HomeMy WebLinkAbout8.a. City Project Update
EXECUTIVE SUMMARY
Utility Commission Meeting: August 24, 2020
AGENDA SECTION:
AGENDA ITEM: City Project Update Executive Director’s
Report
PREPARED BY: Brian Erickson, P.E. Director of Public Works
AGENDA NO. 8.a.
/ City Engineer
ATTACHMENTS: None APPROVED BY: BLE
RECOMMENDED ACTION: None, informational only
BACKGROUND
The 2020 construction season well underway and there has been a significant amount of
construction completed to date. The following list is the current and planned City of
Rosemount projects. There are additional developments that are in early stages of the
process and those will be added as appropriate. Changes since the last report are shown as
strike out for deletions and underlined for additions as well as a bar along the left margin to
indicate the changes.
132nd Street Improvements – Scope includes construction of utilities and paving
between MN Hwy 3 and Dodd Boulevard. Wear course will be installed in 2020 with
exact dates to be established. Addition of a small retaining wall near an existing
power pole is complete.will be added to reduce the change for erosion at the pole.
145th Street Sidewalk Improvements – Scope includes constructing sidewalk and
th
pedestrian ramps along the north side of 145 Street to the east of Brazil Ave. There
is a portion of sidewalk across the Union Pacific Railroad that has not been done as
the crossing material was removed for rail maintenance. Union Pacific has finally
completed this work. this work on their plan; however, actual dates are not yet
available. Staff has continued to communicate with Union Pacific; however, there is
still no date for reinstallation of the crossing material.Staff is working with the
contractor for a completion date which is anticipated to be this summer.
2019 Street Improvement Project – Scope includes mill and overlay of Connemara
Trail between Diamond Path and Shannon Parkway and restriping to a three-lane
section with some minor storm sewer improvements. Work started on May 14, 2020.
Work is nearly complete with boulevard restoration as the primary remaining
item.progressing with concrete curb and ADA improvements. The scope includes mill
and overlay or reclamation of:
Chippendale Avenue from 145th Street W to 160th Street W
Dodd Boulevard from Shannon Parkway to Chippendale Avenue
151st Street W from Shannon Parkway to Chippendale Avenue
Crestone Ave, Claret Ave and Cimarron Ave from CSAH 42 to 151st Street W
C:\\Users\\jab\\AppData\\Local\\Temp\\8.a. City Project Update_610756\\8.a. City Project Update.docxG:\\MEETINGS\\UTILITY COMMISSION\\UC Items
and Packets\\2020\\20200824\\8.a. Project Update - Copy.docx
Adalyn Avenue – Scope includes construction of utilities and paving between Addison
Avenue and Connemara Trail. Wear course will be installed in 2020 with exact dates
to be established.
st
Addison Ave – Scope includes construction of utilities and paving between 141
Street East and a temporary cul-de-sac to the east. Project was completed except for
wear course in 2018 and because of additional 2019 construction in the area, the
removal of the cul-de-sac and road extension to the east this summer. Final wear
course will be done in 2020 with exact dates to be established.
Autumn Path – Scope includes construction of utilities and paving from Bonaire Path
north approximately 2,500 feet. Construction is planned to start in June August with
substantial completion this year. Start date was delayed due to a delay in sanitary
sewer permitting as well as a recent retaining wall easement problem.
Biscayne Ave – Scope includes construction of utilities and paving between Boulder
th
Trail and 160 Street (CSAH 46). This contract was awarded and is currently under
construction. Extension of sanitary sewer will provide service to the Biscayne
Business Park on the southern end of the project. This project is currently nearly
completed for the season. Final grading and work on stormwater features remains.
Final bituminous wear course will be done in 2021. Right of way acquisition is
completed. Project is under construction and a majority of the pipe/underground work
has been completed.
Bonaire Path – Scope includes construction of utilities and paving between Akron
Avenue and Anderson Drive. Additionally, the installation of crossing arms at the
Union Pacific Railroad intersection are in the scope of the project and planned for
2020. Ultimately, the city will request that this intersection become a quiet zone (i.e.
no train horns). Wear course and construction is anticipated to be completed in 2021;
however, that will hinge on Union Pacific completing the necessary crossing work.will
be installed in 2020 with exact dates to be established. Final design for rail
improvements was approved by City Council at the February 4 meeting. The next step
in this process requires that Union Pacific complete an agreement document so that all
costs are documented and then the work can be put forward for scheduling. Because
of the significant delays by Union Pacific no work is anticipated in 2020. At this time
staff has been attempting to coordinate scheduling for the Union Pacific work;
however, there has not been much response from the railroad. Additional
communication with both MnDOT and other Union Pacific staff is being done as well.
This work is anticipated to be complete this summer. Staff has been in contact with
the Federal Railroad Administration regarding application for a quiet zone (QZ).
Because of the design, the QZ application is expected to be approved.
Connemara Trail Extension – Scope includes construction of utilities and paving
from Akron Avenue east approximately 1,300 feet. Contract was awarded and work is
being planned for 2021 due to the significant workload. the contractor is planning to
start work sometime in July. Some additional work is being coordinated with the
parcel to the east to assist with future development.
2
Deepwoods Court – Scope includes pavement reclamation and minor curb repair
from McAndrews Road south approximately 1,900 feet. The contract has been
awarded and a preconstruction conference is scheduled for June 24. The work will
start after that date, but the actual schedule has not been established. Paving of base
course was completed on August 19. Final wear course schedule is being
coordinated. This project will be completed in 2020. Ribbon curb will be installed and
the residents have agree to pay for the additional cost.
Dunmore Storm Lift Station – Scope includes the construction of a stormwater lift
station in the Dunmore subdivision and connection to existing force main.
Construction is completed. Initial start up and control programming has been
performed. Restoration is underway.Generator connection tests will be performed in
the spring. Restoration will be completed in 2020.
Shannon Pond Outlet Feasibility Study – Scope includes reviewing potential routes
for stormwater outlet at Shannon Pond. Because of the land locked location outlet will
be a significant undertaking. Initially study work is anticipated in February 2020.
Information from this study will be used to establish future improvements necessary to
reduce the potential for structure flooding. Staff plans a future presentation to the
Utility Commission regarding this work.
TH 3 Drainage Improvements – Scope includes improving the stormwater crossing at
MN Hwy 3 between Dunmore and Harmony subdivisions. This is a joint project
between the City of Rosemount and MnDOT. Construction has been completed and
minor punch list work remains. This is the last month this project will be reported.
The following list is the current and planned developer projects.
Bella Vista 6 – Scope includes construction of utilities and paving from Aulden
Avenue to the cul-de-sac approximately 850’ north east as well as 19 single family
residential (SFR) lots of a planned total 158. In addition, there is a temporary sanitary
sewer lift station that will be installed until trunk sewer is extended at a future date.
Utilities and base course are in place and the lift station construction is complete with
minor punch list items to be corrected. Wear course is planned for 2020 with exact
dates to be established.
Bella Vista 7 – Scope will include construction of utilities and paving from a temporary
connection to the Autumn Path extension (see above) west approximately 1500 feet
as well as 26 SFR lots of a planned total 158. This is the final phase of this
development. Actual construction cannot occur until Autumn Path is construction to
allow access as this portion of Bella Vista is currently ‘land locked’. With the award of
Autumn Path, work has started on this project. Grading is completed.
Biscayne Business Park – Scope includes construction of utilities and paving from
Biscayne Avenue to the cul-de-sac approximately 750’ west as well as 8 commercial
lots. Temporary Metropolitan Council Environmental Services connect has been
removed. One building is under construction. and a temporary connection to the
Metropolitan Council Environmental Services (MCES) interceptor line. This
connection will be changed once Biscayne Avenue is reconstructed. Paving will be
done in 2020.
3
Caramore Crossing – Scope includes construction of utilities and paving from Akron
Avenue and from Bonaire Path as well as 82 SFR lots of a planned total 177. This
project is in the initial construction stage. Currently, the developer is preparing to
install a deep sanitary sewer manhole in the Akron right of way. This work is being
expedited so that it will minimize the impact to the paving of Akron by Dakota
County.This project is currently on hold.
nd
Dunmore – Scope includes construction of utilities and paving from 132 Street as
well as 30 SFR lots of a planned total 87. This project is complete Final acceptance
will take place in 2020. This is the last month this project will be reported.
Dunmore 2 – Scope includes construction of utilities and paving from Caffery Court as
well as 25 SFR lots of a planned total 87. Wear course will be installed in 2020 with
exact dates to be established. Contractor will be required to make repairs to the
stormwater ponds due to poor dewatering practices.
Greystone 7 – Scope includes construction of utilities and paving as well as 46 SFR
lots of a planned total 287. Wear course will be installed in 2020 with exact dates to be
established.
Greystone 8 – Scope includes construction of utilities and paving as well as 56 SFR
lots of a planned total 287. This is the final phase of this development. Wear course
will be installed in 2020 with exact dates to be established.
Harmony Parkview – Scope includes construction of utilities and paving as well as 22
townhomes. Utilities are city owned and the streets are private. This is the last month
this project will be reported.
nd
Harmony Parkview 2 – Scope includes construction of utilities and paving as well
as 26 townhomes. Utilities will be city owned and the streets are private. This project
will also fill temporary stormwater ponding on the east side of MN Hwy 3. Filling of the
temporary ponding is nearly completecurrently underway. Utility construction has
begun.
Harmony Villas – Scope includes construction of utilities and paving as well as 42
townhomes. Utilities are city owned and the streets are private. Utility construction is
complete. Minor site corrections are being performed. This is the last month this
project will be reported.
Harmony Villas 2 – Scope includes construction of utilities and paving as well as 26
townhomes. Utilities are city owned and the streets are private. Utility construction is
complete. Site corrections and building construction is underway.
nd
Meadow Ridge 2 – Scope includes construction of utilities and paving as well as 29
SFR lots of a planned total 154. Wear course will be installed in 2020 with exact dates
to be established.
4
rd
Meadow Ridge 3 – Scope includes construction of utilities, paving and a temporary
sanitary sewer lift station as well as 28 SFR lots of a planned total 154. This project is
planned for 2020 construction.
Morrison (Downtown redevelopment) – Scope includes redevelopment of the area
west of TH 3 in proximity to Shenanigans. Mixed commercial and apartments are
planned for this area. Demolition of Shenanigans and the mall are complete.
Foundation work is underway. Utility connections have been made.Ground breaking is
was done and demolition will start in the near future.
Prestwick 17 – Scope includes construction of utilities and paving, including the
completion of Addison Avenue to a temporary dead end to the east as well as 26
townhomes. Utilities will be city owned and the streets are private. Wear course will
be installed in 2020 with exact dates to be established.
Prestwick 18 – Scope includes construction of utilities and paving as well as 40
townhomes. Utilities will be city owned and the streets are private. Utilities have been
installed. Wear course will be installed in 2020 with exact dates to be established.
Prestwick 19 – Scope includes construction of utilities and paving as well as 35 SFR
lots. Wear course will be installed in 2020 with exact dates to be established.
Prestwick 20 – Scope includes construction of utilities and paving as well as 27 SFR
lots. This is the final phase of this development on the west side of Akron Avenue.
Construction is underway and planned for completion this year, with wear course
planned for 2021.This project is planned for 2020 construction.
Prestwick 21 – Scope includes construction of utilities and paving as well as 24
townhomes. Utilities will be city owned and the streets are private. Construction is
underway and planned for completion this year.This project is planned for 2020
construction.
Prestwick 22 – Scope includes construction of utilities and paving as well as 64
townhomes. Utilities will be city owned and the streets are private. Construction is
underway and planned for completion this year.This project is planned for 2020
construction.
Rosemount Woods Expansion – Scope includes construction of 39 additional
manufactured home sites as well as construction of private utility extensions for those
sites. Project was approved at the February 18 City Council meeting.This project is
currently in the initial stages of construction.
Wexford Place – Scope includes redevelopment of a multifamily residence at the
intersection of Chippendale Ave and CSAH 46 with an apartment building. Project is
currently under construction with a planned completion in 2020.
The following is the list of Dakota County and MnDOT projects.
CR 73 (Akron Ave) – Scope includes the reconstruction of Akron Avenue from
Bonaire Path to the Rosemount city limit. It also includes the construction of a trail
5
under pass near Flint Hills Soccer Complex. Finally, it includes pavement
thst
rehabilitation for 124 Court and 121 Street. Work is currently underway with the
stth
southern section being closed to traffic. Final paving on 121 Street and 124 Court
was completed. Due to construction access to this area will start to transition to the
south. Greenway trail underpass is nearing completion.is planned to be completed in
st
the next month. Some additional storm improvemenets were required along 121
Street.
Roundabout Connemara Trail/Diamond Path – Scope preliminary engineering for
the construction of a roundabout at this intersection. This project is planned for
construction in 2022. Preliminary design work continues.
CSAH 42/CR 73 (Akron Ave) Signal – Scope calls for installation of a traffic signal at
the intersection of CSAH 42 and CR 73 (Akron Ave) to address the increase in traffic
at this intersection. This project is planned for construction in 2021. Preliminary
design work is in process along with right of way determinations. City of Rosemount,
Dakota County, Dakota County Technical College and the University of Minnesota
continue to work in partnership to complete this project. A proposal to extend the
water main has been received and is under reviewapproved.
CSAH 42 Visioning Study – This is a study that will look at nearly the entire length of
CSAS 42 starting at the western county line (Burnsville) and ending at MN Trunk
Highway 52. Future open houses and public engagement opportunities will be
promulgated as they are established. At this time most public engagement will be via
on-line comments and updates.
CSAH 46 Corridor Study and Preliminary Engineering – This is a study that will
look at the section of CSAH 46 from Minnesota Trunk Highway 3 to CSAH 48 in
Coates. The scope of work anticipated is right of way acquisition to support expanding
the highway to a divided four-lane. This is a high priority project for Dakota County
and since a portion of this is within Rosemount city limits a portion of the cost would be
carried by the city. This study will assist with quantifying those costs.
TH 55 Safety Improvements – Scope includes improvements along Minnesota Trunk
Highway 55 (TH 55) by adding a left turn lane to Doyle Path. The Toward Zero Deaths
(TZD) program is leading a working group for this project.
6