EXECUTIVE SUMMARY
City Council Meeting: October 19, 2021
AG ENDA ITEM: Connemara Storm Interceptor Extension, City
Project 2021-06: Approve Change Order 1
AGENDA SECTION:
Consent
PREPARED BY: Nick Egger, PE, Public Works Director AGENDA NO. 6.j.
ATTACHMENTS: Ryan Contracting Bid Prices APPROVED BY: LJM
RECOMMENDED ACTION: Motion to Approve Change Order 1 for Connemara Trail
Trunk Storm Sewer Extension
BACKGROUND
The Connemara Trail Trunk Storm Sewer extension project was awarded on September 21st. Since then
and due to an updated understanding of the intentions for timing on the remainder of the Emerald Isle
development, it has become apparent that lengthening the extension beyond the eastern property line of
Emerald Isle into the adjacent Bester property would be prudent.
DISCUSSION
The original plans and project scope would have the trunk storm sewer pipe being constructed to about 38
feet shy of the west side of the Emerald Isle/Bester property line. However, in order to get sufficiently
away from the remaining footprint of pending development activity within Emerald Isle, the staff is
proposing to carry the pipe across the property line by approximately 50 feet into the Bester property.
Staff has connected with the Bester’s, and they are amenable to allowing the work to enter their property.
As part of the process for the City obtaining permission for the work to occur on the Bester property, staff
would develop the necessary easement documents and exhibits for Bester’s approval.
As with the funding for the original contract being sourced from the Stormwater Trunk Fund, the costs of
the change order work would also be paid from that fund. The estimated cost of the Change Order, based
on original contract bid prices, is $52,264, which represents just shy of a 9% increase to the overall
contract value to a new total of $644,492, and would bring the anticipated total project construction cost
to $744,388. Below is an amended summary of total anticipated project expenses.
Item Estimate
Ryan Contracting
Bid Prices
Storm Trunk 520,608$ 592,228$
Change Order No. 1 -52,264$
Contingency (5%)26,030$ 32,225$
Construction Total 546,638$ 676,717$
Indirect Costs (10%)54,664$ 67,672$
Total Project Cost 601,302$ 744,388$
AMENDED TOTAL PROJECT COST ESTIMATE
2
RECOMMENDATION
Staff is recommending the approval of a change order to add an estimated 88 additional lineal feet of 54”
reinforced concrete storm sewer pipe to carry the trunk extension across the Emerald Isle/Bester property
line east into the Bester property.
WSB Project:Connemara Trail - Emerald Isle Extension - Change Order # 1
Project Location:City of Rosemount
City Project No.:2021-06
WSB Project No:18074-000
1 2021.501 MOBILIZATION (5% MAXIMUM)L S 25,000.00$ 0 -$
2 2104.502 SALVAGE TYPE III BARRICADE EACH 50.00$ 0 -$
3 2106.507 SELECT GRANULAR EMBANKMENT C Y 4.00$ 700 2,800.00$
4 2123.610 STREET SWEEPER (WITH PICKUP BROOM)HOUR 85.00$ 0 -$
5 2503.503 54" RC PIPE SEWER DES 3006 CLASS V L F 550.00$ 88 48,400.00$
6 2503.602 CONNECT TO EXISTING STORM SEWER EACH 15,000.00$ 0 -$
7 2503.602 CONSTRUCT BULKHEAD EACH 500.00$ 0 -$
8 2503.603 VIDEO TAPE PIPE SEWER LF 3.00$ 88 264.00$
9 2506.502 CASTING ASSEMBLY EACH 1,000.00$ 0 -$
10 2506.503 CONSTRUCT DRAINAGE STRUCTURE DESIGN 84-4020 L F 850.00$ 0 -$
11 2506.503 CONSTRUCT DRAINAGE STRUCTURE DESIGN 48-4020 L F 190.00$ 0 -$
12 2554.503 INSTALL SALVAGED TYPE III BARRICADE EACH 200.00$ 0 -$
13 2573.501 STABILIZED CONSTRUCTION EXIT L S 500.00$ 0 -$
14 2573.503 SILT FENCE, TYPE MS L F 1.00$ 600 600.00$
15 2573.503 SEDIMENT CONTROL LOG TYPE WOOD FIBER L F 2.00$ 0 -$
16 2574.508 FERTILIZER, TYPE 1 POUND 0.60$ -$
17 2575.505 SEEDING ACRE 400.00$ -$
18 2575.508 SEED, MIXTURE 22-111 POUND 2.00$ -$
19 2575.509 MULCH MATERIAL, TYPE 3 TON 175.00$ 0 -$
20 2575.509 MULCH MATERIAL, TYPE 1 TON 100.00$ 2 200.00$
CONSTRUCTION TOTAL 52,264.00$
TOTAL 52,264.00$
ITEM NO.
MN/DOT
SPECIFICATI
ON NO.
DESCRIPTION UNIT UNIT PRICE
PROJECT
ESTIMATED
TOTAL
QUANTITY
ESTIMATED TOTAL
COST
OPINION OF PROBABLE COST