EXECUTIVE SUMMARY
Utility Commission Meeting: January 25, 2021
AGENDA SECTION:
AGENDA ITEM: City Project Update Executive Director’s
Report
PREPARED BY: Brian Erickson, P.E. Director of Public Works
AGENDA NO. 8.a.
/ City Engineer
ATTACHMENTS: None APPROVED BY: BLE
RECOMMENDED ACTION: None, informational only
BACKGROUND
The 2020 construction season has wrapped up for the season and this year has seen a
significant amount of construction throughout the city. The following list is the current and
planned City of Rosemount projects. There are additional developments that are in early
stages of the process and those will be added as appropriate. Changes since the last report
are shown as strike out for deletions and underlined for additions as well as a bar along the
left margin to indicate the changes.
2019 Street Improvement Project – Work is nearly complete with boulevard
restoration as the primary remaining item. No further work is anticipated in 2020. The
scope includes mill and overlay or reclamation of:
Chippendale Avenue from 145th Street W to 160th Street W
Dodd Boulevard from Shannon Parkway to Chippendale Avenue
151st Street W from Shannon Parkway to Chippendale Avenue
Crestone Ave, Claret Ave and Cimarron Ave from CSAH 42 to 151st Street W
2021 Street Improvement Project – Scope includes mill and overlay or reclaim of:
Covington Avenue
Colorado Avenue
th
Upper 149 Street W from Crandall Avenue to Colorado Avenue
Darling Path from Danbury Avenue to the southern curve
th
156 Street W from Darling Path to Shannon Parkway
th
Upper 156 Street W from Darling Path to Danville Avenue
th
156 Court W.
Dapple Court
Dapple Circle
th
157 Court W.
th
157 Street W.
thth
Danville Avenue from 156 Street W.to 156 Court W.
Cumberland Avenue
Crocus Avenue
Crocus Court
C:\\Users\\jab\\AppData\\Local\\Temp\\8.a. Project Update_632169\\8.a. Project Update.docxG:\\MEETINGS\\UTILITY COMMISSION\\UC Items and
Packets\\2021\\20210125\\8.a. Project Update.docx
Crystal Path from Danville Avenue to Shannon Parkway
Crystal Court
The design is complete and the project is currently out for bid with a bid opening date
of February 22, 2021.Design is currently in progress with an anticipated bid date of
February 9, 2021. Construction is planned for 2021.
Autumn Path – Scope includes construction of utilities and paving from Bonaire Path
north approximately 2,500 feet. Construction started in October with utility installation
complete this year. Road paving will be completed in 2021; however, there will be
th
gravel to allow access to the Bella Vista 7 subdivision. Construction is complete for
the year. The portion of Autumn Path between Bonaire Path and Aulden Ave
remaining closed to traffic through the winter.
Biscayne Ave – Scope includes construction of utilities and paving between Boulder
th
Trail and 160 Street (CSAH 46). Extension of sanitary sewer will provide service to
the Biscayne Business Park on the southern end of the project. Final grading and
stormwater features completed. Final bituminous wear course will be done in 2021.
No truck traffic will be allowed until the final bituminous course is place.
Bonaire Path – Scope includes construction of utilities and paving between Akron
Avenue and Anderson Drive. Additionally, the installation of crossing arms at the
Union Pacific Railroad intersection are in the scope of the project and planned for
2020. Ultimately, the city will request that this intersection become a quiet zone (i.e.
no train horns). Wear course and construction is anticipated to be completed in 2021;
however, that will hinge on Union Pacific completing the necessary crossing work.
Final design for rail improvements was approved by City Council at the February 4,
2020 meeting. Draft construction agreement was finally provided by UP on 12/3/2020.
The City Attorney has provided comments and feedback given to UP. Actual
construction work by UP remains unscheduled at this time. Because of the significant
delays by Union Pacific no work is anticipated in 2020. Additional communication with
both MnDOT and other Union Pacific staff is being done as well. Staff has been in
contact with the Federal Railroad Administration regarding application for a quiet zone
(QZ). Because of the design, the QZ application is expected to be approved.
Connemara Trail Extension – Scope includes construction of utilities and paving
from Akron Avenue east approximately 1,300 feet. Contract was awarded and work is
being planned for 2021 due to the significant workload. Some additional work is being
coordinated with the parcel to the east to assist with future development.
Dunmore Storm Lift Station – Scope includes the construction of a stormwater lift
station in the Dunmore subdivision and connection to existing force main.
Construction is completed. Initial startup and control programming has been
performed. Restoration is underway.
Shannon Pond Outlet Feasibility Study – Scope includes reviewing potential routes
for stormwater outlet at Shannon Pond. Because of the land locked location outlet will
be a significant undertaking. Initial study work was received this summer. Information
from this study will be used to establish future improvements necessary to reduce the
potential for structure flooding. Staff and consultant are coordinating with additional
2
authorities regarding some of the potential options provided in the study. Updates will
be provided to the Utility Commission at future meetings as needed.
The following list is the current and planned developer projects.
Ardan Place – Scope includes the construction of utilities and both public and private
streets from Bonaire Path and Autumn Path as well 79 single family residential (SFR)
and 137 townhomes.
Autumn Fields – Scope includes the development of approximately 435 acres of
University of Minnesota, Outreach, Research and Education Park (UMore Park). This
property is planned to have a mixture of single family, multi-family and commercial
properties. It is located west of Dakota County Technical College (DCTC) and south
of CSAH 42. Current comprehensive planning has accounted for this expansion of the
utility systems.
th
Bella Vista 6 – Scope includes construction of utilities and paving from Aulden
Avenue to the cul-de-sac approximately 850’ north east as well as 19 single family
residential (SFR) lots of a planned total 158. In addition, there is a temporary sanitary
sewer lift station that will be installed until trunk sewer is extended at a future date.
Utilities and base course are in place and the lift station construction is complete with
minor punch list items to be corrected. Wear course delayed until 2021 due to
st
construction to the east of 131 Court.
th
Bella Vista 7 – Scope includes construction of utilities and paving from a temporary
connection to the Autumn Path extension (see above) west approximately 1500 feet
as well as 26 SFR lots of a planned total 158. This is the final phase of this
development. Construction of utilities is complete, and the developer has completed
paving of the base course for 2020.
Biscayne Business Park – Scope includes construction of utilities and paving from
Biscayne Avenue to the cul-de-sac approximately 750’ west as well as 8 commercial
lots. One building is under construction. Paving will be donecompleted in 2020.
st
Caramore Crossing 1 – Scope includes construction of utilities and paving from
Akron Avenue and from Bonaire Path as well as 82 SFR lots of a planned total 177.
This project is in the initial construction stage. Developer has installed utilities from
Akron and is currently working on site grading.
nd
Dunmore 2 – Scope includes construction of utilities and paving from Caffery Court
as well as 25 SFR lots of a planned total 87. Wear course will be installed in 2020 with
exact dates to be established. Contractor will be required to make repairs to the
stormwater ponds due to poor dewatering practices.
st
Emerald Isle 1 – Scope includes construction of utilities and paving as well as 40
SFR lots of a planned total 151. Grading work and initial utility construction is
complete. Contractor has paved the base course for 2020.
nd
Emerald Isle 2 – Scope includes construction of utilities and paving as well as 57
SFR lots of a planned total of 151. Possible extension of Connemara and associated
3
utilities are being considered. City Council continued the public hearing on this project
until February 2, 2021 in order to address concerns regarding stormwater ponding
easements related to the CSAH 42/Akron Ave Signal Project.Approval is scheduled for
January 19, 2021.
nd
Harmony Parkview 2 – Scope includes construction of utilities and paving as well
as 26 townhomes. Utilities will be city owned and the streets are private. This project
will also fill temporary stormwater ponding on the east side of MN Hwy 3. Filling of the
temporary ponding is complete. Utility construction has been completed and
townhome construction is underway.
nd
Harmony Villas 2 – Scope includes construction of utilities and paving as well as 26
townhomes. Utilities are city owned and the streets are private. Utility construction is
complete. Site corrections and building construction is underway.
rd
Meadow Ridge 3 – Scope includes construction of utilities, paving and a temporary
sanitary sewer lift station as well as 28 SFR lots of a planned total 154. This project is
complete for the season. Lift station will be coming on line before home construction
can be started.
th
Meadow Ridge 4 – Scope includes construction of utilities and paving as well as 63
SFR lots of a planned total 154. This is the final phase of this development.
Construction is planned for 2021.
Morrison (Downtown redevelopment) – Scope includes redevelopment of the area
west of TH 3 in proximity to Shenanigans. Mixed commercial and apartments are
planned for this area. Utility connections and minor corrections completed. Developer
is currently working on building construction.
th
Prestwick 17 – Scope includes construction of utilities and paving, including the
completion of Addison Avenue to the east property line as well as 26 townhomes.
Utilities will be city owned and the streets are private. Wear course was installed in
2020.
th
Prestwick 18 – Scope includes construction of utilities and paving as well as 40
townhomes. Utilities will be city owned and the streets are private. Utilities have been
installed. Wear course was installed in 2020.
th
Prestwick 20 – Scope includes construction of utilities and paving as well as 27 SFR
lots. This is the final phase of this development on the west side of Akron Avenue.
Construction is underway and planned for completion this year, with wear course
planned for 2021.
st
Prestwick 21 – Scope includes construction of utilities and paving as well as 24
townhomes. Utilities will be city owned and the streets are private. Construction is
underway and planned for completion this year, with wear course planned for 2021.
nd
Prestwick 22 – Scope includes construction of utilities and paving as well as 64
townhomes. Utilities will be city owned and the streets are private. Construction is
underway and planned for completion this year, with wear course planned for 2021.
4
Rosemount Woods Expansion – Scope includes construction of 39 additional
manufactured home sites as well as construction of private utility extensions for those
sites. This project is currently under construction. Wear course paving on Brazil
Avenue is complete for 2020.
The following is the list of Dakota County and MnDOT projects.
CR 73 (Akron Ave) – Scope includes the reconstruction of Akron Avenue from
Bonaire Path to the Rosemount city limit. It also includes the construction of a trail
under pass near Flint Hills Soccer Complex. Finally, it includes pavement
thst
rehabilitation for 124 Court and 121 Street. The entire length of Akron has been
paved and restoration and striping are planned to be completed prior to winter. Final
stth
paving on 121 Street and 124 Court was completed. Greenway trail underpass is
nearing completion.
Roundabout Connemara Trail/Diamond Path – Scope preliminary engineering for
the construction of a roundabout at this intersection. This project is planned for
construction in 2022. Preliminary design work nearing completion.
CSAH 42/CR 73 (Akron Ave) Signal – Scope calls for installation of a traffic signal at
the intersection of CSAH 42 and CR 73 (Akron Ave) to address the increase in traffic
at this intersection. This project is planned for construction in 2021. Final design work
is complete, and Dakota County has the project out for bids currently. Design will
include an extension of water main south to service possible future development. City
of Rosemount, Dakota County, Dakota County Technical College and the University of
Minnesota continue to work in partnership to complete this project. Review of possible
road and water main extension is in progress to assist with potential future
development.
CSAH 42 Visioning Study – This is a study that will look at nearly the entire length of
CSAS 42 starting at the western county line (Burnsville) and ending at MN Trunk
Highway 52. Future open houses and public engagement opportunities will be
promulgated as they are established. At this time most public engagement will be via
on-line comments and updates.
CSAH 46 Corridor Study and Preliminary Engineering – This is a study that will
look at the section of CSAH 46 from Minnesota Trunk Highway 3 to CSAH 48 in
Coates. The scope of work anticipated is right of way acquisition to support expanding
the highway to a divided four-lane. This is a high priority project for Dakota County
and since a portion of this is within Rosemount city limits a portion of the cost would be
carried by the city. This study will assist with quantifying those costs. Initial survey
work is completed.
Mississippi River Greenway – Scope includes the reconstruction of a portion of Pine
Bend Trail to allow for the completion of the Dakota County trail connection from St.
Paul to Hastings. This work will be funded by Dakota County. Additionally, the section
of Pine Bend Trail between TH 55 and the reconstructed section will be reclaimed at
city cost. This work is planned for 2021. Dakota County is in the process of securing
agreements with the rail road to allow for the trail crossing.
5
TH 55 Safety Improvements – Scope includes improvements along Minnesota Trunk
Highway 55 (TH 55) by adding a left turn lane to Doyle Path and increasing the truck
acceleration lane at the rail road crossing. The Toward Zero Deaths (TZD) program is
leading a working group for this project.