E X E C U T I V E S U M M A R Y
Utility Commission Meeting: November 23, 2020
AGENDA ITEM: City Project Update
AGENDA SECTION:
Executive Director’s
Report
PREPARED BY: Brian Erickson, P.E. Director of Public Works
/ City Engineer AGENDA NO. 8.a.
ATTACHMENTS: None APPROVED BY: BLE
RECOMMENDED ACTION: None, informational only
BACKGROUND
The 2020 construction season is beginning to wrap up for the season and this year has seen
a significant amount of construction throughout the city. The following list is the current and
planned City of Rosemount projects. There are additional developments that are in early
stages of the process and those will be added as appropriate. Changes since the last report
are shown as strike out for deletions and underlined for additions as well as a bar along the
left margin to indicate the changes.
• 145th Street Sidewalk Improvements – Scope includes constructing sidewalk and
pedestrian ramps along the north side of 145th Street to the east of Brazil Ave. The
final sections of sidewalk have been completed and this area is open for pedestrian
traffic. Some restoration work remains.Restoration work is completed. This project is
in the close out phase and this will be the last report.
• 2019 Street Improvement Project – Work is nearly complete with boulevard
restoration as the primary remaining item. No further work is anticipated in 2020. The
scope includes mill and overlay or reclamation of:
• Chippendale Avenue from 145th Street W to 160th Street W
• Dodd Boulevard from Shannon Parkway to Chippendale Avenue
• 151st Street W from Shannon Parkway to Chippendale Avenue
• Crestone Ave, Claret Ave and Cimarron Ave from CSAH 42 to 151st Street W
• 2021 Street Improvement Project – Scope includes mill and overlay or reclaim of:
• Covington Avenue
• Colorado Avenue
• Upper 149th Street W from Crandall Avenue to Colorado Avenue
• Darling Path from Danbury Avenue to the southern curve
• 156th Street W from Darling Path to Shannon Parkway
• Upper 156th Street W from Darling Path to Danville Avenue
• 156th Court W.
• Dapple Court
• Dapple Circle
2
• 157th Court W.
• 157th Street W.
• Danville Avenue from 156th Street W.to 156th Court W.
• Cumberland Avenue
• Crocus Avenue
• Crocus Court
• Crystal Path from Danville Avenue to Shannon Parkway
• Crystal Court
Initial planning is and a neighborhood meeting is scheduled for October 8.The
feasibility report has been completed and the Improvement Hearing was held on
November 17, 2020. The City Council then ordered the preparation of plans and
specifications. Construction is planned for 2021.
• Autumn Path – Scope includes construction of utilities and paving from Bonaire Path
north approximately 2,500 feet. Construction is planned to restartstarted in October
with utility installation complete this year. Road paving will be completed in 2021;
however, there will be gravel to allow access to the Bella Vista 7 th subdivision.
• Biscayne Ave – Scope includes construction of utilities and paving between Boulder
Trail and 160th Street (CSAH 46). Extension of sanitary sewer will provide service to
the Biscayne Business Park on the southern end of the project. Final grading and
work on stormwater features remains and will be completed prior to winter. Final
bituminous wear course will be done in 2021. No truck traffic will be allowed until the
final bituminous course is place.
• Bonaire Path – Scope includes construction of utilities and paving between Akron
Avenue and Anderson Drive. Additionally, the installation of crossing arms at the
Union Pacific Railroad intersection are in the scope of the project and planned for
2020. Ultimately, the city will request that this intersection become a quiet zone (i.e.
no train horns). Wear course and construction is anticipated to be completed in 2021;
however, that will hinge on Union Pacific completing the necessary crossing work.
Final design for rail improvements was approved by City Council at the February 4 ,
2020 meeting. The next step in this process requires that Union Pacific complete an
agreement document so that all costs are documented and then the work can be put
forward for scheduling. Staff received notice that a draft agreement is in process;
however, because of the lengthy delay by UP the cost estimates expired and are being
updated. Once the agreement is received staff will bring to Council for approval.
Actual construction work by UP remains unscheduled at this time. Because of the
significant delays by Union Pacific no work is anticipated in 2020. Additional
communication with both MnDOT and other Union Pacific staff is being done as well.
Staff has been in contact with the Federal Railroad Administration regarding
application for a quiet zone (QZ). Because of the design, the QZ application is
expected to be approved.
• Connemara Trail Extension – Scope includes construction of utilities and paving
from Akron Avenue east approximately 1,300 feet. Contract was awarded and work is
being planned for 2021 due to the significant workload. Some additional work is being
coordinated with the parcel to the east to assist with future development.
3
• Deepwoods Court – Scope includes pavement reclamation and minor curb repair
from McAndrews Road south approximately 1,900 feet. Final wear course is
completed and restoration is under way. This project will be completed in 2020.
Ribbon curb will be installed and the residents have agree to pay for the additional
cost. This project is in the close out phase and this will be the last report.
• Dunmore Storm Lift Station – Scope includes the construction of a stormwater lift
station in the Dunmore subdivision and connection to existing force main.
Construction is completed. Initial startup and control programming has been
performed. Restoration is underway.
• Shannon Pond Outlet Feasibility Study – Scope includes reviewing potential routes
for stormwater outlet at Shannon Pond. Because of the land locked location outlet will
be a significant undertaking. Initial study work was received this summer. Information
from this study will be used to estab lish future improvements necessary to reduce the
potential for structure flooding. Staff plans a future presentation to the Utility
Commission regarding this work.
The following list is the current and planned developer projects.
• Bella Vista 6th – Scope includes construction of utilities and paving from Aulden
Avenue to the cul-de-sac approximately 850’ north east as well as 19 single family
residential (SFR) lots of a planned total 158. In addition, there is a temporary sanitary
sewer lift station that will be installed until trunk sewer is extended at a future date.
Utilities and base course are in place and the lift station construction is complete with
minor punch list items to be corrected. Wear course is planned for 2020 with exact
dates to be established.
• Bella Vista 7th – Scope will include construction of utilities and paving from a
temporary connection to the Autumn Path extension (see above) west approximately
1500 feet as well as 26 SFR lots of a planned total 158. This is the final phase of this
development. Construction of utilities is complete and the developer has completed
paving of the base course for 2020.is working on roadway construction.
• Biscayne Business Park – Scope includes construction of utilities and paving from
Biscayne Avenue to the cul-de-sac approximately 750’ west as well as 8 commercial
lots. One building is under construction. Paving will be done in 2020.
• Caramore Crossing 1st – Scope includes construction of utilities and paving from
Akron Avenue and from Bonaire Path as well as 82 SFR lots of a planned total 177.
This project is in the initial construction stage. Developer has installed utilities from
Akron and is currently working on site grading.
• Dunmore 2nd – Scope includes construction of utilities and paving from Caffery Court
as well as 25 SFR lots of a planned total 87. Wear course will be installed in 2020 with
exact dates to be established. Contractor will be required to make repairs to the
stormwater ponds due to poor dewatering practices.
4
• Emerald Isle 1st – Scope includes construction of utilities and paving as w ell as 40
SFR lots of a planned total 151. Grading work and initial utility construction is
complete. Contractor has paved the base course for 2020.
• Greystone 8th – Scope includes construction of utilities and paving as well as 56 SFR
lots of a planned total 287. This is the final phase of this development. Wear course
will bewas installed in 2020. with exact dates to be established.
• Harmony Parkview 2nd – Scope includes construction of utilities and paving as well
as 26 townhomes. Utilities will be city owned and the streets are private. This project
will also fill temporary stormwater ponding on the east side of MN Hwy 3. Filling of the
temporary ponding is complete. Utility construction has been completed and
townhome construction is underway.
• Harmony Villas 2nd – Scope includes construction of utilities and paving as well as 26
townhomes. Utilities are city owned and the streets are private. Utility construction is
complete. Site corrections and building construction is underway.
• Meadow Ridge 3rd – Scope includes construction of utilities, paving and a temporary
sanitary sewer lift station as well as 28 SFR lots of a planned total 154. This project is
nearly complete for the season. Lift station will be coming on line before home
construction can be started.
• Meadow Ridge 4th – Scope includes construction of utilites and paving as well as 63
SFR lots of a planned total 154. This is the final phase of this development.
Construction is planned for 2021.
• Morrison (Downtown redevelopment) – Scope includes redevelopment of the area
west of TH 3 in proximity to Shenanigans. Mixed commercial and apartments are
planned for this area. Utility connections and minor corrections completedbeing
performed.
• Prestwick 17th – Scope includes construction of utilities and paving, including the
completion of Addison Avenue to a temporary dead end to the east as well as 26
townhomes. Utilities will be city owned and the streets are private. Wear course will
be installed in 2020 with exact dates to be established.
• Prestwick 18th – Scope includes construction of utilities and paving as well as 40
townhomes. Utilities will be city owned and the streets are private. Utilities have been
installed. Wear course will be installed in 2020 with exact dates to be established.
• Prestwick 20th – Scope includes construction of utilities and paving as well as 27 SFR
lots. This is the final phase of this development on the west side of Akron Avenue.
Construction is underway and planned for completion this year, with wear course
planned for 2021.
• Prestwick 21st – Scope includes construction of utilities and paving as well as 24
townhomes. Utilities will be city owned and the streets are private. Construction is
underway and planned for completion this year.
5
• Prestwick 22nd – Scope includes construction of utilities and paving as well as 64
townhomes. Utilities will be city owned and the streets are private. Construction is
underway and planned for completion this year.
• Rosemount Woods Expansion – Scope includes construction of 39 additional
manufactured home sites as well as construction of private utility extensions for those
sites. This project is currently under construction. Wear course paving on Brazil
Avenue is complete for 2020.Preparation for improving the northern section of Brazil
Avenue is underway.
The following is the list of Dakota County and MnDOT projects.
• CR 73 (Akron Ave) – Scope includes the reconstruction of Akron Avenue from
Bonaire Path to the Rosemount city limit. It also includes the construction of a trail
under pass near Flint Hills Soccer Complex. Finally, it includes pavement
rehabilitation for 124th Court and 121st Street. The entire length of Akron has been
paved and restoration and striping are planned to be completed prior to winter.The
southern end of Akron Avenue between Biscayne and 127th St has been paved. Work
has now shifted to the northern end of the project. Final paving on 121st Street and
124th Court was completed. Greenway trail underpass is nearing completion.
• Roundabout Connemara Trail/Diamond Path – Scope preliminary engineering for
the construction of a roundabout at this intersection. This project is planned for
construction in 2022. Preliminary design work nearing completion.
• CSAH 42/CR 73 (Akron Ave) Signal – Scope calls for installation of a traffic signal at
the intersection of CSAH 42 and CR 73 (Akron Ave) to address the increase in traffic
at this intersection. This project is planned for construction in 2021. Final design work
is nearly complete, and Dakota County has the project out for bids currently.intends to
bid this project by the end of 2020. Design will include an extension of water main
south to service possible future development. City of Rosemount, Dakota County,
Dakota County Technical College and the University of Minnesota continue to work in
partnership to complete this project. Review of possible road and water main
extension is in progress to assist with potential future development.
• CSAH 42 Visioning Study – This is a study that will look at nearly the entire length of
CSAS 42 starting at the western county line (Burnsville) and ending at MN Trunk
Highway 52. Future open houses and public engagement opportunities will be
promulgated as they are established. At this time most public engagement will be via
on-line comments and updates.
• CSAH 46 Corridor Study and Preliminary Engineering – This is a study that will
look at the section of CSAH 46 from Minnesota Trunk Highway 3 to CSAH 48 in
Coates. The scope of work anticipated is right of way acquisition to support expandin g
the highway to a divided four-lane. This is a high priority project for Dakota County
and since a portion of this is within Rosemount city limits a portion of the cost would be
carried by the city. This study will assist with quantifying those costs. Initial survey
work is completedunderway.
6
• Mississippi River Greenway – Scope includes the reconstruction of a portion of Pine
Bend Trail to allow for the completion of the Dakota County trail connection from St.
Paul to Hastings. This work will be funded by Dakota County. Additionally, the section
of Pine Bend Trail between TH 55 and the reconstructed section will be reclaimed at
city cost. This work is planned for 2021. Dakota County is in the process of securing
agreements with the rail road to allow for the trail crossing.
• TH 55 Safety Improvements – Scope includes improvements along Minnesota Trunk
Highway 55 (TH 55) by adding a left turn lane to Doyle Path and increasing the truck
acceleration lane at the rail road crossing. The Toward Zero Deaths (TZD) program is
leading a working group for this project.