Loading...
HomeMy WebLinkAbout6.l. 132nd Street Improvements, City Project 465 Final Acceptance and Authorization of Final Payment TOTAL PROJECT COST Amount Original Contract$ 288,075.20 CO #1$ 34,432.90 CO #2$ 8,626.35 Final Quantity Adjustments$ (15,059.90) TOTAL COST$ 316,074.55 EXECUTIVE SUMMARY City Council Meeting: January 19, 2021 nd AGENDA ITEM: 132 Street Improvements, City Project AGENDA SECTION: 465 Final Acceptance and Authorization Consent of Final Payment PREPARED BY: Brian Erickson, PE, Director of Public AGENDA NO. 6.l. Works / City Engineer ATTACHMENTS: Resolution, Engineer’s Recommendation, Final Payment APPROVED BY: LJM Application RECOMMENDED ACTIONS: Resolution to Approve Final Payment to Friedges nd Contracting Co., Inc. for 132 Street Improvements, City Project 465 and Accepting the Improvements for Perpetual Maintenance BACKGROUND On September 5, 2017, the City Council approved a contract with Friedges Contracting Co., Inc. for the nd improvement of 132 Street between Minnesota Highway 3 and Dodd Boulevard. The scope of work included installation of utilities and paving the street surface. Unfortunately, as Friedges began work concerns about the depth of excavation and utility conflicts presented problems that required significant additional coordination. This effort resulted in a substantial delay. The project was finally completed, and the wear course of pavement installed in 2020. DISCUSSION Through the course of construction there were two contract modifications issued and the following table shows the final cost for the work completed which is 9.7% higher than the original contract amount. At this time, Friedges Contracting Co., Inc. has completed all the improvements as detailed in the contract and WSB and Associates has recommended acceptance of the work. Final payment is ready to be issued pending receipt of final administrative paper work. RECOMMENDATION Staff recommends that the City Council adopt the attached resolution accepting the improvements and nd authorizing final payment to Friedges Contracting Co., Inc. for 132 Street Improvements, City Project c:\\users\\jab\\appdata\\local\\temp\\6.l. 132nd street improvements, city project 465 final acceptance and author_631216\\6.l. 132nd street improvements, city project 465 final acceptance an.docx 465. 2 CITY OF ROSEMOUNT DAKOTA COUNTY, MINNESOTA RESOLUTION 2021 – 06 A RESOLUTION ACCEPTING PUBLIC IMPROVEMENT ND FOR 132 STREET IMPROVEMENTS CITY PROJECT 465 WHEREAS, Friedges Contracting Co., Inc. has completed the required construction as per the scope of the contract, and; WHEREAS, the City received a concurrence from WSB and Associates that the work has been completed in accordance with the approved plans and specifications and finds the improvements acceptable, and; WHEREAS, the contractor is compiling all necessary administrative requirements to close out the contract. NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ROSEMOUNT, MINNESOTA: 1. The improvements completed under said agreement are hereby accepted for perpetual maintenance and ownership. 2. Final payment to the contractor is authorized upon receipt of all required administrative paperwork. th ADOPTED this 19 day of January, 2021. William H. Droste, Mayor ATTEST: Erin Fasbender, City Clerk K:\01928-710\Admin\Construction Admin\Pay Vouchers\Final Payment\2021.01.12 Memo - Project Closeout.docx 540 GATEWAY BLVD | BURNSVILLE, MN | 55337 | 952.737.4660 | WSBENG.COM Memorandum To: Brian Erickson, PE, Public Works Director/City Engineer City of Rosemount From: Tim Hanson, PE, Senior Project Manager Date: January 12, 2021 Re: 132nd Street Improvements City Project No. 465 WSB Project No. 01928-71 The City of Rosemount is in the process of closing out and accepting the street and utility improvements for the 132nd Street Improvement Project. The improvements, consisting of sanitary sewer extension, watermain extension, storm sewer improvements, sidewalk improvements and street construction were designed and inspected by WSB in accordance with the City’s Standard Specifications and Engineering Guidelines. The public improvements were constructed by Friedges Contracting Co., Inc. Improvements were constructed in the summer of 2019 and 2020. Friedges Contracting has submitted most of the paperwork necessary for final payment including IC 134 forms, contractor affidavit, Mechanic’s Lien Waivers, Maintenance Warranty Bond and the signed final pay voucher for final payment. Surety for Payment is being processed by the contractor. The final project cost is $316,074.55. Final Payment amount is $51,445.74. WSB recommends approval and acceptance of the public improvements and final payment to Friedges Contracting Co., Inc. as indicated. Please contact me at thanson@wsbeng.com or 612-219-2553 with any comments or questions. Sincerely, WSB Timothy Hanson, PE Senior Project Manager