EXECUTIVE SUMMARY
Utility Commission Meeting: September 28, 2020
AGENDA SECTION:
AGENDA ITEM: City Project Update Executive Director’s
Report
PREPARED BY: Brian Erickson, P.E. Director of Public Works
AGENDA NO. 8.a.
/ City Engineer
ATTACHMENTS: None APPROVED BY: BLE
RECOMMENDED ACTION: None, informational only
BACKGROUND
The 2020 construction season is beginning to wrap up for the season and this year has seen
a significant amount of construction throughout the city. The following list is the current and
planned City of Rosemount projects. There are additional developments that are in early
stages of the process and those will be added as appropriate. Changes since the last report
are shown as strike out for deletions and underlined for additions as well as a bar along the
left margin to indicate the changes.
132nd Street Improvements – Scope includes construction of utilities and paving
between MN Hwy 3 and Dodd Boulevard. Wear course has been completed and this
project is into the close out phase. This will be the last report on this project.will be
installed in 2020 with exact dates to be established. Addition of a small retaining wall
near an existing power pole is complete.
145th Street Sidewalk Improvements – Scope includes constructing sidewalk and
th
pedestrian ramps along the north side of 145 Street to the east of Brazil Ave. The
final sections of sidewalk have been completed and this area is open for pedestrian
traffic. Some restoration work remains.There is a portion of sidewalk across the Union
Pacific Railroad that has not been done as the crossing material was removed for rail
maintenance. Union Pacific has finally completed this work.
2019 Street Improvement Project – Scope includes mill and overlay of Connemara
Trail between Diamond Path and Shannon Parkway and restriping to a three-lane
section with some minor storm sewer improvements. Work started on May 14, 2020.
Work is nearly complete with boulevard restoration as the primary remaining item.
The scope includes mill and overlay or reclamation of:
Chippendale Avenue from 145th Street W to 160th Street W
Dodd Boulevard from Shannon Parkway to Chippendale Avenue
151st Street W from Shannon Parkway to Chippendale Avenue
Crestone Ave, Claret Ave and Cimarron Ave from CSAH 42 to 151st Street W
2021 Street Improvement Project – Scope includes mill and overlay or reclaim of:
C:\\Users\\jab\\AppData\\Local\\Temp\\8.a. Project Update_614898\\8.a. Project Update.docxG:\\MEETINGS\\UTILITY COMMISSION\\UC Items and
Packets\\2020\\20200928\\8.a. Project Update.docx
Covington Avenue
Colorado Avenue
th
Upper 149 Street W from Crandall Avenue to Colorado Avenue
Darling Path from Danbury Avenue to the southern curve
th
156 Street W from Darling Path to Shannon Parkway
th
Upper 156 Street W from Darling Path to Danville Avenue
th
156 Court W.
Dapple Court
Dapple Circle
th
157 Court W.
th
157 Street W.
thth
Danville Avenue from 156 Street W.to 156 Court W.
Cumberland Avenue
Crocus Avenue
Crocus Court
Crystal Path from Danville Avenue to Shannon Parkway
Crystal Court
Initial planning is underway and a neighborhood meeting is scheduled for October 8.
Construction is planned for 2021.
Adalyn Avenue – Scope includes construction of utilities and paving between Addison
Avenue and Connemara Trail. Wear course installed and project is in the close out
phase. This will be the last report on this project. will be installed in 2020 with exact
dates to be established.
st
Addison Ave – Scope includes construction of utilities and paving between 141
Street East and a temporary cul-de-sac to the east. Project was completed except for
wear course in 2018 and because of additional 2019 construction in the area, the
removal of the cul-de-sac and road extension to the east this summer. Final wear
installed and project is in the close out phase. This will be the last report on this
project.course will be done in 2020 with exact dates to be established.
Autumn Path – Scope includes construction of utilities and paving from Bonaire Path
north approximately 2,500 feet. Construction is planned to restart in August October
with utility installation complete this year. Road paving will be completed in 2021 due;
th
however, there will be gravel to allow access to the Bella Vista 7 subdivision.
substantial completion this year. Start date was delayed due to a delay in sanitary
sewer permitting as well as a recent retaining wall easement problem.
Biscayne Ave – Scope includes construction of utilities and paving between Boulder
th
Trail and 160 Street (CSAH 46). Extension of sanitary sewer will provide service to
the Biscayne Business Park on the southern end of the project. This project is
currently nearly completed for the season. Final grading and work on stormwater
features remains and will be completed prior to winter. Final bituminous wear course
will be done in 2021. No truck traffic will be allowed until the final bituminous course is
place.
Bonaire Path – Scope includes construction of utilities and paving between Akron
Avenue and Anderson Drive. Additionally, the installation of crossing arms at the
2
Union Pacific Railroad intersection are in the scope of the project and planned for
2020. Ultimately, the city will request that this intersection become a quiet zone (i.e.
no train horns). Wear course and construction is anticipated to be completed in 2021;
however, that will hinge on Union Pacific completing the necessary crossing work.
Final design for rail improvements was approved by City Council at the February 4
meeting. The next step in this process requires that Union Pacific complete an
agreement document so that all costs are documented and then the work can be put
forward for scheduling. Staff received notice that a draft agreement is in process;
however, because of the lengthy delay by UP the cost estimates expired and are being
updated. Once the agreement is received staff will bring to Council for approval.
Actual construction work by UP remains unscheduled at this time. Because of the
significant delays by Union Pacific no work is anticipated in 2020. Additional
communication with both MnDOT and other Union Pacific staff is being done as well.
Staff has been in contact with the Federal Railroad Administration regarding
application for a quiet zone (QZ). Because of the design, the QZ application is
expected to be approved.
Connemara Trail Extension – Scope includes construction of utilities and paving
from Akron Avenue east approximately 1,300 feet. Contract was awarded and work is
being planned for 2021 due to the significant workload. Some additional work is being
coordinated with the parcel to the east to assist with future development.
Deepwoods Court – Scope includes pavement reclamation and minor curb repair
from McAndrews Road south approximately 1,900 feet. Paving of base course was
completed on August 19. Final wear course is completed and restoration is under
way.schedule is being coordinated. This project will be completed in 2020. Ribbon
curb will be installed and the residents have agree to pay for the additional cost.
Dunmore Storm Lift Station – Scope includes the construction of a stormwater lift
station in the Dunmore subdivision and connection to existing force main.
Construction is completed. Initial startup and control programming has been
performed. Restoration is underway.
Shannon Pond Outlet Feasibility Study – Scope includes reviewing potential routes
for stormwater outlet at Shannon Pond. Because of the land locked location outlet will
be a significant undertaking. Initial study work is anticipated in February 2020was
received this summer. Information from this study will be used to establish future
improvements necessary to reduce the potential for structure flooding. Staff plans a
future presentation to the Utility Commission regarding this work.
The following list is the current and planned developer projects.
Bella Vista 6 – Scope includes construction of utilities and paving from Aulden
Avenue to the cul-de-sac approximately 850’ north east as well as 19 single family
residential (SFR) lots of a planned total 158. In addition, there is a temporary sanitary
sewer lift station that will be installed until trunk sewer is extended at a future date.
Utilities and base course are in place and the lift station construction is complete with
minor punch list items to be corrected. Wear course is planned for 2020 with exact
dates to be established.
3
Bella Vista 7 – Scope will include construction of utilities and paving from a temporary
connection to the Autumn Path extension (see above) west approximately 1500 feet
as well as 26 SFR lots of a planned total 158. This is the final phase of this
development. Construction of utilities is complete and the developer is working on
roadway construction. Actual construction cannot occur until Autumn Path is
construction to allow access as this portion of Bella Vista is currently ‘land locked’.
With the award of Autumn Path, work has started on this project.
Biscayne Business Park – Scope includes construction of utilities and paving from
Biscayne Avenue to the cul-de-sac approximately 750’ west as well as 8 commercial
lots. Temporary Metropolitan Council Environmental Services connect has been
removed. One building is under construction. Paving will be done in 2020.
Caramore Crossing – Scope includes construction of utilities and paving from Akron
Avenue and from Bonaire Path as well as 82 SFR lots of a planned total 177. This
project is in the initial construction stage. Developer has installed utilities from Akron
and is currently working on site grading.Currently, the developer is preparing to install
a deep sanitary sewer manhole in the Akron right of way. This work is being expedited
so that it will minimize the impact to the paving of Akron by Dakota County.
Dunmore 2 – Scope includes construction of utilities and paving from Caffery Court as
well as 25 SFR lots of a planned total 87. Wear course will be installed in 2020 with
exact dates to be established. Contractor will be required to make repairs to the
stormwater ponds due to poor dewatering practices.
Greystone 7 – Scope includes construction of utilities and paving as well as 46 SFR
lots of a planned total 287. Wear course is installed and project is in the close out
phase. This will be the last report on this project.will be installed in 2020 with exact
dates to be established.
Greystone 8 – Scope includes construction of utilities and paving as well as 56 SFR
lots of a planned total 287. This is the final phase of this development. Wear course
will be installed in 2020 with exact dates to be established.
nd
Harmony Parkview 2 – Scope includes construction of utilities and paving as well
as 26 townhomes. Utilities will be city owned and the streets are private. This project
will also fill temporary stormwater ponding on the east side of MN Hwy 3. Filling of the
temporary ponding is nearly complete. Utility construction has been completed and
townhome construction is underway.begun.
Harmony Villas 2 – Scope includes construction of utilities and paving as well as 26
townhomes. Utilities are city owned and the streets are private. Utility construction is
complete. Site corrections and building construction is underway.
nd
Meadow Ridge 2 – Scope includes construction of utilities and paving as well as 29
SFR lots of a planned total 154. Wear course is installed and project is in the close out
phase. This will be the last report on this project.will be installed in 2020 with exact
dates to be established.
4
rd
Meadow Ridge 3 – Scope includes construction of utilities, paving and a temporary
sanitary sewer lift station as well as 28 SFR lots of a planned total 154. This project is
nearly complete for the season. Lift station will be coming on line before home
construction can be started.planned for 2020 construction.
Morrison (Downtown redevelopment) – Scope includes redevelopment of the area
west of TH 3 in proximity to Shenanigans. Mixed commercial and apartments are
planned for this area. Utility connections and minor corrections being
performed.Demolition of Shenanigans and the mall are complete. Foundation work is
underway. Utility connections have been made.
Prestwick 17 – Scope includes construction of utilities and paving, including the
completion of Addison Avenue to a temporary dead end to the east as well as 26
townhomes. Utilities will be city owned and the streets are private. Wear course will
be installed in 2020 with exact dates to be established.
Prestwick 18 – Scope includes construction of utilities and paving as well as 40
townhomes. Utilities will be city owned and the streets are private. Utilities have been
installed. Wear course will be installed in 2020 with exact dates to be established.
Prestwick 19 – Scope includes construction of utilities and paving as well as 35 SFR
lots. Wear course is installed and project is in the close out phase. This will be the last
report on this project. will be installed in 2020 with exact dates to be established.
Prestwick 20 – Scope includes construction of utilities and paving as well as 27 SFR
lots. This is the final phase of this development on the west side of Akron Avenue.
Construction is underway and planned for completion this year, with wear course
planned for 2021.
Prestwick 21 – Scope includes construction of utilities and paving as well as 24
townhomes. Utilities will be city owned and the streets are private. Construction is
underway and planned for completion this year.
Prestwick 22 – Scope includes construction of utilities and paving as well as 64
townhomes. Utilities will be city owned and the streets are private. Construction is
underway and planned for completion this year.
Rosemount Woods Expansion – Scope includes construction of 39 additional
manufactured home sites as well as construction of private utility extensions for those
sites. This project is currently under construction. Preparation for improving the
northern section of Brazil Avenue is underway.in the initial stages of construction.
Wexford Place – Scope includes redevelopment of a multifamily residence at the
intersection of Chippendale Ave and CSAH 46 with an apartment building. Project is
currently under construction with a planned completion in 2020. This will be the last
report on this project.
The following is the list of Dakota County and MnDOT projects.
CR 73 (Akron Ave) – Scope includes the reconstruction of Akron Avenue from
5
Bonaire Path to the Rosemount city limit. It also includes the construction of a trail
under pass near Flint Hills Soccer Complex. Finally, it includes pavement
thst
rehabilitation for 124 Court and 121 Street. The southern end of Akron Avenue
th
between Biscayne and 127 St has been paved. Work has now shifted to the northern
end of the project.Work is currently underway with the southern section being closed
stth
to traffic. Final paving on 121 Street and 124 Court was completed. Due to
construction access to this area will start to transition to the south. Greenway trail
underpass is nearing completion.
Roundabout Connemara Trail/Diamond Path – Scope preliminary engineering for
the construction of a roundabout at this intersection. This project is planned for
construction in 2022. Preliminary design work continuesnearing completion.
CSAH 42/CR 73 (Akron Ave) Signal – Scope calls for installation of a traffic signal at
the intersection of CSAH 42 and CR 73 (Akron Ave) to address the increase in traffic
at this intersection. This project is planned for construction in 2021. Final design work
is nearly complete and Dakota County intends to bid this project by the end of 2020.
Design will include an extension of water main south to service possible future
development.Preliminary design work is in process along with right of way
determinations. City of Rosemount, Dakota County, Dakota County Technical College
and the University of Minnesota continue to work in partnership to complete this
project. A proposal to extend the water main has been approved.
CSAH 42 Visioning Study – This is a study that will look at nearly the entire length of
CSAS 42 starting at the western county line (Burnsville) and ending at MN Trunk
Highway 52. Future open houses and public engagement opportunities will be
promulgated as they are established. At this time most public engagement will be via
on-line comments and updates.
CSAH 46 Corridor Study and Preliminary Engineering – This is a study that will
look at the section of CSAH 46 from Minnesota Trunk Highway 3 to CSAH 48 in
Coates. The scope of work anticipated is right of way acquisition to support expanding
the highway to a divided four-lane. This is a high priority project for Dakota County
and since a portion of this is within Rosemount city limits a portion of the cost would be
carried by the city. This study will assist with quantifying those costs. Initial survey
work is underway.
TH 55 Safety Improvements – Scope includes improvements along Minnesota Trunk
Highway 55 (TH 55) by adding a left turn lane to Doyle Path. The Toward Zero Deaths
(TZD) program is leading a working group for this project.