. In addition, there is a temporary sanitary sewer lift station that will be installed until trunk sewer is extended at a future date. Utilities and base course are in place and the lift station is under construction now. Wear course is planned for 2020.  Bella Vista 7 – Scope will include construction of utilities and paving from a temporary connection to the Autumn Path extension (see above) west approximately 1500 feet as well as 26 SFR lots of a planned total 158. Actual construction cannot occur until Autumn Path is construction to allow access as this portion of Bella Vista is currently ‘land locked’. Grading is nearly completed.  Biscayne Business Park – Scope includes construction of utilities and paving from Biscayne Avenue to the cul-de-sac approximately 750’ west as well as 8 commercial lots and a temporary connection to the Metropolitan Council Environmental Services 2 (MCES) interceptor line. This connection will be changed once Biscayne Avenue is reconstructed. Final wear coursePaving will be done in 2020.  Caramore Crossing – Scope includes construction of utilities and paving from Akron Avenue and from Bonaire Path as well as 82 SFR lots of a planned total 177. This project is planned for 2020 construction and is currently in design. nd  Dunmore – Scope includes construction of utilities and paving from 132 Street as well as 30 SFR lots of a planned total 87. This project is nearly complete, wear course has been done. nd  Dunmore 2 – Scope includes construction of utilities and paving from 132 Street as well as 25 SFR lots of a planned total 87. Project is completed for the season with utilities and base course in place. Wear course will be installed in 2020.  Greystone 7 – Scope includes construction of utilities and paving as well as 46 SFR lots of a planned total 287. Project is completed for the season with utilities and base course in place. Wear course will be installed in 2020.  Greystone 8 – Scope includes construction of utilities and paving as well as 56 SFR lots of a planned total 287. Project is completed for the season with utilities and base course in place. Wear course will be installed in 2020.  Harmony Parkview – Scope includes construction of utilities and paving as well as 22 townhomes. Utilities are city owned and the streets are private. nd  Harmony Parkview 2 – Scope includes construction of utilities and paving as well as 26 townhomes. Utilities will be city owned and the streets are private. This project will also fill temporary stormwater ponding on the east side of MN Hwy 3. This project is planned for 2020 construction.  Harmony Villas – Scope includes construction of utilities and paving as well as 42 townhomes. Utilities are city owned and the streets are private. Utility construction is complete.  Harmony Villas 2 – Scope includes construction of utilities and paving as well as 26 townhomes. Utilities are city owned and the streets are private. Utility construction is complete.  Meadow Ridge – Scope includes construction of utilities and paving as well as 34 SFR lots of a planned total 154. Project is completed and final acceptance of the project is process. This project will be removed from future reports. nd  Meadow Ridge 2 – Scope includes construction of utilities and paving as well as 29 SFR lots of a planned total 154. Project is completed for the season with utilities and base course in place. Wear course will be installed in 2020. rd  Meadow Ridge 3 – Scope includes construction of utilities, paving and a temporary sanitary sewer lift station as well as 28 SFR lots of a planned total 154. This project is planned for 2020 construction.  Minea/ISD 196 Sanitary Extn – Scope includes construction of sanitary sewer from Akron Avenue to the west. No additional construction is planned this was completed to allow for future development to the west of Akron. Project is completed and final acceptance of the project is process. This project will be removed from future reports.  Morrison (Downtown redevelopment) – Scope includes redevelopment of the area west of TH 3 in proximity to Shenanigans. Mixed commercial and apartments are planned for this area. Project is currently in the planning stage.  Prestwick 17 – Scope includes construction of utilities and paving, including the completion of Addison Avenue to a temporary dead end to the east as well as 26 townhomes. Utilities will be city owned and the streets are private. Project is completed for the season with utilities and base course in place. Wear course will be installed in 2020. 3  Prestwick 18 – Scope includes construction of utilities and paving as well as 40 townhomes. Utilities will be city owned and the streets are private. Utilities have been installed. Wear course will be installed in 2020.  Prestwick 19 – Scope includes construction of utilities and paving as well as 35 SFR lots. Project is completed for the season with utilities and base course in place. Wear course will be installed in 2020.  Prestwick 20 – Scope includes construction of utilities and paving as well as SFR lots. This project is planned for 2020 construction.  Prestwick 21 – Scope includes construction of utilities and paving as well as 24 townhomes. Utilities will be city owned and the streets are private. This project is planned for 2020 construction.  Prestwick 22 – Scope includes construction of utilities and paving as well as 64 townhomes. Utilities will be city owned and the streets are private. This project is planned for 2020 construction.  Wexford Place – Scope includes redevelopment of a single family resident at the intersection of Chippendale Ave and CSAH 46 with an apartment building. Project is currently under construction with a planned completion in 2020. The following is the list of Dakota County/City of Rosemount projects.  CR 73 (Akron Ave) – Scope includes the reconstruction of Akron Avenue from Bonaire Path to the Rosemount city limit. It also includes the construction of a trail under pass th near Flint Hills Soccer Complex. Finally, it includes pavement rehabilitation for 124 st Court and 121 Street. This project is planned for 2020 construction. Bid opening is planned for February 5, 2020.  Roundabout Connemara Trail/Diamond Path – Scope preliminary engineering for the construction of a roundabout at this intersection. This project is planned for construction in 2022. There will be an open house for residents near the project on February 6, 2020 at the Rosemount Community Center.  CSAH 42/CR 73 (Akron Ave) Signal – Scope calls for installation of a traffic signal at the intersection of CSAH 42 and CR 73 (Akron Ave) to address the increase in traffic at this intersection. This project is planned for construction in 2021.  CSAH 42 Visioning Study – This is a study that will look at nearly the entire length of CSAS 42 starting at the western county line (Burnsville) and ending at MN Trunk Highway 52. Future open houses and public engagement opportunities will be promulgated as they are established. 4