EXECUTIVE SUMMARY
Utility Commission Meeting: March 16, 2020
AGENDA SECTION:
AGENDA ITEM: City Project Update Executive Director’s
Report
PREPARED BY: Brian Erickson, P.E. Director of Public Works
AGENDA NO. 8.a.
/ City Engineer
ATTACHMENTS: None APPROVED BY: BLE
RECOMMENDED ACTION: None, informational only
BACKGROUND
The beginning of the 2020 construction season is nearly here. The following list is the current
and planned City of Rosemount projects. There are additional developments that are in early
stages of the process and those will be added as a appropriate. Changes since the last
report are shown as strike out for deletions and underlined for additions as well as a bar
along the left margin to indicate the changes.
132nd Street Improvements – Scope includes construction of utilities and paving
between MN Hwy 3 and Dodd Boulevard. Project is completed for the season with
utilities and base course in place. Wear course will be installed in 2020 with exact
dates to be established.
145th Street Sidewalk Improvements – Scope includes constructing sidewalk and
th
pedestrian ramps along the north side of 145 Street to the east of Brazil Ave. Project
is completed for the season. There is a portion of sidewalk across the Union Pacific
Railroad that has not been done as the crossing material was removed for rail
maintenance. Union Pacific has this work on their plan; however, actual dates are not
yet available.
2019 Street Improvement Project – Scope includes mill and overlay of Connemara
Trail between Diamond Path and Shannon Parkway and restriping to a three-lane
section with some minor storm sewer improvements. Project is completed for the
season. Bid opening for the second phase of this project had 5 contractors bidding
with an apparent low bid from McNamara Contracting. Contract award will be at an
upcoming City Council meeting. The scope includes mill and overlay or reclamation
of:
Chippendale Avenue from 145th Street W to 160th Street W
Dodd Boulevard from Shannon Parkway to Chippendale Avenue
151st Street W from Shannon Parkway to Chippendale Avenue
Crestone Ave, Claret Ave and Cimarron Ave from CSAH 42 to 151st Street W
C:\\Users\\jab\\AppData\\Local\\Temp\\8.a. Project Update_591095\\8.a. Project Update.docxG:\\MEETINGS\\UTILITY COMMISSION\\UC Items and
Packets\\2020\\20200316\\8.a. Project Update.docx
Adalyn Avenue – Scope includes construction of utilities and paving between Addison
Avenue and Connemara Trail. Project is completed for the season with utilities and
base course in place. Wear course will be installed in 2020 with exact dates to be
established.
st
Addison Ave – Scope includes construction of utilities and paving between 141
Street East and a temporary cul-de-sac to the east. Project was completed except for
wear course in 2018 and because of additional 2019 construction in the area, the
removal of the cul-de-sac and road extension to the east this summer. Final wear
course will be done in 2020 with exact dates to be established.
Autumn Path – Scope includes construction of utilities and paving from Bonaire Path
north approximately 2,500 feet. This project is planned for 2020 construction and is
currently in design. Bid opening is planned for March 326, 2020.
Biscayne Ave – Scope includes construction of utilities and paving between Boulder
th
Trail 160 Street (CSAH 46). This project is planned for 2020 construction and is
currently in design. Bid opening is planned for March 10, 2020. Bids were opened on
March 10, and there were a total of 9 bidders with an apparent low bid from Northwest
Asphalt. Contract award will be at an upcoming City Council meeting. Right of way
acquisition is currently underwaynearly completed.
Bonaire Path – Scope includes construction of utilities and paving between Akron
Avenue and Anderson Drive. Additionally, the installation of crossing arms at the
Union Pacific Railroad intersection are in the scope of the project and planned for
2020. Ultimately, the city will request that this intersection become a quiet zone (i.e.
no train horns). Project is completed for the season with utilities and base course in
place. Wear course will be installed in 2020 with exact dates to be established. Final
design for rail improvements was approved by City Council at the February 4 meeting.
This work is anticipated to be complete this summer. Staff has been in contact with
the Federal Railroad Administration regarding application for a quiet zone (QZ).
Because of the design, the QZ application is expected to be approved.
Connemara Trail Extension – Scope includes construction of utilities and paving
from Akron Avenue east approximately 1,300 feet. This project is planned for 2020
construction and is currently in design. Bids were opened on February 28, and there
were a total of 9 bidders with an apparent low bid from A-1 Excavating. Contract
award will be at the March 17City Council meeting. Bid opening is planned for
February 28, 2020.
Deepwoods Court – Scope includes pavement reclamation and minor curb repair
from McAndrews Road south approximately 1,900 feet. This project is planned for
2020 construction and is currently in design. Bid opening is planned for March 1224,
2020. A meeting with residents is scheduled after the bid opening to discuss the
construction of ‘ribbon’ curb along the corridor.
Dunmore Storm Lift Station – Scope includes the construction of a stormwater lift
station in the Dunmore subdivision and connection to existing force main.
Construction is nearly completed. Initial start up and control programming has been
2
performed. Generator connection tests will be performed in the spring. Restoration
will be completed in 2020.
Shannon Pond Outlet Feasibility Study – Scope includes reviewing potential routes
for stormwater outlet at Shannon Pond. Because of the land locked location outlet will
be a significant undertaking. Initially study work is anticipated in February 2020.
Information from this study will be used to establish future improvements necessary to
reduce the potential for structure flooding.
TH 3 Drainage Improvements – Scope includes improving the stormwater crossing at
MN Hwy 3 between Dunmore and Harmony subdivisions. This is a joint project
between the City of Rosemount and MnDOT. Design in completed and work is
planned for 2020. Bids were opened on February 7, and there were a total of 6
bidders with a low bid from Alcon Excavating. Contract award was at the March 4City
Council meeting. Completion of this project is planned for June 30, 2020.Bid opening
is planned for February 6, 2020.
The following list is the current and planned developer projects.
Bella Vista 6 – Scope includes construction of utilities and paving from Aulden
Avenue to the cul-de-sac approximately 850’ north east as well as 19 single family
residential (SFR) lots of a planned total 158. In addition, there is a temporary sanitary
sewer lift station that will be installed until trunk sewer is extended at a future date.
Utilities and base course are in place and the lift station is under construction now.
Wear course is planned for 2020 with exact dates to be established.
Bella Vista 7 – Scope will include construction of utilities and paving from a temporary
connection to the Autumn Path extension (see above) west approximately 1500 feet
as well as 26 SFR lots of a planned total 158. This is the final phase of this
development. Actual construction cannot occur until Autumn Path is construction to
allow access as this portion of Bella Vista is currently ‘land locked’. Grading is
completed.
Biscayne Business Park – Scope includes construction of utilities and paving from
Biscayne Avenue to the cul-de-sac approximately 750’ west as well as 8 commercial
lots and a temporary connection to the Metropolitan Council Environmental Services
(MCES) interceptor line. This connection will be changed once Biscayne Avenue is
reconstructed. Paving will be done in 2020.
Caramore Crossing – Scope includes construction of utilities and paving from Akron
Avenue and from Bonaire Path as well as 82 SFR lots of a planned total 177. This
project is planned for 2020 construction and is currently in design.
nd
Dunmore – Scope includes construction of utilities and paving from 132 Street as
well as 30 SFR lots of a planned total 87. This project is nearly complete, wear course
has been done.
Dunmore 2 – Scope includes construction of utilities and paving from Caffery Court as
well as 25 SFR lots of a planned total 87. Project is completed for the season with
3
utilities and base course in place. Wear course will be installed in 2020 with exact
dates to be established. Contractor will be required to make repairs to the stormwater
ponds due to poor dewatering practices.
Greystone 7 – Scope includes construction of utilities and paving as well as 46 SFR
lots of a planned total 287. Project is completed for the season with utilities and base
course in place. Wear course will be installed in 2020 with exact dates to be
established.
Greystone 8 – Scope includes construction of utilities and paving as well as 56 SFR
lots of a planned total 287. This is the final phase of this development. Project is
completed for the season with utilities and base course in place. Wear course will be
installed in 2020 with exact dates to be established.
Harmony Parkview – Scope includes construction of utilities and paving as well as 22
townhomes. Utilities are city owned and the streets are private.
nd
Harmony Parkview 2 – Scope includes construction of utilities and paving as well
as 26 townhomes. Utilities will be city owned and the streets are private. This project
will also fill temporary stormwater ponding on the east side of MN Hwy 3. This project
is planned for 2020 construction.
Harmony Villas – Scope includes construction of utilities and paving as well as 42
townhomes. Utilities are city owned and the streets are private. Utility construction is
complete.
Harmony Villas 2 – Scope includes construction of utilities and paving as well as 26
townhomes. Utilities are city owned and the streets are private. Utility construction is
complete.
nd
Meadow Ridge 2 – Scope includes construction of utilities and paving as well as 29
SFR lots of a planned total 154. Project is completed for the season with utilities and
base course in place. Wear course will be installed in 2020 with exact dates to be
established.
rd
Meadow Ridge 3 – Scope includes construction of utilities, paving and a temporary
sanitary sewer lift station as well as 28 SFR lots of a planned total 154. This project is
planned for 2020 construction.
Morrison (Downtown redevelopment) – Scope includes redevelopment of the area
west of TH 3 in proximity to Shenanigans. Mixed commercial and apartments are
planned for this area. Project was approved at the February 4 City Council meeting.
Design is currently in progress. Work is expected to begin this year.
Prestwick 17 – Scope includes construction of utilities and paving, including the
completion of Addison Avenue to a temporary dead end to the east as well as 26
townhomes. Utilities will be city owned and the streets are private. Project is
completed for the season with utilities and base course in place. Wear course will be
installed in 2020 with exact dates to be established.
4
Prestwick 18 – Scope includes construction of utilities and paving as well as 40
townhomes. Utilities will be city owned and the streets are private. Utilities have been
installed. Wear course will be installed in 2020 with exact dates to be established.
Prestwick 19 – Scope includes construction of utilities and paving as well as 35 SFR
lots. Project is completed for the season with utilities and base course in place. Wear
course will be installed in 2020 with exact dates to be established.
Prestwick 20 – Scope includes construction of utilities and paving as well as 27 SFR
lots. This is the final phase of this development on the west side of Akron Avenue.
This project is planned for 2020 construction.
Prestwick 21 – Scope includes construction of utilities and paving as well as 24
townhomes. Utilities will be city owned and the streets are private. This project is
planned for 2020 construction.
Prestwick 22 – Scope includes construction of utilities and paving as well as 64
townhomes. Utilities will be city owned and the streets are private. This project is
planned for 2020 construction.
Rosemount Woods Expansion – Scope includes construction of 39 additional
manufactured home sites as well as construction of private utility extensions for those
sites. Project was approved at the February 18 City Council meeting.
Wexford Place – Scope includes redevelopment of a multifamily residence at the
intersection of Chippendale Ave and CSAH 46 with an apartment building. Project is
currently under construction with a planned completion in 2020.
The following is the list of Dakota County/City of Rosemount and MnDOT projects.
CR 73 (Akron Ave) – Scope includes the reconstruction of Akron Avenue from
Bonaire Path to the Rosemount city limit. It also includes the construction of a trail
under pass near Flint Hills Soccer Complex. Finally, it includes pavement
thst
rehabilitation for 124 Court and 121 Street. This project is planned for 2020
construction. Bid opening had 8 contractors bidding with an apparent low bid from
Northland Grading and Excavating. Contract award was at the February 25 will be at
an upcoming County Board meeting.
Roundabout Connemara Trail/Diamond Path – Scope preliminary engineering for
the construction of a roundabout at this intersection. This project is planned for
construction in 2022. Preliminary design work has continued and a future open house
will be held in early May 2020.There was be an open house for residents near the
project on February 6, 2020 at the Rosemount Community Center.
CSAH 42/CR 73 (Akron Ave) Signal – Scope calls for installation of a traffic signal at
the intersection of CSAH 42 and CR 73 (Akron Ave) to address the increase in traffic
at this intersection. This project is planned for construction in 2021.
5
CSAH 42 Visioning Study – This is a study that will look at nearly the entire length of
CSAS 42 starting at the western county line (Burnsville) and ending at MN Trunk
Highway 52. Future open houses and public engagement opportunities will be
promulgated as they are established.
TH 55 Safety Improvements – Scope includes improvements along Minnesota Trunk
Highway 55 (TH 55) by adding a left turn lane to Doyle Path. The Toward Zero Deaths
(TZD) program is leading a working group for this project.