HomeMy WebLinkAbout6.h. Award Contract and Enter Cooperative Agreement for the Boulder Ave Extension Project, City Project 2022-02\\rsm-file\common\city clerk\agenda items\approved items\6.h. award contract and enter cooperative agreement for the boulder ave extension project, city
project 2022-02.docx
EXECUTIVE SUMMARY
City Council Meeting: October 4, 2022
AGENDA ITEM: Award Contract and Enter Cooperative
Agreement for the Boulder Ave Extension
Project, City Project 2022-02
AGENDA SECTION:
Consent
PREPARED BY: Brian Erickson, PE, City Engineer AGENDA NO. 6.h.
ATTACHMENTS: Resolutions, MnDOT Agreement, Bid
Tabulation, Letter of Recommendation,
Location Map
APPROVED BY: LJM
RECOMMENDED ACTIONS:
1. Adopt a Resolution Accepting the Bids and Awarding the Contract for the Boulder
Avenue Extension Project, City Project 2022-02.
2. Adopt a Resolution Authorizing Rosemount to Enter into a Cooperative Agreement
with MnDOT
BACKGROUND
The Boulder Avenue Street and Utility Extension Project, City Project 2022-02, is proposed to construct
approximately 1,250 feet of new road and utilities in conjunction with the improvements being
constructed by Seefried to the north as they complete the Home Depot materials distribution facility. In
addition, this project would construct a right turn lane along the east side of Minnesota Trunk Highway 3
along with restriping to provide a left turn lane in the vicinity of Canada Court. Finally, the project would
also extend the city’s trunk storm sewer along this corridor.
The extension of Boulder Avenue from Minnesota Trunk Highway 3 (TH 3) to the east and then north to
connect the portion of Boulder being constructed by Seefried will eliminate a long dead-end road. This
project also provides infrastructure to prepare for future development in the area of TH 3 and Dakota
County Highway 46 which has seen increased interest of late.
WSB and Associates, Inc. completed the design and prepared an estimate of costs. Additionally,
coordination with MnDOT was required for construction of the turn lanes along TH 3. One final step for
the MnDOT approvals includes the execution of a cooperative agreement for the construction of the turn
lanes. This agreement has been reviewed by the City Attorney. There are some items noted as future city
maintenance including municipal utilities (water, sewer, storm water) and any installed sidewalks.
The project was bid on September 13, 2022 and at that time there were 15 bidders. The table below shows
the bid summary along with the engineer’s estimate. The lowest bid was $88,920.94 or 4.8% below the
engineer’s estimate and the two lowest bids had a difference of $20,991.58 or 1.1%.
2
Cost and Funding
The following table shows the total project costs using the low bid.
The following table shows the anticipated funding breakdown by funding type.
Work Item Low Bid
Surface Improvements 490,771.31$
Sanitary Sewer Improvements 247,666.00$
Watermain Improvements 150,871.00$
Storm Sewer Improvments 652,580.00$
TH 3 Improvements 211,746.75$
Subtotal Construction*1,753,635.06$
Overhead (22%)385,799.71$
Total Construction 2,139,434.77$
Estimate 4 lights @ $14,000 56,000.00$
2,195,430.00$ TOTAL PROJECT COST
Boulder Avenue Extension (2022-02) - Total Project
Cost
Construction
Street Light Installation
Overhead/Indirect Costs
Fund Amount
TIF Agreement 1,929,483$
Sanitary Sewer Core 60,042$
Water Core 36,576$
Storm Sewer Core 158,205$
Street Light Fund 11,128$
TOTAL PROJECT FUNDING 2,195,430$
Boulder Avenue Extension (2022-02) - Project Funding
Contractor Bid Amount
S. R. Weidema, Incorporated 1,753,635.06$ (88,920.94)$ -4.8%
Northwest 1,774,626.64$ (67,929.36)$ -3.7%
Engineer's Estimate 1,842,556.00$ -$ 0.0%
Northern Lines Contracting 1,917,715.15$ 75,159.15$ 4.1%
Ryan Contracting Co.1,943,348.20$ 100,792.20$ 5.5%
McNamara Contracting 1,996,135.60$ 153,579.60$ 8.3%
A-1 Excavating LLC 2,018,957.36$ 176,401.36$ 9.6%
Eureka Construction, Inc.2,034,152.05$ 191,596.05$ 10.4%
Kuechle Underground, Inc.2,043,845.36$ 201,289.36$ 10.9%
Miller Excavating, Inc.2,157,081.63$ 314,525.63$ 17.1%
S.M. Hentges & Sons, Inc.2,215,768.90$ 373,212.90$ 20.3%
RL Larson Excavating, Inc.2,264,476.38$ 421,920.38$ 22.9%
Douglas-Kerr Underground, LLC 2,274,367.65$ 431,811.65$ 23.4%
Geislinger & Sons 2,301,833.50$ 459,277.50$ 24.9%
Max Steininger, Inc.2,381,490.96$ 538,934.96$ 29.2%
Carl Bolander & Sons 2,433,785.75$ 591,229.75$ 32.1%
Difference
3
Schedule
Due to the late start for this project it is anticipated that the contractor will perform grading and begin
utility installation this fall; however, any surface improvements will be complete in 2023.
RECOMMENDATION
Staff recommends Council adoption of the attached resolutions approving:
1. Accepting the bids and awarding the construction contract to S.R. Weidema, Incorporated in the
amount of $1,753,635.06.
2. Authorizing the City of Rosemount to enter into a cooperative agreement with MnDOT for
construction along TH 3.
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2022-XX
A RESOLUTION RECEIVING BIDS AND AWARDING CONTRACT
FOR BOULDER AVENUE EXTENSION PROJECT,
CITY PROJECT 2022-02
BE IT RESOLVED, by the City Council of the City of Rosemount, Minnesota, as follows:
1. All bids for construction of the Boulder Avenue Extension Project, City Project 2022-02, are
hereby received and tabulated.
2. The bid of S.R. Weidema, Incorporated of Maple Grove, MN in the amount of $1,753,635.06
for the construction of said improvements is in accordance with the plans and specifications
and advertisement for bids and is the lowest responsible bid and shall be and hereby is
accepted.
3. The Mayor and Clerk are hereby authorized and directed to enter into a contract with said
bidder for the construction of said improvements for and on behalf of the City of Rosemount.
4. The City Clerk is hereby authorized and directed to return forthwith to all bidders the deposits
made with their bids, except that the deposit of the successful bidder and the next two lowest
bidders shall be retained until a contract has been executed.
ADOPTED this 4th day of October, 2022.
William H. Droste, Mayor
ATTEST:
Erin Fasbender, City Clerk
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2022-XX
A RESOLUTION AUTHORIZING THE CITY OF
ROSEMOUNT TO ENTER INTO A
COOPERATIVE AGREEMENT WITH MNDOT
BE IT RESOLVED, by the City Council of the City of Rosemount, Minnesota, as follows:
1. That the City of Rosemount enter into MnDOT Agreement No. 1051096 with the State of
Minnesota, Department of Transportation for the purpose of providing routine maintenance
by the City upon, along and adjacent to Trunk Highway No. 3, the limits of which are defined
in said agreement.
2. The Mayor and City Clerk are hereby authorized and directed to execute the Agreement and
any amendments to the Agreement.
ADOPTED this 4th day of October, 2022.
William H. Droste, Mayor
ATTEST:
Erin Fasbender, City Clerk
MnDOT Contract No.: 1051096
-1-
Construction within State R/W & Maintenance (Cooperative Agreements)
STATE OF MINNESOTA
DEPARTMENT OF TRANSPORTATION
AND
CITY OF ROSEMOUNT
COOPERATIVE CONSTRUCTION
AGREEMENT
State Project Number: 1921-117
Trunk Highway Number: 3=001
City Project Number: 2022-02
This Agreement is between the State of Minnesota, acting through its Commissioner of Transportation ("State") and
the City of Rosemount, acting through its City Council ("City").
Recitals
1. The City will perform grading, bituminous surfacing, curb and gutter, and municipal utilities construction and
other associated construction upon, along, and adjacent to Boulder Avenue from South Robert Trail (Trunk
Highway [TH] No. 3) to 1400 feet east of South Robert Street (TH 3) and on South Robert Street (TH 3) from
650 feet south of Boulder Avenue to 450 feet north of Boulder Avenue according to City-prepared plans,
specifications, and special provisions designated by the City as City Project No. 2022-02 and by the State as
State Project No. 1921-117 (TH 3=001) ("Project"); and
2. The City requests the State allow the construction of grading, bituminous surfacing, curb and gutter, and
municipal utilities on Trunk Highway Right-of-Way, and the State is willing to allow said construction; and
3. Minnesota Statutes § 161.20, subdivision 2 authorizes the Commissioner of Transportation to make
arrangements with and cooperate with any governmental authority for the purposes of constructing,
maintaining, and improving the trunk highway system.
Agreement
1. Term of Agreement; Survival of Terms; Plans; Incorporation of Exhibits
1.1. Effective Date. This Agreement will be effective on the date the State obtains all signatures required by
Minnesota Statutes § 16C.05, subdivision 2.
1.2. Expiration Date. This Agreement will expire when all obligations have been satisfactorily fulfilled.
1.3. Survival of Terms. All clauses which impose obligations continuing in their nature and which must survive
in order to give effect to their meaning will survive the expiration or termination of this Agreement,
including, without limitation, the following clauses: 2.4. State Ownership of Improvements;
5. Maintenance by the City; 8. Liability; Worker Compensation Claims; Insurance; 10. State Audits;
11. Government Data Practices; 12. Governing Law; Jurisdiction; Venue; and 14. Force Majeure.
1.4. Plans, Specifications, and Special Provisions. State-approved City plans, specifications, and special
provisions designated by the City as City Project No. 2022-02 and by the State as State Project
No. 1921-117 (TH 3=001)are on file in the office of the City's Engineer and incorporated into this
Agreement by reference ("Project Plans").
1.5. Exhibits. Exhibit "A" – Storm Sewer Maintenance Responsibilities is attached and incorporated into this
Agreement.
MnDOT Contract No.: 1051096
-2-
Construction within State R/W & Maintenance (Cooperative Agreements)
2. Right-of-Way Use
2.1. Limited Right to Occupy. The State grants to the City (and its contractors and consultants) the right to
occupy Trunk Highway Right-of-Way as necessary to perform the work described in the Project Plans. This
right is limited to the purpose of constructing the project, and administering such construction, and may
be revoked by the State at any time, with or without cause. Cause for revoking this right of occupancy
includes, but is not limited to, breaching the terms of this or any other agreement (relevant to this project)
with the State, failing to provide adequate traffic control or other safety measures, failing to perform the
construction properly and in a timely manner, and failing to observe applicable environmental laws or
terms of applicable permits. The State will have no liability to the City (or its contractors or consultants) for
revoking this right of occupancy.
2.2. State Access; Suspension of Work; Remedial Measures. The State's District Engineer or assigned
representative retains the right to enter and inspect the Trunk Highway Right-of-Way (including the
construction being performed on such right-of-way) at any time and without notice to the City or its
contractor. If the State determines (in its sole discretion) that the construction is not being performed in a
proper or timely manner, or that environmental laws (or the terms of permits) are not being complied
with, or that traffic control or other necessary safety measures are not being properly implemented, then
the State may notify and require the City (and its contractors and consultants) to suspend their operations
until the City (and its contractors and consultants) take all necessary actions to rectify the situation to the
satisfaction of the State. The State will have no liability to the City (or its contractors or consultants) for
exercising or failing to exercise its rights under this provision.
2.3. Traffic Control; Worker Safety. While the City (and its contractors and consultants) are occupying the
State's Trunk Highway Right-of-Way, they must comply with the approved traffic control plan, and with
applicable provisions of the Work Zone Field Handbook
(http://www.dot.state.mn.us/trafficeng/workzone/index.html). All City, contractor, and consultant
personnel occupying the State's Trunk Highway Right-of-Way must be provided with required reflective
clothing and hats.
2.4. State Ownership of Improvements. The State will retain ownership of its Trunk Highway Right-of-Way,
including any improvements made to such right-of-way under this Agreement, unless otherwise noted.
The warranties and guarantees made by the City's contractor with respect to such improvements (if any)
will flow to the State. The City will assist the State, as necessary, to enforce such warranties and
guarantees, and to obtain recovery from the City's consultants, and contractor (including its sureties) for
non-performance of contract work, for design errors and omissions, and for defects in materials and
workmanship. Upon request of the State, the City will undertake such actions as are reasonably necessary
to transfer or assign contract rights to the State and to permit subrogation by the State with respect to
claims against the City's consultants and contractors.
3. Contract Award and Construction
3.1. Direction, Supervision, and Inspection of Construction.
A. The contract construction will be under the direction of the City and under the supervision of a
registered professional engineer; however, the State participation construction covered under this
Agreement will be open to inspection by the State District Engineer's authorized representatives. The
City will give the State Aid Agreements Engineer at Roseville five days' notice of its intention to start the
contract construction.
MnDOT Contract No.: 1051096
-3-
Construction within State R/W & Maintenance (Cooperative Agreements)
B. Responsibility for the control of materials for the contract construction will be on the City and its
contractor and will be carried out according to Specifications No. 1601 through and including No. 1609
in the State's current "Standard Specifications for Construction".
3.2. Completion of Construction. The City will cause the contract construction to be started and completed
according to the time schedule in the construction contract special provisions. The completion date for the
contract construction may be extended, by an exchange of letters between the appropriate City official
and the State District Engineer's authorized representative, for unavoidable delays encountered in the
performance of the contract construction.
3.3. Compliance with Laws, Ordinances, and Regulations. The City will comply and cause its contractor to
comply with all Federal, State, and Local laws, and all applicable ordinances and regulations. With respect
only to that portion of work performed on the State's Trunk Highway Right-of-Way, the City will not
require the contractor to follow local ordinances or to obtain local permits.
4. Right-of-Way; Easements; Permits
4.1. The City will, without cost or expense to the State, obtain all rights-of-way, easements, construction
permits, and any other permits and sanctions that may be required in connection with the local and trunk
highway portions of the contract construction.
4.2. The City will convey to the State by quit claim deed, all newly acquired rights needed for the continuing
operation and maintenance of the Trunk Highway, if any, upon completion of the Project, at no cost or
expense to the State.
4.3. The City will comply with Minnesota Statutes § 216D.04, subdivision 1(a), for identification, notification,
design meetings, and depiction of utilities affected by the contract construction.
4.4. The City will submit to the State's Utility Engineer an original permit application for all utilities owned by
the City to be constructed upon and within the Trunk Highway Right-of-Way. Applications for permits will
be made on State form "Application for Utility Permit on Trunk Highway Right-of-Way" (Form 2525).
4.5. The City will submit to the Minnesota Pollution Control Agency the plans and specifications for the
construction or reconstruction of its sanitary sewer facilities to be performed under the construction
contract and obtain, under Minnesota Statutes § 115.07 or Minnesota Rules 7001.1030, subpart 2C, either
a permit or written waiver from that agency for that construction or reconstruction. The City is advised
that under Minnesota Rules 7001.1040, a written application for the permit or waiver must be submitted
to the Minnesota Pollution Control Agency at least 180 days before the planned date of the sanitary sewer
facility construction or reconstruction.
5. Maintenance by the City
Upon completion of the project, the City will provide the following without cost or expense to the State:
5.1. Storm Sewers. Routine maintenance of storm sewer facilities construction as shown on Exhibit "A" – Storm
Sewer Maintenance Responsibilities. Routine maintenance includes, but is not limited to, removal of
sediment, debris, vegetation and ice from grates and catch basins, and any other maintenance activities
necessary to preserve the facilities and to prevent conditions such as flooding, erosion, or sedimentation,
this also includes informing the District Maintenance Engineer of any needed repairs.
5.2. Municipal Utilities. Maintenance of any municipal-owned utilities construction, without cost or expense to
the State.
MnDOT Contract No.: 1051096
-4-
Construction within State R/W & Maintenance (Cooperative Agreements)
5.3. Sidewalks. Maintenance of any sidewalk construction, including stamped and colored concrete sidewalk (if
any) and pedestrian ramps. Maintenance includes, but is not limited to, snow, ice, and debris removal,
patching, crack repair, panel replacement, cross street pedestrian crosswalk markings, vegetation control
of boulevards (if any), and any other maintenance activities necessary to perpetuate the sidewalks in a
safe, useable, and aesthetically acceptable condition.
5.4. Additional Drainage. No party to this Agreement will drain any additional drainage volume into the storm
sewer facilities constructed under the construction contract that was not included in the drainage for
which the storm sewer facilities were designed, without first obtaining written permission to do so from
the other party.
6. Authorized Representatives
Each party's Authorized Representative is responsible for administering this Agreement and is authorized to give
and receive any notice or demand required or permitted by this Agreement.
6.1. The State's Authorized Representative will be:
Name, Title: Malaki Ruranika, Cooperative Agreements Engineer (or successor)
Address: 395 John Ireland Boulevard, Mailstop 682, St. Paul, MN 55155
Telephone: (651) 366-4634
Email: malaki.ruranika@state.mn.us
6.2. The City's Authorized Representative will be:
Name, Title: Brian Erickson, City Engineer (or successor)
Address: 2875 145th Street West, Rosemount, MN 55068
Telephone: (651) 322-2025
Email: brian.erickson@ci.rosemount.mn.us
7. Assignment; Amendments; Waiver; Contract Complete
7.1. Assignment. No party may assign or transfer any rights or obligations under this Agreement without the
prior consent of the other party and a written assignment agreement, executed and approved by the same
parties who executed and approved this Agreement, or their successors in office.
7.2. Amendments. Any amendment to this Agreement must be in writing and will not be effective until it has
been executed and approved by the same parties who executed and approved the original Agreement, or
their successors in office.
7.3. Waiver. If a party fails to enforce any provision of this Agreement, that failure does not waive the
provision or the party's right to subsequently enforce it.
7.4. Contract Complete. This Agreement contains all prior negotiations and agreements between the State and
the City. No other understanding regarding this Agreement, whether written or oral, may be used to bind
either party.
8. Liability; Worker Compensation Claims; Insurance
8.1. Each party is responsible for its own acts, omissions, and the results thereof to the extent authorized by
law and will not be responsible for the acts, omissions of others, and the results thereof. Minnesota
Statutes § 3.736 and other applicable law govern liability of the State. Minnesota Statutes Chapter 466 and
other applicable law govern liability of the City. Notwithstanding the foregoing, the City will indemnify,
hold harmless, and defend (to the extent permitted by the Minnesota Attorney General) the State against
any claims, causes of actions, damages, costs (including reasonable attorneys fees), and expenses arising in
MnDOT Contract No.: 1051096
-5-
Construction within State R/W & Maintenance (Cooperative Agreements)
connection with the project covered by this Agreement, regardless of whether such claims are asserted by
the City's contractor(s) or consultant(s) or by a third party because of an act or omission by the City or its
contractor(s) or consultant(s).
8.2. Each party is responsible for its own employees for any claims arising under the Workers Compensation
Act.
8.3. The City may require its contractor to carry insurance to cover claims for damages asserted against the
City's contractor.
9. Nondiscrimination
Provisions of Minnesota Statutes § 181.59 and of any applicable law relating to civil rights and discrimination are
considered part of this Agreement.
10. State Audits
Under Minnesota Statutes § 16C.05, subdivision 5, the City's books, records, documents, accounting procedures,
and practices relevant to this Agreement are subject to examination by the State and the State Auditor or
Legislative Auditor, as appropriate, for a minimum of six years from the end of this Agreement.
11. Government Data Practices
The City and State must comply with the Minnesota Government Data Practices Act, Minnesota Statutes
Chapter 13, as it applies to all data provided under this Agreement, and as it applies to all data created,
collected, received, stored, used, maintained, or disseminated by the City under this Agreement. The civil
remedies of Minnesota Statutes §13.08 apply to the release of the data referred to in this clause by either the
City or the State.
12. Governing Law; Jurisdiction; Venue
Minnesota law governs the validity, interpretation, and enforcement of this Agreement. Venue for all legal
proceedings arising out of this Agreement, or its breach, must be in the appropriate state or federal court with
competent jurisdiction in Ramsey County, Minnesota.
13. Termination; Suspension
13.1. By Mutual Agreement. This Agreement may be terminated by mutual agreement of the parties or by the
State for insufficient funding as described below.
13.2. Termination for Insufficient Funding. The State may immediately terminate this Agreement if it does not
obtain funding from the Minnesota Legislature, or other funding source; or if funding cannot be continued
at a level sufficient to allow for the payment or the provision of the services covered here. Termination
must be by written or fax notice to the City. The State will not be assessed any penalty if this Agreement is
terminated because of the decision of the Minnesota Legislature, or other funding source, not to
appropriate funds.
13.3. Suspension. In the event of a total or partial government shutdown, the State may suspend this
Agreement and all work, activities, performance, and payments authorized through this Agreement.
14. Force Majeure
No party will be responsible to the other for a failure to perform under this Agreement (or a delay in
performance), if such failure or delay is due to a force majeure event. A force majeure event is an event beyond
a party's reasonable control, including but not limited to, unusually severe weather, fire, floods, other acts of
God, labor disputes, acts of war or terrorism, or public health emergencies.
MnDOT Contract No.: 1051096
-6-
Construction within State R/W & Maintenance (Cooperative Agreements)
CITY OF ROSEMOUNT
The undersigned certify that they have lawfully
executed this contract on behalf of the Governmental
Unit as required by applicable charter provisions,
resolutions, or ordinances.
By:
Title:
Date:
By:
Title:
Date:
DEPARTMENT OF TRANSPORTATION
Recommended for Approval:
By:
(District Engineer)
Date:
Approved:
By:
(State Design Engineer)
Date:
COMMISSIONER OF ADMINISTRATION
By:
(With Delegated Authority)
Date:
INCLUDE COPY OF RESOLUTION APPROVING THE AGREEMENT AND AUTHORIZING ITS EXECUTION.
|
|
|
|
|
|
|
|
|||||||||||||||||||||||
>>
>
>
>
>
>
OE
OE
OE
OE OE OE OE OE OE OE OE OE OE OE OE OE OE
C
C
C
C
C C C C C C C C C C C C C C
>>>>>>>>>>>>>>>>>>>>>>
>>
>>
>>
>>
>>
>>
>>
|
|
>>>>>>
>>
>>
>>
>>
>>
910
920
930
940
950
960
970
980
990
910
920
930
940
950
960
970
980
990
SCALE IN FEET
0
H:
30 60
SCALE IN FEET
0
V:
10 20
>>
>>
DTL
>>
>>>>>>
>>
Exhibit "A" - Storm Sewer Maintenance Responsibilities
SP 1921-117, Agreement # 1051096, Page 1 of 1
[ ] - State
[ ] - City of Rosemount
Note: Any storm sewer drainage structure not shown in
this exhibit is City of Rosemount responsibility.
[]
[
CITY OF ROSEMOUNT
RESOLUTION
IT IS RESOLVED that the City of Rosemount enter into MnDOT Agreement No. 1051096 with the State of Minnesota,
Department of Transportation for the following purposes:
To provide for routine maintenance by the City upon, along, and adjacent to Trunk Highway No. 3, the limits of
which are defined in said Agreement.
IT IS FURTHER RESOLVED that the Mayor and the
(Title)
are authorized to execute the Agreement and any amendments to the Agreement.
CERTIFICATION
I certify that the above Resolution is an accurate copy of the Resolution adopted by the Council of the City of
Rosemount at an authorized meeting held on the day of
, 2022, as shown by the minutes of the meeting in my possession.
Subscribed and sworn to me this
day of , 2022
Notary Public
My Commission Expires
(Signature)
(Type or Print Name)
(Title)
PROJECT:
SP 1921-117 TH 3
OWNER:
City of Rosemount, MN
WSB PROJECT NO.: 018351-000
City Project No. 2022-02
Bids Opened: Tuesday, September 13, 2022 at 10:00 a.m.
Contractor Bid Security (5%)
Add. No. 1
Rec'd.Add. No. 2 Rec'd.Grand Total Bid
1 S R Weidema, Incorporated X X X $1,753,635.06
2 Northwest X X X $1,774,626.64
3 Northern Lines Contracting X X X $1,917,715.15
4 Ryan Contracting Co.X X X $1,943,348.20
5 McNamara Contracting X X X $1,996,135.60
6 A-1 Excavating LLC X X X $2,018,957.36
7 Eureka Construction, Inc.X X X $2,034,152.05
8 Kuechle Underground Inc.X X X $2,043,845.36
9 Miller Excavating, Inc.X X X $2,157,081.63
10 S.M. Hentges & Sons, Inc.X X X $2,215,768.90
11 RL Larson Excavating Inc.X X X $2,264,476.38
12 Douglas-Kerr Underground, L.L.C X X X $2,274,367.65
13 Geislinger & Sons X X X $2,301,833.50
14 Max Steininger, Inc.X X X $2,381,490.96
15 Carl Bolander & Sons X X X $2,433,785.75
Engineer's Opinion of Cost $1,842,556.00
Denotes corrected figure
Timothy C. Hanson, PE Project Manager
BID TABULATION SUMMARY
I hereby certify that this is a true and correct tabulation of the bids as received on September 13, 2022.
Boulder Avenue Street and Utility Extension
K:\018351-000\Admin\Construction Admin\Bidding\018351-000 Bid Tab Summary 09152022
K:\018351-000\Admin\Construction Admin\Bidding\018351-000 LOR - 09152022.docx
1
7
8
E
9
T
H
S
T
R
E
E
T
|
S
U
I
T
E
2
0
0
|
S
A
I
N
T
P
A
U
L
,
M
N
|
5
5
1
0
1
|
6
5
1
.
2
8
6
.
8
4
5
0
|
W
S
B
E
N
G
.
C
O
M
September 15, 2022
Honorable Mayor and City Council
City of Rosemount
2875 145th Street West
Rosemount, MN 55068
Re: Boulder Avenue Street and Utility Extension
SP 1921-117 TH 3
City of Rosemount, MN Project No. 2022-02
WSB Project No. 018351-000
Dear Mayor and Council Members:
Bids were received for the above-referenced project on Tuesday, September 13, 2022, and were
opened and read aloud. Fifteen bids were received. The bids were checked for mathematical
accuracy. Please find enclosed the bid summary indicating the low bid as submitted by S.R.
Weidema, Incorporated, Maple Grove, Minnesota in the amount of $1,753,635.06. The
Engineer’s Estimate was $1,842,556.00.
We recommend that the City Council consider these bids and award a contract in the amount of
$1,753,635.06 to S.R. Weidema, Incorporated based on the results of the bids received.
Sincerely,
WSB
Timothy Hanson, PE
Project Manager
Attachments
cc: Brian Erickson, City of Rosemount
Tim Hanson, WSB
tmw
1
0
+
0
0
1
1
+
0
0
1
2
+
0
0
1
3
+
0
0
14
+
0
0
15
+
0
0
16
+
0
0
17
+
0
0
1
8
+
0
0
1
9
+
0
0
2
0
+
0
0
2
1
+
0
0
22+
0
0
23+00 24+00 25+00 26+00 27+00 28+00 29+00 30+00 31+00 32+00 33+00 34+00 35+00 36+00 37+00 38+00 39+00 40+00 41+0041+41
WSB PROJECT NO.:
K:
\
0
1
7
0
2
2
-
0
0
0
\
C
a
d
\
E
x
h
i
b
i
t
s
\
0
1
7
0
2
2
-
0
0
0
-
F
I
G
-
1
.
d
w
g
3/
1
8
/
2
0
2
1
1
0
:
4
2
:
1
8
A
M
017022-000
BOULDER AVENUE EXTENSION
FIGURE 3
ROSEMOUNT, MINNESOTA SCALE IN FEET
0 100 200
N
BOULDER AVENUE
SOUT
H
R
O
B
E
R
T
T
R
A
I
L
R 400'
R 400'
R 400'
80' ROW
80' ROW
AREA: 56,741 SF
CA
N
A
D
A
C
O
U
R
T