E X E C U T I V E S U M M A R Y
Utility Commission Meeting: February 22, 2021
AGENDA ITEM: City Project Update
AGENDA SECTION:
Executive Director’s
Report
PREPARED BY: Brian Erickson, P.E. Director of Public Works
/ City Engineer AGENDA NO. 8.a.
ATTACHMENTS: None APPROVED BY: BLE
RECOMMENDED ACTION: None, informational only
BACKGROUND
The 2021 construction season preparation underway and this year will see a significant
amount of work being done. The following list is the current and planned City of Rosemount
projects. There are additional developments that are in early stages of the process and those
will be added as appropriate. Changes since the last report are shown as strike out for
deletions and underlined for additions as well as a bar along the left margin to indicate the
changes. Minor grammatical corrections and updates will not be highlighted.
• 2019 Street Improvement Project – Work is nearly complete with boulevard
restoration as the primary remaining item. This will be the final report for this project.
No further work is anticipated in 2020. The scope includes mill and overlay or
reclamation of:
• Chippendale Avenue from 145th Street W to 160th Street W
• Dodd Boulevard from Shannon Parkway to Chippendale Avenue
• 151st Street W from Shannon Parkway to Chippendale Avenue
• Crestone Ave, Claret Ave and Cimarron Ave from CSAH 42 to 151st Street W
• 2021 Street Improvement Project – Scope includes mill and overlay or reclaim of:
• Covington Avenue
• Colorado Avenue
• Upper 149th Street W from Crandall Avenue to Colorado Avenue
• Darling Path from Danbury Avenue to the southern curve
• 156th Street W from Darling Path to Shannon Parkway
• Upper 156th Street W from Darling Path to Danville Avenue
• 156th Court W.
• Dapple Court
• Dapple Circle
• 157th Court W.
• 157th Street W.
• Danville Avenue from 156th Street W.to 156th Court W.
• Cumberland Avenue
• Crocus Avenue
2
• Crocus Court
• Crystal Path from Danville Avenue to Shannon Parkway
• Crystal Court
The design is complete and the project is currently out for bid with a bid opening date
of February 22, 2021. Construction is planned for 2021.
• Autumn Path – Scope includes construction of utilities and paving from Bonaire Path
north approximately 2,500 feet. Construction started in October with utility installation
complete in 2020. this year. Road paving will be completed in 2021; however, there
will be gravel to allow access to the Bella Vista 7 th subdivision. Construction is
complete for the year. The portion of Autumn Path between Bonaire Path and Aulden
Ave remains closed to traffic through the winter.
• Biscayne Ave – Scope includes construction of utilities and paving between Boulder
Trail and 160th Street (CSAH 46). Extension of sanitary sewer will provide service to
the Biscayne Business Park on the southern end of the project. Final grading and
stormwater features completed. Final bituminous wear course will be done in 2021.
No truck traffic will be allowed until the final bituminous course is place.
• Bonaire Path – Scope includes construction of utilities and paving between Akron
Avenue and Anderson Drive. Additionally, the installation of crossing arms at the
Union Paci fic Railroad intersection are in the scope of the project and planned for
2020. Ultimately, the city will request that this intersection become a quiet zone (i.e.
no train horns). Wear course and construction is anticipated to be completed in 2021;
however, that will hinge on Union Pacific completing the necessary crossing work.
Final design for rail improvements was approved by City Council at the February 4 ,
2020 meeting. Draft construction agreement was finally provided by UP on December
3, 2020. The City Attorney has provided comments and feedback given to UP. Actual
construction work by UP remains unscheduled at this time. Additional communication
with both MnDOT and other Union Pacific staff is being done as well. Staff has been
in contact with the Federal Railroad Administration regarding application for a quiet
zone (QZ). Because of the design, the QZ application is expected to be a pproved.
• Connemara Trail Extension – Scope includes construction of utilities and paving
from Akron Avenue east approximately 1,300 feet. Contract was awarded and work is
being planned for 2021 due to the significant workload. Some additional work is being
coordinated with the parcel to the east to assist with future development in Emerald
Isle.
• Dunmore Storm Lift Station – Scope includes the construction of a stormwater lift
station in the Dunmore subdivision and connection to existing force main.
Construction is completed. Initial startup and control programming has been
performed. Restoration is underway. This will be the final report for this project.
• Shannon Pond Outlet Feasibility Study – Scope includes reviewing potential routes
for stormwater outlet at Shannon Pond. Because of th e land locked location,
establishing an outlet will be a significant undertaking. Initial study work was received
this summer. Information from this study will be used to establish future improvements
necessary to reduce the potential for structure flooding. Staff and consultant are
coordinating with additional authorities regarding some of the potential options
3
provided in the study. Updates will be provided to the Utility Commission at future
meetings as needed.
The following list is the current and planned developer projects.
• Ardan Place – Scope includes the construction of utilities and both public and private
streets from Bonaire Path and Autumn Path as well 79 single family residential (SFR)
and 137 townhomes.
• Autumn Fields – Scope includes the development of approximately 435 acres of
University of Minnesota, Outreach, Research and Education Park (UMore Park). This
property is planned to have a mixture of single family, multi -family and commercial
properties. It is located west of Dakota County Technical College (DCTC) and south
of CSAH 42. Current comprehensive planning has accounted for this expansion of the
utility systems.
• Bella Vista 6th – Scope includes construction of utilities and paving from Aulden
Avenue to the cul-de-sac approximately 850’ north east as well as 19 SFR lots of a
planned total 158. In addition, there is a temporary sanitary sewer lift station that will
be installed until trunk sewer is extended at a future date. Utilities and base course
are in place and the lift station construction is complete with minor punch list items to
be corrected. Wear course delayed until 2021 due to construction to the east of 131st
Court.
• Bella Vista 7th – Scope includes construction of utilities and paving from a temporary
connection to the Autumn Path extension (see above) west approximately 1500 feet
as well as 26 SFR lots of a planned total 158. This is the final phase of this
development. Construction of utilities is complete, and the developer has completed
paving of the base course for 2020.
• Biscayne Business Park – Scope includes construction of utilities and paving from
Biscayne Avenue to the cul -de-sac approximately 750’ west as well as 8 commercial
lots. One building is under construction. Paving completed in 2020. This will be the
final report for this project.
• Caramore Crossing 1st – Scope includes construction of utilities and paving from
Akron Avenue and from Bonaire Path as well as 82 SFR lots of a planned total 177.
This project is in the initial construction stage. Developer has installed utilities from
Akron and is currently working on site grading.
• Dunmore 2nd – Scope includes construction of utilities and paving from Caffery Court
as well as 25 SFR lots of a planned total 87. Wear course will be installed in 2020
2021 with exact dates to be established. Contractor will be required to make repairs to
the stormwater ponds due to poor dewatering practices.
• Emerald Isle 1st – Scope includes construction of utilities and paving as well as 40
SFR lots of a planned total 151. Grading work and initial utility construction is
complete. Contractor has paved the base course for 2020 .
4
• Emerald Isle 2nd – Scope includes construction of utilities and paving as well as 57
SFR lots of a planned total of 151. Possible extension of Connemara Trail and
associated utilities are being considered. City Council approved this project at the
February 2, 2021 meeting.continued the public hearing on this project until February 2,
2021 in order to address concerns regarding stormwater ponding easements related to
the CSAH 42/Akron Ave Signal Project.
• Harmony Parkview 2nd – Scope includes construction of utilities and paving as well
as 26 townhomes. Utilities will be city owned and the streets are private. This project
will also fill temporary stormwater ponding on the east side of MN Hwy 3. Filling of the
temporary ponding is complete. Utility construction has been completed and
townhome construction is underway.
• Harmony Villas 2nd – Scope includes construction of utilities and paving as well as 26
townhomes. Utilities are city owned and the streets are private. Utility construction is
complete. Site corrections and building construction is underway.
• Meadow Ridge 3rd – Scope includes construction of utilities, paving and a temporary
sanitary sewer lift station as well as 28 SFR lots of a planned total 154. This project is
complete for the season. Lift station will be coming on line before home construction
can be started. Final wear course will be paved in 2021.
• Meadow Ridge 4th – Scope includes construction of utilities and paving as well as 63
SFR lots of a planned total 154. This is the final phase of this development.
Construction is planned for 2021.
• Morrison (Downtown redevelopment) – Scope includes redevelopment of the area
west of TH 3 in proximity to Shenanigans. Mixed commercial and apartments are
planned for this area. Utility connections and minor corrections completed. Developer
is currently working on building construction.
• Prestwick 17th – Scope includes construction of utilities and paving, including the
completion of Addison Avenue to the east property line as well as 26 townhomes.
Utilities will be city owned and the streets are private. Wear course was installed in
2020.
• Prestwick 18th – Scope includes construction of utilities and paving as well as 40
townhomes. Utilities will be city owned and the streets are private. Utilities have been
installed. Wear course was installed in 2020.
• Prestwick 20th – Scope includes construction of utilities and paving as well as 27 SFR
lots. This is the final phase of this development on the west side of Akron Avenue.
Construction is underway and planned for completion this year, with wear course
planned for 2021.
• Prestwick 21st – Scope includes construction of utilities and paving as well a s 24
townhomes. Utilities will be city owned and the streets are private. Construction is
underway and planned for completion this year , with wear course planned for 2021.
5
• Prestwick 22nd – Scope includes construction of utilities and paving as well as 64
townhomes. Utilities will be city owned and the streets are private. Construction is
underway and planned for completion this year , with wear course planned for 2021.
• Rosemount Woods Expansion – Scope includes construction of 39 additional
manufactured home sites as well as construction of private utility extensions for those
sites. This project is currently under construction. Wear course paving on Brazil
Avenue is complete for 2020.
The following is the list of Dakota County and MnDOT projects.
• CR 73 (Akron Ave) – Scope includes the reconstruction of Akron Avenue from
Bonaire Path to the Rosemount city limit. It also includes the construction of a trail
under pass near Flint Hills Soccer Complex. Finally, it includes pavement
rehabilitation for 124th Court and 121st Street. The entire length of Akron has been
paved and restoration and striping are planned to be completed prior to winter. Final
paving on 121st Street and 124th Court was completed. Greenway trail underpass is
nearing completion.
• Roundabout Connemara Trail/Diamond Path – Scope preliminary engineering for
the construction of a roundabout at this intersection. This project is planned for
construction in 2022. Preliminary design work nearing completion.
• CSAH 42/CR 73 (Akron Ave) Signal – Scope calls for installation of a traffic signal at
the intersection of CSAH 42 and CR 73 (Akron Ave) to address the increase in traffic
at this intersection. This project is planned for construction in 2021. Dakota County
has awarded this project and construction will begin in the spring.Final design work is
complete, and Dakota County has the project out for bids currently. Design will
includes an extension of water main south to service possible future development.
City of Rosemount, Dakota County, Dakota County Technical College and the
University of Minnesota continue to work in partnership to complete this project.
Review of possible road and water main extension is in progress to assist with
potential future development.
• CSAH 42 Visioning Study – This is a study that will look at nearly the entire length of
CSAS 42 starting at the western county line (Burnsville) and ending at MN Trunk
Highway 52. Future open houses and public engagement opportunities will be
promulgated as they are established. At this time most public engagement will be via
on-line comments and updates.
• CSAH 46 Corridor Study and Preliminary Engineering – This is a study that will
look at the section of CSAH 46 from Minnesota Trunk Highway 3 to CSAH 48 in
Coates. The scope of work anticipated is right of way acquisition to support expanding
the highway to a divided four -lane. This is a high priority project for Dakota County
and since a portion of this is within Rosemount city limits a portion of the cost would be
carried by the city. This study will assist with quantifying those costs. Initial survey
work is completed.
• Mississippi River Greenway – Scope includes the reconstruction of a portion of Pine
Bend Trail to allow for the completion of the Dakota County trail connection from St.
6
Paul to Hastings. This work will be funded by Dakota County. Additionally, the section
of Pine Bend Trail between TH 55 and the reconstructed section will be reclaimed at
city cost. This work is planned for 20212022. Dakota County is in the process of
securing agreements with the rail road to allow for the trail crossing.
• TH 55 Safety Improvements – Scope includes improvements along Minnesota Trunk
Highway 55 (TH 55) by adding a left turn lane to Doyle Path and increasing the truck
acceleration lane at the rail road crossing . The Toward Zero Deaths (TZD) program is
leading a working group for this project.