HomeMy WebLinkAbout6.g. Professional Services Contract for Landscape Architectural Engineering Services – UMore Ballfield Complex Phase 2
EXECUTIVE SUMMARY
City Council Regular Meeting: May 19, 2020
AGENDA ITEM: Professional Services Contract for
Landscape Architectural/Engineering
Services – UMore Ballfield Complex
Phase 2
AGENDA SECTION:
Consent
PREPARED BY: Dan Schultz, Parks and Recreation
Director AGENDA NO. 6.g.
ATTACHMENTS: Site Plan APPROVED BY: LJM
RECOMMENDED ACTION: Motion to recommend the City Council approve entering into a
professional services agreement with WSB to provide the services to create the necessary
plans and specifications for the future development of the second phase of the UMore
Ballfield Complex.
BACKGROUND
The City of Rosemount recently invited the three consulting firms from the City’s consulting pool for
Landscape/Engineering services to provide the City with a quote for creating the necessary plans and
specifications for building the second phase of improvements at the UMore Ball Field Complex. The
second phase of the project would include two youth softball/baseball fields, parking lot, landscaping,
scoreboards, and field lighting for all four fields (two new and two existing). The anticipated construction
cost of the second phase improvements is estimated at $1,750,000.
The submittals that staff received are listed below.
Architect Quote
WSB $63,917
ISG $64,200
SRF $71,763
The City of Rosemount built phase one of the UMore Ballfields in 2012. The first phase included an
irrigation well, two fields, parking lot and landscaping.
RECOMMENDATION
Staff recommends the City Council approve entering into a professional services agreement with WSB to
provide the services to create the necessary plans and specifications for the future development of the
second phase of the UMore Ballfield Complex.
2
Concept Plan