EXECUTIVE SUMMARY
City Council Meeting: December 1, 2020
BACKGROUND
Per the NPDES MS4 General Permit administered by the Minnesota Pollution Control Agency
(MPCA), the City is required to inspect every stormwater pond and outfall at least once per permit
term and develop a method to assess the effectiveness of all stormwater ponds for
preventing/capturing pollution. Inspections performed in 2015 and subsequent modeling indicated
that pond 1935 (Broback Industrial Park) and pond 0589 (Dawson CT) were operating at a low
efficiency and maintenance was recommended.
The project proposes to excavate 1640 cubic yards of accumulated sediment from pond 1935 and
1,285 cubic yards of accumulated sediment from pond 0589. An additional 520 cubic yards of soil
will be removed from upland areas of pond 1935 to reduce slope steepness as a safety precaution for
equipment, such as mowers, that accesses the site regularly for maintenance. Approximately 1,985
cubic yards of the sediment being removed have contaminant levels that require special disposal (e.g.
not for use as fill in residential areas or disposal at a landfill).
Phosphorus removal efficiency is expected to improve by 12% in pond 0589 and by 29% in pond
1935. Suspended solids removal is expected to improve by 15% in pond 0589 and by 43% in pond
1935. Additional benefits of the project include removal of voluntary trees for better inspection and
maintenance access and increased flood storage capacity.
COSTS & FUNDING
A summary of the Bid Tabulation including the Engineer’s Estimate is shown in the following table.
The low bid received is $136,409.40. This is approximately $78,000 below the Engineer’s Estimate.
AGENDA ITEM: 2021 Storm Basin Maintenance, City
Project 2021-02: Receive Bids and Award
Contract
AGENDA SECTION:
Consent
PREPARED BY: Brian Erickson, PE, Director of Public
Works / City Engineer
Jane Byron, PE, Storm Water Specialist
AGENDA NO. 6.h.
ATTACHMENTS: Resolution; Letter or Recommendation;
Bid Tabulation; Bid Summary; Map APPROVED BY: LJM
RECOMMENDED ACTIONS: Motion to Adopt a Resolution Receiving Bids and Awarding
Contract for 2021 Storm Basin Maintenance Project, City Project 2021-02.
2
Contactor Bid Amount Percentage Above
Low Bid
Nadeau Companies $136,409.40 Low Bid
Fitzgerald Excavating $150,984.00 10.68%
Kevitt Excavating $165,995.05 21.69%
US SiteWork $166,674.70 22.19%
BKJ Land Co II dba BKJ Excavating $171,560.90 25.77%
Peterson Companies $176,501.30 29.39%
Standard Contracting $180,064.25 32.00%
Minnesota Dirt Works $187,986.00 37.81%
Rachel Contracting, LLC $188,794.00 38.40%
JACON LLC $196,674.00 44.18%
McNamara Contracting $209,755.25 53.77%
Sunram Construction, Inc. $229,003.00 67.88%
New Look Contracting, Inc. $229,676.00 68.37%
Meyer Contracting, Inc. $243,988.00 78.86%
Frattalone Companies $251,198.75 84.15%
Veit & Company, Inc. $264,415.00 93.84%
Blackstone Contractors LLC $276,553.50 102.74 %
This project will be funded using the Storm Water Utility, and the engineer’s estimate of probable
project cost was $214,250.00. Stormwater System Improvement is a regular line item in the Storm
Water Utility budget.
SCHEDULE
Should the Council approve this resolution, the proposed project schedule is shown below.
Construction Start Winter 2020/21
Substantial Completion February 28, 2021
Restoration May 31, 2021
RECOMMENDATION
Staff recommends Council adopt the attached resolutions accepting bids, awarding the contract to
Nadeau Companies for the 2021 Storm Basin Maintenance Project, City Project 2021-02.
K:\015819-000\Admin\Construction Admin\015819-000 CST LOR_20201124.docx 701 XENIA AVENUE S | SUITE 300 | MINNEAPOLIS, MN | 55416 | 763.541.4800 | WSBENG.COM November 24, 2020
Honorable Mayor and City Council
City of Rosemount
2875 145th Street West
Rosemount, MN
Re: 2020 Rosemount Pond Maintenance Project
City of Rosemount Project No. 2021-02
WSB Project No. 015819-000
Dear Mayor and Council Members:
Bids were received for the above-referenced project on Tuesday, November 24, 2020, and were
opened and read aloud. A total of 17 bids were received. The bids were checked for
mathematical accuracy and tabulated and there are no errors made on the Bid Forms. The
Engineer’s Estimate was $214,250.00. The bid tabulation indicates the low bidder as Nadeau
Companies, LLC., Hampton, MN, in the amount of $136,409.40.
We recommend that the City consider these bids and award a contract to Nadeau Companies,
LLC., based on the results of the bids received.
Sincerely,
WSB
Bill Alms, PE
Project Manager
Enclosure
cc: Michael Nadeau, Nadeau Companies, LLC
Tim Hanson, City of Rosemount
Kendra Fallon, WSB
alp
2020 Rosemount Pond Maintenance Project
City of Rosemount Project No. 2021-02
Bid Opening: November 24, 2020 at 10:00 a.m. local time
WSB Project No. 015819-000
DENOTES CORRECTED FIGURE
Contractor Bid Docs Bid Security (5%)Grand Total Bid
1 Nadeau Companies X X $136,409.40
2 Fitzgerald Excavating X X $150,984.00
3 Kevitt Excavating X X $165,995.05
4 US SiteWork X X $166,674.70
5 BKJ Land Co II dba BKJ Excavating X X $171,560.90
6 Peterson Companies X X $176,501.30
7 Standard Contracting X X $180,064.25
8 Minnesota Dirt Works X X $187,986.00
9 Rachel Contracting, LLC X X $188,794.00
10 JACON LLC X X $196,674.00
11 McNamara Contracting X X $209,755.25
12 Sunram Construction, Inc.X X $229,003.00
13 New Look Contracting, Inc.X X $229,676.00
14 Meyer Contracting, Inc.X X $243,988.00
15 Frattalone Companies X X $251,198.75
16 Veit & Company, Inc.X X $264,415.00
17 Blackstone Contractors LLC X X $276,553.50
Engineer's Opinion of Cost $214,250.00
BID TABULATION SUMMARY
Bill Alms, PE Project Manager
I hereby certify that this is a true and correct tabulation of the bids as received on November 24, 2020.
K:\015819-000\Admin\Construction Admin\015819-000 CST Bid Tab Summary_20201124.xlsx
Bid Tabulation2020 Rosemount Pond Maintenance ProjectCity of Rosemount Project No. 2021-02Bid Opening: Tuesday, November 24, 2020 at 10:00 a.m. Local TimeWSB Project No. 015819-000DENOTES CORRECTED FIGURELine # Mat. # Item Units Qty Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price1 2021.501 MOBILIZATION LS 1 $10,000.00 $10,000.00 $10,100.00 $10,100.00 $12,000.00 $12,000.00 $8,000.00 $8,000.002 2051.501 MAINTENANCE AND RESTORATION OF HAUL ROADS LS 1 $6,000.00 $6,000.00 $3,100.00 $3,100.00 $2,000.00 $2,000.00 $12,560.00 $12,560.003 2101.505 CLEARING ACRE 0.15 $10,000.00 $1,500.00 $26,000.00 $3,900.00 $7,000.00 $1,050.00 $46,960.00 $7,044.004 2105.504 GEOTEXTILE FABRIC TYPE 4 S Y 68 $5.00 $340.00 $4.30 $292.40 $4.00 $272.00 $10.20 $693.605 2105.507 POND EXCAVATION (LV) C Y 1,460 $30.00 $43,800.00 $17.20 $25,112.00 $14.00 $20,440.00 $17.90 $26,134.006 2105.507 POND EXCAVATION (SPECIAL 1) (LV) CY 700 $40.00 $28,000.00 $17.20 $12,040.00 $20.00 $14,000.00 $17.90 $12,530.007 2105.509 POND EXCAVATION (SPECIAL 2) (LV) TON 1,800 $45.00 $81,000.00 $29.80 $53,640.00 $40.00 $72,000.00 $30.80 $55,440.008 2105.601 DEWATERING LS 1 $12,000.00 $12,000.00 $3,100.00 $3,100.00 $8,500.00 $8,500.00 $11,830.00 $11,830.009 2511.507 RANDOM RIPRAP CLASS III C Y 34 $125.00 $4,250.00 $44.00 $1,496.00 $50.00 $1,700.00 $119.00$4,046.0010 2511.507 GRANULAR FILTER C Y 17 $50.00 $850.00 $46.00 $782.00 $58.00 $986.00 $118.00 $2,006.0011 2573.502 STORM DRAIN INLET PROTECTION EACH 4 $150.00 $600.00 $170.00 $680.00 $150.00 $600.00 $298.00 $1,192.0012 2573.533 SEDIMENT CONTROL LOG TYPE BIOROLL L F 800 $3.00 $2,400.00 $2.80 $2,240.00 $3.00 $2,400.00 $5.45 $4,360.0013 2105.602 TEMPORARY ROCK CONSTRUCTION ENTRANCE EACH 2 $1,000.00 $2,000.00 $2,200.00 $4,400.00 $8.00 $16.00 $1,700.00 $3,400.0014 2575.504 EROSION CONTROL BLANKETS CATEGORY 3N S Y 6,150 $2.00 $12,300.00 $1.90 $11,685.00 $2.00 $12,300.00 $2.30 $14,145.0015 2575.505 SEEDING ACRE 1 $5,000.00 $6,500.00 $1,300.00 $1,690.00 $1,500.00 $1,950.00 $704.00 $915.2016 2575.508 SEED MIXTURE 21-111 LB 125 $10.00 $1,250.00 $4.40 $550.00 $2.00 $250.00 $2.75 $343.7517 2575.508 SEEDING MIXTURE 25-151 LB 70 $8.00 $560.00 $6.60 $462.00 $4.00 $280.00 $5.35 $374.5018 2575.508 SEED MIXTURE 33-261 LB 30 $30.00 $900.00 $38.00 $1,140.00 $8.00 $240.00 $32.70 $981.00$214,250.00 $136,409.40 $150,984.00 $165,995.05GRAND TOTAL BIDEngineer's Estimate Fitzgerald ExcavatingNadeau Companies Kevitt Excavating Page 1 of 6K:\015819-000\Admin\Construction Admin\015819-000 CST Bid Tab_20201124.xlsx
Bid Tabulation2020 Rosemount Pond Maintenance ProjectCity of Rosemount Project No. 2021-02Bid Opening: Tuesday, November 24, 2020 at 10:00 a.m. Local TimeWSB Project No. 015819-000DENOTES CORRECTED FIGURELine # Mat. # Item Units Qty Unit Price Total Price1 2021.501 MOBILIZATION LS 1 $10,000.00 $10,000.002 2051.501 MAINTENANCE AND RESTORATION OF HAUL ROADS LS 1 $6,000.00 $6,000.003 2101.505 CLEARING ACRE 0.15 $10,000.00 $1,500.004 2105.504 GEOTEXTILE FABRIC TYPE 4 S Y 68 $5.00 $340.005 2105.507 POND EXCAVATION (LV) C Y 1,460 $30.00 $43,800.006 2105.507 POND EXCAVATION (SPECIAL 1) (LV) CY 700 $40.00 $28,000.007 2105.509 POND EXCAVATION (SPECIAL 2) (LV) TON 1,800 $45.00 $81,000.008 2105.601 DEWATERING LS 1 $12,000.00 $12,000.009 2511.507 RANDOM RIPRAP CLASS III C Y 34 $125.00 $4,250.0010 2511.507 GRANULAR FILTER C Y 17 $50.00 $850.0011 2573.502 STORM DRAIN INLET PROTECTION EACH 4 $150.00 $600.0012 2573.533 SEDIMENT CONTROL LOG TYPE BIOROLL L F 800 $3.00 $2,400.0013 2105.602 TEMPORARY ROCK CONSTRUCTION ENTRANCE EACH 2 $1,000.00 $2,000.0014 2575.504 EROSION CONTROL BLANKETS CATEGORY 3N S Y 6,150 $2.00 $12,300.0015 2575.505 SEEDING ACRE 1 $5,000.00 $6,500.0016 2575.508 SEED MIXTURE 21-111 LB 125 $10.00 $1,250.0017 2575.508 SEEDING MIXTURE 25-151 LB 70 $8.00 $560.0018 2575.508 SEED MIXTURE 33-261LB 30 $30.00 $900.00$214,250.00GRAND TOTAL BIDEngineer's EstimateUnit Price Total Price Unit Price Total Price Unit Price Total Price$11,140.00 $11,140.00 $11,500.00 $11,500.00 $17,380.00 $17,380.00$24,560.00 $24,560.00 $9,800.00 $9,800.00 $7,400.00 $7,400.00$29,970.00 $4,495.50 $25,000.00 $3,750.00 $30,800.00 $4,620.00$9.00 $612.00 $1.00 $68.00 $5.60 $380.80$17.00 $24,820.00 $21.63 $31,579.80 $22.50 $32,850.00$12.00 $8,400.00 $23.80 $16,660.00 $18.60 $13,020.00$30.50 $54,900.00 $32.16 $57,888.00 $29.25 $52,650.00$14,110.00 $14,110.00 $7,500.00 $7,500.00 $9,290.00 $9,290.00$112.00 $3,808.00 $105.00 $3,570.00 $127.00 $4,318.00$71.00 $1,207.00 $16.80 $285.60 $130.00 $2,210.00$157.00 $628.00 $5.00 $20.00 $271.00 $1,084.00$3.50 $2,800.00 $4.50 $3,600.00 $4.30 $3,440.00$535.00 $1,070.00 $1,200.00 $2,400.00 $2,040.00 $4,080.00$2.00 $12,300.00 $3.25 $19,987.50 $1.50 $9,225.00$689.00 $895.70 $1,200.00 $1,560.00 $9,980.00 $12,974.00$1.70 $212.50 $2.50 $312.50 $0.94 $117.50$8.00 $560.00 $3.85 $269.50 $3.85 $269.50$5.20 $156.00 $27.00 $810.00 $39.75 $1,192.50$166,674.70 $171,560.90 $176,501.30Peterson CompaniesBKJ Land Co II dba BKJ ExcavatingUS SiteWorkPage 2 of 6K:\015819-000\Admin\Construction Admin\015819-000 CST Bid Tab_20201124.xlsx
Bid Tabulation2020 Rosemount Pond Maintenance ProjectCity of Rosemount Project No. 2021-02Bid Opening: Tuesday, November 24, 2020 at 10:00 a.m. Local TimeWSB Project No. 015819-000DENOTES CORRECTED FIGURELine # Mat. # Item Units Qty Unit Price Total Price1 2021.501 MOBILIZATION LS 1 $10,000.00 $10,000.002 2051.501 MAINTENANCE AND RESTORATION OF HAUL ROADS LS 1 $6,000.00 $6,000.003 2101.505 CLEARING ACRE 0.15 $10,000.00 $1,500.004 2105.504 GEOTEXTILE FABRIC TYPE 4 S Y 68 $5.00 $340.005 2105.507 POND EXCAVATION (LV) C Y 1,460 $30.00 $43,800.006 2105.507 POND EXCAVATION (SPECIAL 1) (LV) CY 700 $40.00 $28,000.007 2105.509 POND EXCAVATION (SPECIAL 2) (LV) TON 1,800 $45.00 $81,000.008 2105.601 DEWATERING LS 1 $12,000.00 $12,000.009 2511.507 RANDOM RIPRAP CLASS III C Y 34 $125.00 $4,250.0010 2511.507 GRANULAR FILTER C Y 17 $50.00 $850.0011 2573.502 STORM DRAIN INLET PROTECTION EACH 4 $150.00 $600.0012 2573.533 SEDIMENT CONTROL LOG TYPE BIOROLL L F 800 $3.00 $2,400.0013 2105.602 TEMPORARY ROCK CONSTRUCTION ENTRANCE EACH 2 $1,000.00 $2,000.0014 2575.504 EROSION CONTROL BLANKETS CATEGORY 3N S Y 6,150 $2.00 $12,300.0015 2575.505 SEEDING ACRE 1 $5,000.00 $6,500.0016 2575.508 SEED MIXTURE 21-111 LB 125 $10.00 $1,250.0017 2575.508 SEEDING MIXTURE 25-151 LB 70 $8.00 $560.0018 2575.508 SEED MIXTURE 33-261LB 30 $30.00 $900.00$214,250.00GRAND TOTAL BIDEngineer's EstimateUnit Price Total Price Unit Price Total Price Unit Price Total Price$7,976.00 $7,976.00 $12,000.00 $12,000.00 $24,440.00 $24,440.00$6,545.00 $6,545.00 $5,500.00 $5,500.00 $5,200.00 $5,200.00$45,475.00 $6,821.25 $30,000.00 $4,500.00 $34,666.67 $5,200.00$2.50 $170.00 $2.50 $170.00 $15.00 $1,020.00$17.00 $24,820.00 $22.90 $33,434.00 $18.00 $26,280.00$17.00 $11,900.00 $49.60 $34,720.00 $18.00 $12,600.00$45.95 $82,710.00 $38.30 $68,940.00 $43.50 $78,300.00$7,855.00 $7,855.00 $9,000.00 $9,000.00 $9,632.50 $9,632.50$113.00 $3,842.00 $92.00 $3,128.00 $155.00 $5,270.00$115.50 $1,963.50 $62.00 $1,054.00 $165.00 $2,805.00$183.00 $732.00 $225.00 $900.00 $300.00 $1,200.00$3.65 $2,920.00 $3.10 $2,480.00 $2.50 $2,000.00$2,345.00 $4,690.00 $1,050.00 $2,100.00 $1,500.00 $3,000.00$2.40 $14,760.00 $1.35 $8,302.50 $1.50 $9,225.00$1,090.00 $1,417.00 $500.00 $650.00 $1,100.00 $1,430.00$0.50 $62.50 $0.80 $100.00 $1.10 $137.50$2.50 $175.00 $3.25 $227.50 $5.20 $364.00$23.50 $705.00 $26.00 $780.00 $23.00 $690.00$180,064.25 $187,986.00 $188,794.00Standard Contracting Minnesota Dirt Works Rachel Contracting, LLCPage 3 of 6K:\015819-000\Admin\Construction Admin\015819-000 CST Bid Tab_20201124.xlsx
Bid Tabulation2020 Rosemount Pond Maintenance ProjectCity of Rosemount Project No. 2021-02Bid Opening: Tuesday, November 24, 2020 at 10:00 a.m. Local TimeWSB Project No. 015819-000DENOTES CORRECTED FIGURELine # Mat. # Item Units Qty Unit Price Total Price1 2021.501 MOBILIZATION LS 1 $10,000.00 $10,000.002 2051.501 MAINTENANCE AND RESTORATION OF HAUL ROADS LS 1 $6,000.00 $6,000.003 2101.505 CLEARING ACRE 0.15 $10,000.00 $1,500.004 2105.504 GEOTEXTILE FABRIC TYPE 4 S Y 68 $5.00 $340.005 2105.507 POND EXCAVATION (LV) C Y 1,460 $30.00 $43,800.006 2105.507 POND EXCAVATION (SPECIAL 1) (LV) CY 700 $40.00 $28,000.007 2105.509 POND EXCAVATION (SPECIAL 2) (LV) TON 1,800 $45.00 $81,000.008 2105.601 DEWATERING LS 1 $12,000.00 $12,000.009 2511.507 RANDOM RIPRAP CLASS III C Y 34 $125.00 $4,250.0010 2511.507 GRANULAR FILTER C Y 17 $50.00 $850.0011 2573.502 STORM DRAIN INLET PROTECTION EACH 4 $150.00 $600.0012 2573.533 SEDIMENT CONTROL LOG TYPE BIOROLL L F 800 $3.00 $2,400.0013 2105.602 TEMPORARY ROCK CONSTRUCTION ENTRANCE EACH 2 $1,000.00 $2,000.0014 2575.504 EROSION CONTROL BLANKETS CATEGORY 3N S Y 6,150 $2.00 $12,300.0015 2575.505 SEEDING ACRE 1 $5,000.00 $6,500.0016 2575.508 SEED MIXTURE 21-111 LB 125 $10.00 $1,250.0017 2575.508 SEEDING MIXTURE 25-151 LB 70 $8.00 $560.0018 2575.508 SEED MIXTURE 33-261LB 30 $30.00 $900.00$214,250.00GRAND TOTAL BIDEngineer's EstimateUnit Price Total Price Unit Price Total Price Unit Price Total Price$10,728.00 $10,728.00 $16,500.00 $16,500.00 $12,150.50 $12,150.50$10,000.00 $10,000.00 $2,500.00 $2,500.00 $29,000.00 $29,000.00$35,000.00 $5,250.00 $25,000.00 $3,750.00 $36,700.00 $5,505.00$12.00 $816.00 $5.50 $374.00 $5.00 $340.00$27.00 $39,420.00 $35.00 $51,100.00 $28.75 $41,975.00$27.00 $18,900.00 $35.00 $24,500.00 $28.75 $20,125.00$36.00 $64,800.00 $48.00 $86,400.00 $40.50 $72,900.00$16,500.00 $16,500.00 $4,000.00 $4,000.00 $10,600.00 $10,600.00$125.00 $4,250.00 $125.00 $4,250.00 $105.00 $3,570.00$50.00 $850.00 $30.00 $510.00 $90.00 $1,530.00$300.00 $1,200.00 $200.00 $800.00 $150.00 $600.00$3.00 $2,400.00 $2.75 $2,200.00 $6.25 $5,000.00$1,500.00 $3,000.00 $900.00 $1,800.00 $800.00 $1,600.00$2.50 $15,375.00 $1.50 $9,225.00 $3.10 $19,065.00$1,500.00 $1,950.00 $525.00 $682.50 $3,075.00 $3,997.50$1.00 $125.00 $0.75 $93.75 $1.00 $125.00$3.00 $210.00 $3.50 $245.00 $5.00 $350.00$30.00 $900.00 $27.50 $825.00 $19.00 $570.00$196,674.00 $209,755.25 $229,003.00McNamara Contracting Sunram Construction, Inc.JACON LLCPage 4 of 6K:\015819-000\Admin\Construction Admin\015819-000 CST Bid Tab_20201124.xlsx
Bid Tabulation2020 Rosemount Pond Maintenance ProjectCity of Rosemount Project No. 2021-02Bid Opening: Tuesday, November 24, 2020 at 10:00 a.m. Local TimeWSB Project No. 015819-000DENOTES CORRECTED FIGURELine # Mat. # Item Units Qty Unit Price Total Price1 2021.501 MOBILIZATION LS 1 $10,000.00 $10,000.002 2051.501 MAINTENANCE AND RESTORATION OF HAUL ROADS LS 1 $6,000.00 $6,000.003 2101.505 CLEARING ACRE 0.15 $10,000.00 $1,500.004 2105.504 GEOTEXTILE FABRIC TYPE 4 S Y 68 $5.00 $340.005 2105.507 POND EXCAVATION (LV) C Y 1,460 $30.00 $43,800.006 2105.507 POND EXCAVATION (SPECIAL 1) (LV) CY 700 $40.00 $28,000.007 2105.509 POND EXCAVATION (SPECIAL 2) (LV) TON 1,800 $45.00 $81,000.008 2105.601 DEWATERING LS 1 $12,000.00 $12,000.009 2511.507 RANDOM RIPRAP CLASS III C Y 34 $125.00 $4,250.0010 2511.507 GRANULAR FILTER C Y 17 $50.00 $850.0011 2573.502 STORM DRAIN INLET PROTECTION EACH 4 $150.00 $600.0012 2573.533 SEDIMENT CONTROL LOG TYPE BIOROLL L F 800 $3.00 $2,400.0013 2105.602 TEMPORARY ROCK CONSTRUCTION ENTRANCE EACH 2 $1,000.00 $2,000.0014 2575.504 EROSION CONTROL BLANKETS CATEGORY 3N S Y 6,150 $2.00 $12,300.0015 2575.505 SEEDING ACRE 1 $5,000.00 $6,500.0016 2575.508 SEED MIXTURE 21-111 LB 125 $10.00 $1,250.0017 2575.508 SEEDING MIXTURE 25-151 LB 70 $8.00 $560.0018 2575.508 SEED MIXTURE 33-261LB 30 $30.00 $900.00$214,250.00GRAND TOTAL BIDEngineer's EstimateUnit Price Total Price Unit Price Total Price Unit Price Total Price$20,000.00 $20,000.00 $24,417.00 $24,417.00 $37,440.00 $37,440.00$10,000.00 $10,000.00 $2,499.95 $2,499.95 $46,630.00 $46,630.00$69,000.00 $10,350.00 $29,866.67 $4,480.00 $31,660.00 $4,749.00$2.00 $136.00 $4.73 $321.64 $13.00 $884.00$33.00 $48,180.00 $16.34 $23,856.40 $19.60 $28,616.00$50.00 $35,000.00 $21.81 $15,267.00 $17.10 $11,970.00$40.00 $72,000.00 $49.86 $89,748.00 $33.75 $60,750.00$12,000.00 $12,000.00 $50,109.76 $50,109.76 $21,300.00 $21,300.00$100.00 $3,400.00 $184.49 $6,272.66 $80.00 $2,720.00$80.00 $1,360.00 $243.29 $4,135.93 $39.75 $675.75$150.00 $600.00 $292.02 $1,168.08 $319.00 $1,276.00$3.00 $2,400.00 $3.00 $2,400.00 $6.25 $5,000.00$1,250.00 $2,500.00 $3,682.04 $7,364.08 $2,420.00 $4,840.00$1.50 $9,225.00 $1.70 $10,455.00 $3.15 $19,372.50$500.00 $650.00 $600.00 $780.00 $3,100.00 $4,030.00$5.00 $625.00 $1.50 $187.50 $0.64 $80.00$5.00 $350.00 $4.50 $315.00 $4.35 $304.50$30.00 $900.00 $7.00 $210.00 $18.70 $561.00$229,676.00 $243,988.00 $251,198.75New Look Contracting, Inc. Meyer Contracting, Inc. Frattalone CompaniesPage 5 of 6K:\015819-000\Admin\Construction Admin\015819-000 CST Bid Tab_20201124.xlsx
Bid Tabulation2020 Rosemount Pond Maintenance ProjectCity of Rosemount Project No. 2021-02Bid Opening: Tuesday, November 24, 2020 at 10:00 a.m. Local TimeWSB Project No. 015819-000DENOTES CORRECTED FIGURELine # Mat. # Item Units Qty Unit Price Total Price1 2021.501 MOBILIZATION LS 1 $10,000.00 $10,000.002 2051.501 MAINTENANCE AND RESTORATION OF HAUL ROADS LS 1 $6,000.00 $6,000.003 2101.505 CLEARING ACRE 0.15 $10,000.00 $1,500.004 2105.504 GEOTEXTILE FABRIC TYPE 4 S Y 68 $5.00 $340.005 2105.507 POND EXCAVATION (LV) C Y 1,460 $30.00 $43,800.006 2105.507 POND EXCAVATION (SPECIAL 1) (LV) CY 700 $40.00 $28,000.007 2105.509 POND EXCAVATION (SPECIAL 2) (LV) TON 1,800 $45.00 $81,000.008 2105.601 DEWATERING LS 1 $12,000.00 $12,000.009 2511.507 RANDOM RIPRAP CLASS III C Y 34 $125.00 $4,250.0010 2511.507 GRANULAR FILTER C Y 17 $50.00 $850.0011 2573.502 STORM DRAIN INLET PROTECTION EACH 4 $150.00 $600.0012 2573.533 SEDIMENT CONTROL LOG TYPE BIOROLL L F 800 $3.00 $2,400.0013 2105.602 TEMPORARY ROCK CONSTRUCTION ENTRANCE EACH 2 $1,000.00 $2,000.0014 2575.504 EROSION CONTROL BLANKETS CATEGORY 3N S Y 6,150 $2.00 $12,300.0015 2575.505 SEEDING ACRE 1 $5,000.00 $6,500.0016 2575.508 SEED MIXTURE 21-111 LB 125 $10.00 $1,250.0017 2575.508 SEEDING MIXTURE 25-151 LB 70 $8.00 $560.0018 2575.508 SEED MIXTURE 33-261LB 30 $30.00 $900.00$214,250.00I hereby certify that this is an exact reproduction of bids received.Certified By: License No. 54301Date: November 24, 2020GRAND TOTAL BIDEngineer's EstimateUnit Price Total Price Unit Price Total Price$32,700.00 $32,700.00 $40,000.00 $40,000.00$5,800.00 $5,800.00 $32,500.00 $32,500.00$74,000.00 $11,100.00 $35,000.00 $5,250.00$5.50 $374.00 $12.00 $816.00$46.00 $67,160.00 $29.00 $42,340.00$46.00 $32,200.00 $47.00 $32,900.00$43.00 $77,400.00 $42.00 $75,600.00$4,600.00 $4,600.00 $15,000.00 $15,000.00$155.00 $5,270.00 $125.00 $4,250.00$100.00 $1,700.00 $125.00 $2,125.00$165.00 $660.00 $150.00 $600.00$3.65 $2,920.00 $4.00 $3,200.00$1,800.00 $3,600.00 $2,000.00 $4,000.00$2.80 $17,220.00 $2.15 $13,222.50$670.00 $871.00 $2,250.00 $2,925.00$2.00 $250.00 $1.00 $125.00$5.00 $350.00 $5.00 $350.00$8.00 $240.00 $45.00 $1,350.00$264,415.00 $276,553.50Veit & Company, Inc. Blackstone Contractors LLCPage 6 of 6K:\015819-000\Admin\Construction Admin\015819-000 CST Bid Tab_20201124.xlsx
SCALE IN FEET
0 200 400
K:\015819-000\Cad\Plan\015819-000-C-TITLE SHEET.dwg 11/10/2020 12:45:28 PMN
2020 ROSEMOUNT POND MAINTENANCE
CITY OF ROSEMOUNT
PROJECT LOCATION MAP
F/O
UGT
G
EXISTING PLAN SYMBOLS
PROPERTY LINES/RIGHT-OF-WAY
UTILITY EASEMENT
TREE LINE
SIGN
DECIDUOUS TREE
SHRUB
CONIFEROUS TREE
EXISTING UTILITY SYMBOLS
FIBER OPTIC CABLE
UNDERGROUND TELEPHONE
GAS LINE
CATV VAULT
POWER POLE
ELECTRIC BOX
CATCH BASIN
STORM APRON
CND
CTV
OH
UNDERGROUND CABLE
CABLE TV
OVERHEAD COMMUNICATIONS LINE
UGE
OHE
UNDERGROUND POWER
OVERHEAD POWER
UGEUNDERGROUND ELECTRIC
OHTOVERHEAD TELEPHONE
WATER MAIN
SANITARY SEWER
STORM SEWER
GATE VALVE
HYDRANT
SANITARY SEWER MANHOLE
STORM SEWER MANHOLE ST
s
COUNTY:DAKOTA
PROJECT LOCATION
THE SUBSURFACE UTILITY INFORMATION IN THIS PLAN IS UTILITY QUALITY LEVEL D. THIS UTILITY QUALITY LEVEL WAS DETERMINED ACCORDING TO THE
GUIDELINES OF CI/ASCE 38-02, ENTITLED "STANDARD GUIDELINES FOR THE COLLECTION AND DEPICTION OF EXISTING SUBSURFACE UTILITY DATA."
GOPHER ONE CALL TICKET NUMBER: 200841695
APPROVED BYSHEET NO.DATE
PLAN REVISIONS
ALL APPLICABLE FEDERAL, STATE, AND LOCAL LAWS AND ORDINANCES
WILL BE COMPLIED WITH IN THE CONSTRUCTION OF THIS PROJECT.
THIS PLAN SET CONTAINS 9 SHEETS
I HEREBY CERTIFY THAT THIS PLAN WAS PREPARED BY ME OR UNDER
MY DIRECT SUPERVISION, AND THAT I AM A DULY LICENSED PROFESSIONAL
ENGINEER UNDER THE LAWS OF THE STATE OF MINNESOTA.
LICENSE NUMBER:DATE:11/10/2020 54301
WILLIAM C ALMS, P.E.
SHEET
9
OF
WSB PROJ. NO. 015819-000
PROJECT LOCATION
1
THIS PLAN SET HAS BEEN PREPARED FOR:
CITY OF ROSEMOUNT
2875 145TH STREET WEST
ROSEMOUNT, MN 55068-4997
(651) 423-4411
A CALL TO GOPHER STATE ONE (651-454-0002)
IS REQUIRED A MINIMUM OF 48 HOURS PRIOR
TO PERFORMING ANY EXCAVATION.
EXCAVATION NOTICE SYSTEM
PLAN SET INDEX
GOVERNING SPECIFICATIONS
UTILITY INFORMATION
THE 2015 CITY OF ROSEMOUNT GENERAL SPECIFICATIONS & STANDARD DETAIL
PLATES FOR STREET AND UTILITY CONSTRUCTION AND THE 2018 EDITION OF
THE MINNESOTA DEPARTMENT OF TRANSPORTATION "STANDARD
SPECIFICATIONS FOR CONSTRUCTION" SHALL GOVERN.
ALL TRAFFIC CONTROL DEVICES SHALL CONFORM TO THE LATEST EDITION OF
THE MINNESOTA MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES, INCLUDING
THE LATEST FIELD MANUAL FOR TEMPORARY TRAFFIC CONTROL ZONE
LAYOUTS.
Sheet List Table
SHEET
NUMBER SHEET TITLE
1 TITLE SHEET
2 POND 1935 EXISTING CONDITIONS PLAN
3 POND 0589 EXISTING CONDITIONS PLAN
4 POND 1935 GRADING PLAN
5 POND 0589 GRADING PLAN
6 POND 1935 EROSION CONTROL AND
RESTORATION PLAN
7 POND 0589 EROSION CONTROL AND
RESTORATION PLAN
8 0589 EROSION CONTROL AND ACCESS PLAN
9 MISCELLANEOUS DETAILS
CITY PROJ. NO. 2021-02
BRIAN ERICKSON, P.E. - DIRECTOR OF PUBLIC WORKS / CITY ENGINEER DATE
145TH ST W
DIAMOND PATH WDAVENPORT AVEDAWSON CT
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2021 – xx
A RESOLUTION RECEIVING BIDS AND AWARDING CONTRACT
FOR 2021 STORM BASIN MAINTENANCE, CITY PROJECT 2021-02.
BE IT RESOLVED, by the City Council of the City of Rosemount, Minnesota, as follows:
1. All bids on construction of the 2021 Storm Basin Maintenance Project, City Project 2021-02,
are hereby received and tabulated.
2. Based on the Total Bid, the bid of Nadeau Companies of Hampton, MN in the amount of
$136,409.40 for the construction of said improvements is in accordance with the plans and
specifications and advertisement for bids and is the lowest responsible bid and shall be and
hereby is accepted.
3. The Mayor and Clerk are hereby authorized and directed to enter into a contract with said
bidder for the construction of said improvements for and on behalf of the City of Rosemount.
4. The City Clerk is hereby authorized and directed to return forthwith to all bidders the deposits
made with their bids, except that the deposit of the successful bidder and the next two lowest
bidders shall be retained until a contract has been executed.
ADOPTED this 1st day of December, 2020.
William H. Droste, Mayor
ATTEST:
Erin Fasbender, City Clerk